Dialogue on site clearance for the Vu Yen island access road project, Hai Phong

Hoàng Khôi |

Hai Phong - On September 10, Thuy Nguyen ward organized a dialogue with households subject to land acquisition coercion to implement the Vu Yen island road project.

The investment project to build the road from Bac Song Cam urban area to VSIP Industrial Park road to Vu Yen island is about 2.44 km long, the roadbed is 36 m wide, and synchronously invests in drainage, electricity supply, lighting and bridges on the route. This is a key traffic infrastructure project of Hai Phong city, which is of great significance in completing the traffic network in the Bac Song Cam area, strengthening the connection of the new Political - Administrative Center with Vu Yen island, industrial parks and large-scale urban, service and tourism areas that are being formed.

The project implementation contributes to gradually completing the transport infrastructure system in Thuy Nguyen area, improving connectivity between regions, creating favorable conditions for traffic, attracting investment, and creating motivation to promote socio-economic development of the locality.

Regarding site clearance, functional agencies fully implemented the steps from implementing land recovery notices, inventorying, determining the origin of land; preparing, publicizing and approving compensation, support, and resettlement plans in accordance with regulations.

To date, 132 households have handed over land; and 8 households have not agreed to hand over land with a total recovered area of about 2,000 m2.

At the dialogue, 8 households continued to propose some contents related to arranging more or allocating resettlement to family members; re-measuring the area and reviewing the origin of land to enjoy higher compensation policies... Opinions were directly answered based on legal regulations.

Concluding the conference, leaders of Thuy Nguyen ward acknowledged and highly appreciated the consensus of most households in implementing the project. At the same time, they affirmed that the Party Committee and local authorities always determine that site clearance work must be carried out publicly, transparently, and objectively; and at the same time, maximize support policies within the scope of law to ensure the legitimate and lawful rights and interests of the people.

To complete site clearance in September 2026, local authorities request households to uphold their sense of responsibility, strictly comply with the land acquisition decisions issued and soon hand over the site so that the Project can be implemented on schedule.

In case people have additional valuable papers and documents proving their origin, land use process, and legitimate rights of their families, they need to provide them to the local authorities before the enforcement date for consideration and resolution.

In case households still do not agree to hand over the land, Thuy Nguyen ward will develop a plan and organize land recovery coercion before September 20.

Hoàng Khôi
RELATED NEWS

Nearly 80 billion VND flower garden in Hai Phong just inaugurated and has to be repaired

|

Hai Phong - Inaugurated in May 2026, to date, many items at Hanh Phuc Lake flower garden (Kien An ward) have shown signs of degradation and must be repaired and replaced.

Payment of 41.1 billion VND for compensation for the road project connecting 2 national highways in Hai Phong

|

Hai Phong - Kien An Ward has just paid 41.1 billion VND to 31 households whose land is recovered to implement the project to invest in building a road connecting National Highway 5 with National Highway 10.

Case of former principal collecting 15,000 VND/extra class: Controversy over documents as a basis for prosecution

|

The case of former Principal of Ba Dinh Secondary School Nguyen Thi Binh being tried for collecting 15,000 VND/extra class, lawyers request reconsideration.

Students crossing the Cau River to school by specialized canoe: Ferry wharf will be reopened

|

Thai Nguyen - Reopening the ferry wharf will help students and people easily move back and forth across both banks of the river.

Houthi forces suffer more than 40 airstrikes from Saudi Arabia

|

The spiral of air retaliation between Saudi Arabia and rebels in Yemen is heating up, leading to the risk of a full-scale war recurring.

AI use still has to be responsible for content and copyright

|

According to Deputy Minister of Culture, Sports and Tourism Nguyen Huy Dung, individuals using AI are still responsible for content, copyright, and risk control.

Bao Loc Pass paved with asphalt after a dense reflection of potholes by Lao Dong Newspaper

|

Lam Dong - After Lao Dong Newspaper's reflection on hundreds of potholes and buffalo pits on the top of Bao Loc pass, the management unit has asphalted and repaired the damage.

Nearly 80 billion VND flower garden in Hai Phong just inaugurated and has to be repaired

Hoàng Khôi |

Hai Phong - Inaugurated in May 2026, to date, many items at Hanh Phuc Lake flower garden (Kien An ward) have shown signs of degradation and must be repaired and replaced.

Công an phối hợp giải quyết vụ khiếu kiện kéo dài hơn 30 năm ở Tiên Lãng, Hải Phòng

Theo Công an TP Hải Phòng |

Hải Phòng - Phòng An ninh nội địa chủ động tham mưu, phối hợp giải quyết dứt điểm vụ việc khiếu kiện kéo dài tại xã Tiên Lãng.

Payment of 41.1 billion VND for compensation for the road project connecting 2 national highways in Hai Phong

Theo Cổng TTĐT phường Kiến An, Hải Phòng |

Hai Phong - Kien An Ward has just paid 41.1 billion VND to 31 households whose land is recovered to implement the project to invest in building a road connecting National Highway 5 with National Highway 10.