The 2,000 billion VND coastal road in Khanh Hoa is slow due to land clearance problems and low disbursement

Hữu Long |

Khanh Hoa - The coastal road worth more than VND2,000 billion is at risk of being behind schedule due to difficulties in site clearance and lack of materials.

On May 23, the Van Phong Economic Zone Management Board (KKT) said that the site clearance progress for the construction of the coastal road project from Van Luong commune (Van Ninh district) to Ninh Hoa town is taking place very slowly, affecting the construction organization plan.

The project also faces difficulties in terms of filling materials because minerals at mines in the area are increasingly depleted and do not meet demand.

In 2025, the project was allocated 400 billion VND from the central budget, however, by mid-May, the disbursement value had only reached nearly 30 billion VND (more than 7.3%).

Due to lack of land, contractors are currently constructing the M1 abutment, casting girders for the Hien Luong 2 bridge (Van Ninh district), digging and filling the roadbed and constructing some precast concrete components.

The coastal route through Van Phong Economic Zone is over 20km long, passing through Van Ninh district and Ninh Hoa town, with a total investment of over VND 2,000 billion. The project started at the end of 2024, and is expected to be completed after 3 years (2024 - 2027).

According to the design, the road surface is 30m wide with two car lanes and one lane for rudimentary vehicles on each side. The starting point of the route connects to the north of Hien Luong 2 bridge (Van Ninh), the end point connects to the right side of National Highway 26B (Ninh Hoa).

The project includes main items such as: roadbed, rainwater drainage system, road handling, lighting system, sea embankment, sidewalk...

After completion, the route will connect directly to Van Phong International Airport, playing an important role in promoting the development of the key economic zone of Khanh Hoa province.

Faced with arising difficulties, the Van Phong Economic Zone Management Board has recommended that the Department of Agriculture and Environment promptly appraise the dossier so that the Van Ninh District People's Committee has a basis to approve the estimate, select a measuring unit to serve the determination and adjustment of cadastral maps, creating conditions to speed up site clearance.

Along with that, the unit requested the People's Committee of Van Ninh district to complete the dossier, pay compensation and hand over the site in July 2025. For Ninh Hoa town, it is necessary to direct the Land Fund Development Center, the People's Committees of Ninh Diem ward and Ninh Tho commune to speed up the site clearance progress, ensuring handover in August 2025.

According to Van Phong Economic Zone Management Board, if the site is fully handed over, the unit is committed to disbursing the entire 400 billion VND of public investment capital in 2025.

The entire Coastal Road Project from Van Luong Commune, Van Ninh District to Ninh Hoa Town (20km long) has a capital of VND2,031 billion.

This project has 3 components, of which component 1 (Van Phong Economic Zone Management Board is the investor) is a construction project with a total investment of 1,700 billion VND.

Components 2 and 3 include compensation, support, resettlement and site clearance through Van Ninh district and Ninh Hoa town with capital of 230 million VND and 95 billion VND respectively (localities are investors).

Hữu Long
TIN LIÊN QUAN

Dialogue with civil affairs on coastal road change in Van Phong

|

Khanh Hoa - The investor had a dialogue with the surrounding people complaining about the change in route direction when marking the coastal road, affecting their lives.

Typing error increases coastal road project cost by 100 billion VND

|

Khanh Hoa - Due to a typing error, the coastal route component project increased to 195 billion VND, while in reality it was only 95 billion.

People complain about last minute change of coastal road

|

Khanh Hoa - People complained about the change in route direction when marking the coastal road with capital of more than 2,000 billion VND, affecting their lives.

China experiences heavy rain, severe earthquakes, Vietnam faces chain risk

|

Heavy rain causing serious landslides is spreading in many Chinese provinces, setting a warning for downstream areas, including Vietnam.

Hanoi Metro admits delays in repairing damage to Cat Linh - Ha Dong route

|

Hanoi Metro admits the delay in repairing damage to infrastructure, causing negative impacts on passengers and operations of the Cat Linh - Ha Dong route.

Close-up of the road collapsed and a large frog's jaw appeared in Can Tho

|

Can Tho - The Mat Cat canal road in Cai Rang district has many cracks, large subsidence and frog jaw making it difficult for people to travel.

Dialogue with civil affairs on coastal road change in Van Phong

Hữu Long |

Khanh Hoa - The investor had a dialogue with the surrounding people complaining about the change in route direction when marking the coastal road, affecting their lives.

Typing error increases coastal road project cost by 100 billion VND

Hữu Long |

Khanh Hoa - Due to a typing error, the coastal route component project increased to 195 billion VND, while in reality it was only 95 billion.

People complain about last minute change of coastal road

Hữu Long |

Khanh Hoa - People complained about the change in route direction when marking the coastal road with capital of more than 2,000 billion VND, affecting their lives.