Gia Lai accelerates clean land handover for a series of projects

THANH TUẤN |

Gia Lai - Key projects, industrial parks, and economic zones are required to accelerate site clearance work.

Early land handover to investors

On July 4, Gia Lai Provincial People's Committee requested departments, functional sectors and communes with projects to accelerate the progress of site clearance.

If clean site handover is delayed, it will affect the progress of investment projects, investment efficiency and investment environment of the province, especially in industrial parks and economic zones.

At Phu My Industrial Park (phase 1), the provincial government assigned Phu My Dong Commune People's Committee to certify the origin of land use for the remaining 129 cases; prioritizing implementation for areas and items of works that investors need to deploy first.

At other projects such as: Binh Nghi Industrial Park, Cat Hai Bay High-Class Resort, Phu Hau - Cat Tien Entertainment Area, Cat Trinh Industrial Park, Nhon Hoa Industrial Park, Hoa Hoi, Tay Giang..., the Provincial People's Committee requested communes to soon verify the origin of land, handle people's complaints well; develop a satisfactory compensation plan.

Project implementation creates development momentum

At the same time, propagate and mobilize people to agree, soon relocate, resettle, and stabilize their lives to allocate clean land funds to investors to implement projects smoothly, serving the general socio-economic development of the province.

In recent years, Gia Lai has implemented legal procedures for a series of projects from industrial parks, urban areas to transport infrastructure projects with a total capital of trillions of VND.

When projects are constructed on the ground, many localities will become "large construction sites", especially in the period 2026 - 2030.

The province's orientation is that the eastern region will strongly develop industrial parks, processing services, logistics, and high technology; while the western region will strongly develop agricultural products and deep processing for export.

Synchronous infrastructure from seaports, airports, expressways... will create favorable conditions for Gia Lai to develop commensurate with its potential.

THANH TUẤN
RELATED NEWS

Removing the bottleneck of a bridge built a long time ago but the access road encounters obstacles at the Nhat Le 3 project

|

Quang Tri - Thanks to the determination of the government, the Nhat Le 3 bridge project and the roads at both ends of the bridge have been removed from site obstacles.

Hai Phong prepares to start the first semiconductor project in the Free Trade Zone

|

Hai Phong - The Standing Committee of the City Party Committee has just agreed in principle to invest in the LG Innotek Hai Phong Semiconductor Packaging Base Production Plant Project.

Nghe An approves social housing project worth over 1,557 billion VND

|

Nghe An - Nghe An Provincial People's Committee approved the investment policy for a social housing project in Vinh Phu ward, with a scale of about 2,000 apartments.

Heavy rain causes 19 landslides on National Highway 32 in Lao Cai

|

Lao Cai - Heavy rain lasting from the night of July 4 to the morning of July 5 caused 19 points on National Highway 32 to landslide with more than 2,000m3 of soil and rocks spilling onto the road surface.

Announcing decisions on personnel work in Hung Yen, Hue, Da Nang, Quang Ninh

|

Hue, Da Nang, Hung Yen, Lai Chau, Quang Ninh provinces/cities... last week deployed and announced decisions on personnel work.

The title of "Player of the Match" at the 2026 World Cup is controversial

|

Votes from fans are turning a FIFA personal award at the 2026 World Cup into a controversial topic.

Da Nang continues to affirm its position as a rendezvous point for the Asian Film Festival

|

Da Nang - On the evening of July 4, the 4th Da Nang Asian Film Festival closed 7 exciting days, honoring many excellent works and artists.

It's time to eliminate the model where EVN is the only electricity buyer

|

According to experts, EVN's single-purchaser model has existed for many years, but is no longer suitable.

Removing the bottleneck of a bridge built a long time ago but the access road encounters obstacles at the Nhat Le 3 project

NGUYỄN LUÂN |

Quang Tri - Thanks to the determination of the government, the Nhat Le 3 bridge project and the roads at both ends of the bridge have been removed from site obstacles.

Hai Phong prepares to start the first semiconductor project in the Free Trade Zone

Hoàng Khôi |

Hai Phong - The Standing Committee of the City Party Committee has just agreed in principle to invest in the LG Innotek Hai Phong Semiconductor Packaging Base Production Plant Project.

Nghe An approves social housing project worth over 1,557 billion VND

QUANG ĐẠI |

Nghe An - Nghe An Provincial People's Committee approved the investment policy for a social housing project in Vinh Phu ward, with a scale of about 2,000 apartments.