Site clearance must be based on the approved project

Khương Duy |

Site clearance in general must be based on the approved project; only when it is separated into an independent project can it be implemented in advance according to regulations.

A resident in Quang Tri reflected that, according to regulations on construction investment procedures, the project is implemented through stages of preparation, implementation and completion of construction.

From there, people are concerned whether the land acquisition, land allocation, and site clearance carried out before the investment project is approved is in accordance with regulations or not.

Answering this content, the Economic - Construction Investment Management Department, Ministry of Construction said that the law on construction has clearly stipulated the contents related to land right from the project preparation stage.

Accordingly, the pre-feasibility study report must state information about the construction location and land use needs; and the feasibility study report must determine the land use area, site clearance plan and resettlement if any.

Việc giải phóng mặt bằng thông thường chỉ được triển khai khi dự án đầu tư xây dựng đã được phê duyệt theo quy định.
Site clearance is usually only implemented when the construction investment project has been approved according to regulations. Photo: Cong Sang

According to this agency, the appraisal process of construction investment projects must also consider the ability to meet land use needs and site clearance requirements. Therefore, construction investment projects after being approved are the basis for implementing land acquisition, compensation, site clearance and resettlement according to regulations.

The Economic - Construction Investment Management Department, Ministry of Construction, also cited the provisions of Clause 1, Article 108 of the 2014 Construction Law, according to which land recovery, land allocation, land lease, compensation and site clearance for construction are carried out in accordance with land law.

However, the replying agency also mentioned an exceptional case according to the law on public investment. The competent authority when approving investment policies for nationally important projects and group A, B, C projects may decide to separate or not separate the content of compensation, support, resettlement, and site clearance into an independent component project.

Thus, if the content of compensation, support, resettlement and site clearance is separated into an independent component project, then site clearance, land recovery, and land allocation can be carried out independently of the construction investment project. In this case, site clearance must be based on the approved project.

Khương Duy
RELATED NEWS

Ho Chi Minh City establishes a new Compensation and Site Clearance Board to handle large projects

|

Ho Chi Minh City pilots the reorganization of the City-level Compensation and Site Clearance Board to improve the efficiency of implementing large-scale projects.

Completion of site clearance for nearly 220 billion VND project in Hai Phong

|

Hai Phong - April 17, Phu Lien ward completed site clearance for the project of connecting Nguyen Luong Bang street with Tran Nhan Tong street.

Dialogue on site clearance for the 5-story apartment building demolition project in Hai Phong

|

Hai Phong - April 15, Do Son ward organized a dialogue with households related to the project of site clearance and demolition of a 5-story apartment building at 75 Ly Thanh Tong.

Live football match Hoang Anh Gia Lai vs Hai Phong in round 20 of V.League

|

Live football match Hoang Anh Gia Lai vs Hai Phong in round 20 of V.League 2025-2026 at 5:00 PM today (April 24).

Discussing 14 contents, many of which are related to the 14th Vietnam Trade Union Congress

|

Hanoi - In the afternoon of April 24, the Executive Committee of the Vietnam General Confederation of Labour organized a Conference to discuss 14 contents, many of which are related to the 14th Vietnam Trade Union Congress.

People live in hardship beside the hundred-billion road project in Tuyen Quang

|

Tuyen Quang - Many households located within the Son Duong - Tan Trao road project area that have not been relocated are facing dusty weather and muddy rain.

Live football U17 Laos vs U17 Australia in the third-place match of the Southeast Asian Championship

|

Live football U17 Laos vs U17 Australia in the third-place match of the 2026 Southeast Asian U17 Championship at 3:30 PM today (April 24).

Stocks are heavily sold off, PC1's capitalization evaporates nearly 1,500 billion VND

|

Nearly 23 million PC1 shares were dumped on the floor in a context of no buyers, reflecting great selling pressure from investors.

Ho Chi Minh City establishes a new Compensation and Site Clearance Board to handle large projects

MINH QUÂN |

Ho Chi Minh City pilots the reorganization of the City-level Compensation and Site Clearance Board to improve the efficiency of implementing large-scale projects.

Completion of site clearance for nearly 220 billion VND project in Hai Phong

Hoàng Khôi |

Hai Phong - April 17, Phu Lien ward completed site clearance for the project of connecting Nguyen Luong Bang street with Tran Nhan Tong street.

Dialogue on site clearance for the 5-story apartment building demolition project in Hai Phong

Hoàng Khôi |

Hai Phong - April 15, Do Son ward organized a dialogue with households related to the project of site clearance and demolition of a 5-story apartment building at 75 Ly Thanh Tong.