Accelerate procedures for building 35 resettlement areas for high-speed railway projects in Ha Tinh

TRẦN TUẤN |

Ha Tinh - The Department of Construction has just reported and requested localities to expedite relevant dossiers and procedures to soon build resettlement areas for high-speed railway projects.

According to reports, the North-South high-speed railway project is expected to pass through 18 communes and 5 wards of Ha Tinh with a total length of about 103.42 km.

Through preliminary review results, to date, the project is expected to recover about 764.12 hectares of land, affecting about 1,800 households with residential land, of which nearly 1,300 households must be relocated and resettled; exhuming thousands of graves.

Ha Tinh province has 35 resettlement areas of the North-South high-speed railway project in 18 communes and wards. To date, 34/35 resettlement areas have completed planning approval.

With 34 resettlement areas that have been approved for planning, 1 resettlement area in Lien Vinh residential group, Ha Huy Tap ward has been constructed with a volume of about 51.5%; 1 area in Cam Hung commune does not need to prepare design dossiers; 28 areas have completed preliminary design dossiers and have been sent to the Department of Construction; 4 areas have been approved for planning and are preparing design dossiers.

Ra soat pham vi anh huong cua du an duong sat Bac - Nam toc do cao tai xa Duc Quang, tinh Ha Tinh. Anh: Quang Tuan.
Reviewing the scope of impact of the North-South high-speed railway project in Duc Quang commune, Ha Tinh province. Photo: Quang Tuan

To ensure the progress of construction of resettlement areas to meet the requirements of the project, the Department of Construction proposed that the Ha Tinh Provincial People's Committee direct to soon unify the authority to decide on investment in resettlement areas.

Ky Van commune accelerates the completion and approval of the resettlement area plan; localities that have resettlement areas approved for planning but have not completed the design need to soon complete the survey and design dossiers of the resettlement area for inspection, consideration, and guidance.

For communes and wards that have sent design dossiers to the Department of Construction, it is necessary to urgently direct design consulting units to receive, revise, and supplement according to the opinions of the Department of Construction and the Department of Industry and Trade, ensuring progress and technical standards according to regulations.

The Department of Finance continues to coordinate with the State Treasury, relevant units and localities to complete the opening of account codes to receive capital for project site clearance.

The Department of Agriculture and Environment coordinates with the investor and the People's Committees of relevant localities to review and prepare ready sources of construction materials, and plan for waste disposal locations, ensuring to meet project implementation progress requirements.

TRẦN TUẤN
RELATED NEWS

Hoa Cuong wholesale market is deteriorating, Da Nang speeds up replacement projects

|

Da Nang - Faced with the situation of many long-standing traditional markets being degraded, Da Nang is implementing a comprehensive plan to build new and renovate the market system.

Quang Ngai accelerates social housing projects, supports workers

|

To turn the dream of settling down for tens of thousands of workers into reality, Quang Ngai province is implementing many support policies while accelerating social housing projects.

Gia Lai supports to accelerate the Pleiku 2 - Krong Buk 220kV transmission line project

|

Gia Lai - The early site clearance will speed up the 220kV Pleiku 2 - Krong Buk transmission line project (line 2) to increase the quality of electricity on the grid.

Real Madrid drops important points in La Liga

|

In the early morning of April 11 (Vietnam time), Real Madrid was held to a 1-1 draw by Girona in La Liga and faced the risk of Barcelona widening the gap in points.

Promulgating the Resolution of the 16th National Assembly on personnel work

|

Politburo Member, National Assembly Chairman Tran Thanh Man signed and promulgated a Resolution electing the Chairman of the Ethnic Council, Chairman of the Committee of the 16th National Assembly.

Orion spacecraft lands safely, ending Artemis II mission

|

The Orion spacecraft of the Artemis II mission has brought 4 astronauts back to Earth safely after a 10-day flight.

Gasoline and oil prices today 11:4: Simultaneously sharply decrease

|

Gasoline and oil prices today 11:4: World oil prices fell sharply. WTI oil fell below 97 USD/barrel; Brent oil reached 95 USD/barrel.

Announcing decisions on personnel work in Hai Phong, Hung Yen, Can Tho

|

Hai Phong, Hung Yen, Can Tho, Ho Chi Minh City, Dong Nai provinces/cities... have implemented and announced decisions on personnel work.

Hoa Cuong wholesale market is deteriorating, Da Nang speeds up replacement projects

Nguyễn Linh - Thanh Huyền |

Da Nang - Faced with the situation of many long-standing traditional markets being degraded, Da Nang is implementing a comprehensive plan to build new and renovate the market system.

Quang Ngai accelerates social housing projects, supports workers

Viên Nguyễn |

To turn the dream of settling down for tens of thousands of workers into reality, Quang Ngai province is implementing many support policies while accelerating social housing projects.

Gia Lai supports to accelerate the Pleiku 2 - Krong Buk 220kV transmission line project

THANH TUẤN |

Gia Lai - The early site clearance will speed up the 220kV Pleiku 2 - Krong Buk transmission line project (line 2) to increase the quality of electricity on the grid.