Removing site bottlenecks for a hundred-billion VND infrastructure project in Lao Cai to reach its target

Đinh Đại |

Lao Cai - Removing site bottlenecks will help the Tan Lap urban area infrastructure project reach the finish line in 2026.

Reporters' records on April 6 show that at the Tan Lap urban area project construction site, many items are being implemented simultaneously.

Machinery and manpower are mobilized to the maximum, taking advantage of favorable weather to speed up progress.

Máy móc, nhân lực tập trung thi công dự án khi thời tiết khô ráo. Ảnh: Đinh Đại
Machinery and manpower focus on project construction when the weather is dry. Photo: Dinh Dai

Through research, the project has a total investment of 260 billion VND, implemented in the period 2023-2026.

The project scale is about 24 hectares, including ground leveling, transportation system, water supply and drainage, electricity, communication and the Red River embankment line more than 436 m long.

This is a key project to complete infrastructure, create land funds and promote local socio-economic development.

Dự án khi hoàn thành cũng góp phần tạo thêm quỹ đất cho địa phương. Ảnh: Đinh Đại
When completed, the project will also contribute to creating more land fund for the locality. Photo: Dinh Dai

At the construction site, Mr. Do Viet Hung - technical officer of Minh Duc General Construction Co., Ltd. said that construction encountered many obstacles because the ground had not been handed over synchronously, while the prolonged rainy weather before that also significantly affected the progress.

The unit is taking advantage of dry time, organizing overtime, increasing shifts, and mobilizing more machinery to compensate for the delayed volume," Mr. Hung said.

Chủ đầu tư và nhà thầu thường xuyên kiểm tra, tháo gỡ những vướng mắc để  việc thi công diễn ra thuận lợi. Ảnh: Đinh Đại
The investor and contractor regularly inspect and remove obstacles to ensure smooth construction. Photo: Dinh Dai

Currently, the Red River embankment item - identified as the key of the project - has basically completed the pile driving and some units, and is continuing to construct the embankment body and embankment behind.

Faced with the pressure of progress, the Lao Cai Provincial Construction Investment Project Management Board has strengthened direction, requiring contractors to organize many parallel construction teams, focusing on key items.

Talking to reporters, Mr. Cu Minh Quan - Deputy Head of Project 1 Department (Lao Cai Provincial Construction Investment Project Management Board) said that despite many difficulties, the investor still requires units to maximize favorable time to accelerate progress and minimize construction interruptions.

Các công nhân thi công kè sông Hồng thuộc dự án hạ tầng kỹ thuật khu đô thị Tân Lập. Ảnh: Đinh Đại
Workers constructing the Red River embankment under the Tan Lap urban area technical infrastructure project. Photo: Dinh Dai

Meanwhile, site clearance work continues to be the biggest "bottleneck". Cam Duong Ward People's Committee is coordinating with relevant units to focus on removing each obstacle.

According to the leader of Cam Duong Ward People's Committee, up to now, about 61% of the area has been cleared. The rest mainly relates to difficult cases of land origin, disputes or disagreements on compensation plans.

Chính quyền địa phương sẽ phối hợp với chủ đầu tư để tháo gỡ vướng mắc về giải phóng mặt bằng. Ảnh: Đinh Đại
Local authorities will coordinate with the investor to remove site bottlenecks. Photo: Dinh Dai

Notably, some households built on agricultural land or land not owned by themselves are not yet eligible for resettlement; some cases have overlapping dossiers or belong to groups without specific support mechanisms.

Cam Duong ward is reviewing dossiers and proposing special mechanisms to handle them thoroughly, especially for 6 households that are heavily affected. The goal is to complete site clearance in July 2026, creating conditions for the project to accelerate to reach the finish line on schedule.

Đinh Đại
RELATED NEWS

Donating land to open roads, creating momentum for development for Lao Cai highland villages

|

Lao Cai - People have agreed to donate land to open new roads when propagated and explained by local authorities.

Site bottleneck hinders a series of traffic projects in Lao Cai

|

A series of traffic projects in Lao Cai are behind schedule due to site clearance problems, interrupted construction, reducing investment efficiency and affecting people's lives.

Land clearance bottlenecks threaten the goal of opening Huu Nghi - Chi Lang expressway

|

Lang Son - 122 households have not been relocated, along with a series of other difficulties, causing the Huu Nghi - Chi Lang expressway to face the risk of being behind schedule.

Changing SIMs to new phones requires facial verification

|

From June 15, users when switching SIMs to another device will have to verify faces. If not completed, the subscriber will be temporarily suspended from the service according to the roadmap.

Explosives discovered near Russian gas pipeline, Hungary holds emergency meeting before elections

|

Hungary held an emergency meeting after Serbia discovered explosives with great destructive power only a few hundred meters from the Russian gas pipeline.

Party and State leaders, National Assembly deputies visit President Ho Chi Minh's Mausoleum

|

Party and State leaders, National Assembly deputies enter the Mausoleum to pay respects to President Ho Chi Minh before the opening session of the First Session of the 16th National Assembly.

Stone mine "suspended" for 9 months, Gia Lai warns to replace commune leaders

|

Gia Lai - Although licensed, a quarry is still "suspended" for 9 months due to land lease procedures at the commune level.

Trump warns of destroying Iranian infrastructure

|

Mr. Trump on April 5 (local time) issued a warning that he would destroy Iran's important civilian infrastructure.

Donating land to open roads, creating momentum for development for Lao Cai highland villages

Đinh Đại |

Lao Cai - People have agreed to donate land to open new roads when propagated and explained by local authorities.

Site bottleneck hinders a series of traffic projects in Lao Cai

Bảo Nguyên - Duy Dũng |

A series of traffic projects in Lao Cai are behind schedule due to site clearance problems, interrupted construction, reducing investment efficiency and affecting people's lives.

Land clearance bottlenecks threaten the goal of opening Huu Nghi - Chi Lang expressway

Khánh Linh |

Lang Son - 122 households have not been relocated, along with a series of other difficulties, causing the Huu Nghi - Chi Lang expressway to face the risk of being behind schedule.