Dung Quat - Sa Huynh coastal road project in Quang Ngai stagnates due to people not allocating land

VIÊN NGUYỄN |

Quang Ngai - The deadline is approaching, but the Dung Quat - Sa Huynh coastal road project phase IIb is still struggling because many households have not yet handed over the site.

The Dung Quat - Sa Huynh coastal road project, phase IIb, has a total investment of nearly VND900 billion, with a route length of more than 16.2 km. The project is invested by the Quang Ngai Provincial Traffic Construction Investment Project Management Board, with implementation period from 2022 to 2025.

Although the deadline for completion is approaching, the project is struggling due to land clearance problems because many households have not yet refused to hand over land.

According to the Quang Ngai Provincial Land Fund Development Center, the total planned area for the project is more than 9 hectares. Currently, there are 7 households in the section through Tinh Hoa commune that have not agreed to be inventoried and signed documents; these households request to be allocated resettlement land before inventorying and making compensation and support plans.

Currently, the Quang Ngai Provincial Land Fund Development Center is coordinating with the Commune People's Committee to organize and mobilize households to coordinate in land inventory work to have a basis to implement the next steps.

In case the household does not agree, it is recommended that the Commune People's Committee report to the Center so that it has a basis to submit to the competent authority to issue a Decision on compulsory inventory according to the provisions of Article 88 of the 2024 Land Law. The expected time to complete and approve the compensation, support and resettlement plan is in the third quarter of 2025.

For the section passing through Dong Son commune: In case the household of Ms. Bui Thi Chang and Ms. Vo Thi Nu had their land partially reclaimed, the remaining land was at the foot of T6 bridge (Chau Me Dong bridge), the household owner proposed to also reclaim the remaining land area. However, currently, the People's Committee of Binh Son district (old) has not had a consensus on the area reclaimed outside the planning.

For the remaining 2 cases that have not been unified in the statistics in the section through Binh Chau commune, the Center is currently coordinating with the locality to organize a campaign.

The remaining project planning area is residential land, which has just been issued specific land prices by the People's Committee of Quang Ngai City (old) and the People's Committee of Binh Son District (old). Currently, the Center is preparing a plan and submitting it for approval according to regulations.

The Quang Ngai Provincial Land Fund Development Center proposed that the People's Committee of Binh Son District (old) give opinions on 2 cases of land recovery outside the planning so that the Center has a basis to develop a land recovery plan and soon issue a decision to enforce land recovery for 8 households that do not agree to receive money and hand over the site.

It is expected that there will be a working session with the People's Committees of Dong Son and Tinh Hoa communes to continue to organize and mobilize households to coordinate in inventorying and signing documents to complete the next legal procedures.

The People's Committees of Tinh Hoa and Dong Son communes continue to mobilize households that have not received compensation and support and hand over the site so that investors can soon implement the project.

VIÊN NGUYỄN
TIN LIÊN QUAN

The 3,500 billion VND project in Quang Ngai faces difficulties in developing compensation plans

|

Quang Ngai - The Hoang Sa - Doc Soi road project is facing great difficulties in the work of developing a compensation plan, leading to the risk of being behind schedule.

Quang Ngai faces a huge wave of investment after merging with Kon Tum

|

After the merger, Quang Ngai promises to accelerate with many strategic projects such as high-speed railway, inter-regional highway, Ly Son airport...

An intersection connecting the Da Nang - Quang Ngai expressway will be completed in December 2025

|

Responding to voters in Quang Ngai, the Ministry of Construction said that an intersection connecting to the Da Nang - Quang Ngai expressway will be completed in December 2025.

Horsemen on the A80 parade training ground

|

In the midst of the hot weather, the Cavalry Mobile Police formation still practiced tirelessly, ready for the A80 parade mission.

Chairman of Khanh Hoa province directs inspection of the Quan Truong river leveling case

|

Khanh Hoa - Chairman of the Provincial People's Committee directs inspection and handling of violations if there is a case of leveling the Quan Truong River in Nha Trang that Lao Dong Newspaper has reported.

EU announces plan to impose US retaliatory tariffs

|

The EU has proposed retaliatory measures after President Donald Trump threatened to impose a 30% tariff on Europe.

President Zelensky nominates new Ukrainian Prime Minister

|

On July 14, Ukrainian President Volodymyr Zelensky officially nominated Economic Minister Yulia Svyrydenko as the new Prime Minister.

Look up the fastest high school graduation exam scores in 2025 on Lao Dong

|

The 2025 high school graduation exam scores will be announced by the Ministry of Education and Training at 8:00 a.m. on July 16. Candidates can look up the fastest exam scores on Lao Dong.

The 3,500 billion VND project in Quang Ngai faces difficulties in developing compensation plans

viên nguyễn |

Quang Ngai - The Hoang Sa - Doc Soi road project is facing great difficulties in the work of developing a compensation plan, leading to the risk of being behind schedule.

Quang Ngai faces a huge wave of investment after merging with Kon Tum

VIÊN NGUYỄN |

After the merger, Quang Ngai promises to accelerate with many strategic projects such as high-speed railway, inter-regional highway, Ly Son airport...

An intersection connecting the Da Nang - Quang Ngai expressway will be completed in December 2025

Xuyên Đông |

Responding to voters in Quang Ngai, the Ministry of Construction said that an intersection connecting to the Da Nang - Quang Ngai expressway will be completed in December 2025.