The 3,500 billion VND project in Quang Ngai faces difficulties in developing compensation plans

viên nguyễn |

Quang Ngai - The Hoang Sa - Doc Soi road project is facing great difficulties in the work of developing a compensation plan, leading to the risk of being behind schedule.

The Hoang Sa - Doc Soi road project has a route length of 26.88 km with a total investment of VND 3,500 billion, of which the central budget is VND 1,300 billion and the provincial budget is VND 2,200 billion (from land use fee revenue). The project is invested by the Quang Ngai Provincial Traffic Construction Investment Project Management Board, with implementation period from 2022 to 2027.

According to the Quang Ngai Provincial Land Fund Development Center, the Hoang Sa - Doc Soi road project through the old Quang Ngai city has a length of 7.36 km. Currently, the inventory work with 42.79 ha/770 households and 6 organizations 1,520 plots of land has been basically completed (reaching 99.4% of the total area). The remaining 10 plots of land/10 households/0.24 ha in Tinh An commune (old) have not been surveyed and inventoried (10 households have not yet identified the land user, and are completing mandatory procedures for inventory).

Thi cong hang muc cau tai du an duong Hoang Sa - Doc Soi. Anh: Vien Nguyen
Construction of the bridge item at the Hoang Sa - Doc Soi road project. Photo: Vien Nguyen

To date, the People's Committee of Quang Ngai City (old) has approved 22 compensation plans with a total area of 20.62 hectares (reaching 47.9% of the total area).

Most households with land have agreed to receive money and hand over the land. However, currently, Truong Quang Trong ward still has 14 households that have not received money due to not completing inheritance procedures; 16 households do not agree to receive money. The People's Committee of Truong Quang Trong Ward has submitted a document requesting the competent authority to issue a decision to enforce the implementation of the land recovery decision.

Currently, the remaining 22.42 hectares (accounting for 52.1% of the total area) have not had their compensation plan approved. The reason is that 3.44 hectares of residential land do not have resettlement areas (except for land plots on the frontage of National Highway 24 and Hoang Sa Street).

1.75 hectares of cemetery land do not have a burial area, so the People's Committee of Quang Ngai city (old) has no basis to approve the compensation plan.

1.1 hectares of agricultural land have graves but there are no burial areas, leading to the inability to establish and approve compensation plans.

Faced with the above difficulties, the Provincial Land Fund Development Center requested the investor to coordinate with the People's Committee of Truong Quang Trong Ward and the Center to hand over the notice of land recovery to households, individuals and organizations whose land was recovered.

At the same time, it is necessary to speed up the arrangement of a burial area for relatives in Truong Quang Trong ward so that the Center has a basis to prepare a compensation plan and submit it for approval according to regulations.

viên nguyễn
TIN LIÊN QUAN

Quang Ngai faces a huge wave of investment after merging with Kon Tum

|

After the merger, Quang Ngai promises to accelerate with many strategic projects such as high-speed railway, inter-regional highway, Ly Son airport...

The third largest mountain tunnel in the country on the Quang Ngai - Hoai Nhon expressway has been dug

|

tunnel No. 3, part of the Quang Ngai - Hoai Nhon expressway component project, has been dug. When completed, this will be the third largest mountain tunnel in the country.

Duyet plans to invest in two urban projects worth VND54,000 billion, including an 18-hole golf course in Quang Ngai

|

The Deputy Prime Minister has just approved the investment policy for two urban projects in Quang Ngai with a total investment of more than 54,000 billion VND.

Fire at a grocery store signboard and then spread to a fried chicken shop in Ho Chi Minh City

|

HCMC - The hang at Ly Thai To roundabout suddenly caught fire, then spread to the fried chicken restaurant next door.

Verifying the case of students paying for martial arts classes to get exercise in Dak Lak

|

Dak Lak - The provincial Department of Education and Training directed Phan Dang Luu High School to verify parents' feedback about students paying for martial arts classes to achieve physical education.

The Ministry of Health proposes cash or in-kind support for families with one child, two daughters

|

The Ministry of Health proposes to give preferential maternity leave, cash or in kind support when giving birth to one child, two daughters.

Building the North-South high-speed railway, Hanoi Chairman assigns tasks to the Secretaries of communes and wards

|

The Chairman of Hanoi believes that the Party Secretaries of the communes must be the head of the commune's steering committee for site clearance to implement the North-South high-speed railway project.

Mr. Trump announces that all tariffs will be imposed on trading partners

|

Mr. Trump has announced that he will impose a Joint Stock tariff (blanket tariff) of 15-20% on most of the remaining US trading partners.

Quang Ngai faces a huge wave of investment after merging with Kon Tum

VIÊN NGUYỄN |

After the merger, Quang Ngai promises to accelerate with many strategic projects such as high-speed railway, inter-regional highway, Ly Son airport...

The third largest mountain tunnel in the country on the Quang Ngai - Hoai Nhon expressway has been dug

VIÊN NGUYỄN |

tunnel No. 3, part of the Quang Ngai - Hoai Nhon expressway component project, has been dug. When completed, this will be the third largest mountain tunnel in the country.

Duyet plans to invest in two urban projects worth VND54,000 billion, including an 18-hole golf course in Quang Ngai

VIÊN NGUYỄN |

The Deputy Prime Minister has just approved the investment policy for two urban projects in Quang Ngai with a total investment of more than 54,000 billion VND.