Hanoi recovers land to build a 4.1km long road, about 1,050 houses affected

SÓNG HỮU |

Hanoi - Son Tay Ward is implementing land acquisition and site clearance steps to build the Tay Thang Long main road, 4.1km long, passing through the area.

On September 11, Son Tay ward (Hanoi) organized a conference to propagate the project scale and regulations on compensation, support, and resettlement when the State recovers land to implement the investment project to build the Tay Thang Long main road in the ward.

According to Son Tay Ward People's Committee, the project to invest in the construction of the Tay Thang Long main road is a group A project, a grade I road traffic project, with a design speed of 80km/h, with a total expected construction investment length of about 22km, passing through the communes and wards of Dan Phuong, Lien Minh, Hat Mon, Phuc Tho, Phuc Loc and Son Tay.

The section passing through Son Tay ward is expected to be 4.1km long, from Km17+823 to Km21+975. According to the introduced design plan, the road has a total roadbed width of about 80m, including the motorized road section, parallel road, median strip and sidewalk system on both sides.

This is a traffic route expected to contribute to strengthening the connection of the western area with the capital center, completing the transportation network, technical infrastructure, expanding urban development space and creating motivation to promote socio-economic development in the area.

According to preliminary reports, the route section through Son Tay ward has a total expected number of affected houses of 1,050 houses and a total expected number of resettlement houses of 858 houses. The resettlement arrangement plan is expected at Phu Thinh Resettlement Area and Duong Lam Resettlement Area.

For Phu Thinh Resettlement Area, the expected area is about 8.56 ha, of which residential land for resettlement is about 37,799m2, accounting for 44.13%, expected to arrange 400 units. This area is also planned for cultural land, public green trees, relic land, religious land, roads and parking lots, aiming to form a residential area with a synchronous infrastructure system.

For Duong Lam Resettlement Area, the total expected area is about 21.67 ha, of which new residential land for resettlement is about 84. 112m2, accounting for 38.80%, expected to arrange 651 units. The plan also allocates land fund for social infrastructure works, cultural houses, public green trees, parking lots, traffic, traffic corridors and other items.

a
Secretary of the Party Committee, Chairman of Son Tay Ward People's Council Ngo Dinh Ngu speaks at the conference. Photo: Trang TTĐT Son Tay Ward

Speaking at the conference, Mr. Ngo Dinh Ngu - Secretary of the Party Committee, Chairman of the People's Council of Son Tay Ward requested the Ward People's Committee and specialized departments and divisions to urgently review and immediately resolve pressing people's livelihood issues in the area related to the project, especially issues under the authority of the locality.

Secretary of the Party Committee of Son Tay ward emphasized the requirement that in the project implementation process, it is necessary to ensure publicity, transparency, compliance with regulations, take the consensus of the people as an important basis, and at the same time continue to strengthen propaganda, dialogue, and explanation to help people understand their guidelines, policies and rights.

With the spirit of receptiveness, listening and accompanying the people, the ward leaders hope that households in the project area will continue to share, agree, and support the general policy, coordinate with the government in the process of counting, verifying the origin of land, developing compensation, support and resettlement plans, contributing to the project being implemented smoothly and on schedule.

SÓNG HỮU
RELATED NEWS

Deploying land recovery from 2,210 households and individuals in Hanoi to build roads 60-80m wide

|

Hanoi - 2. 210 households and individuals in Thanh Tri commune are subject to land acquisition and site clearance to implement the Ring Road 3.5 project.

Deploying land acquisition to expand key roads in Hanoi to 90m

|

Hanoi - Many localities are implementing land acquisition and site clearance steps to expand National Highway 1A to 90m.

Information on land acquisition and site clearance to build and expand roads to 120m in Hanoi

|

The road connecting Gia Binh airport with Hanoi Capital is 41.3km long, of which the section through Hanoi is 13.55km long. Land acquisition and site clearance are being implemented.

Thousands of tons of clams raised by people die after storms

|

Thanh Hoa - Mass clam deaths at about 60ha of farming ground of 50 households in Ngoc Son ward, estimated damage output from 2,000-2,400 tons.

Houthi forces completely control the strategic Bab al Mandab strait

|

Houthi forces in Yemen have just seized control of Mayyun Island and taken over the Bab al Mandab Strait, a vital shipping route for global oil exports.

Ministry of Industry and Trade requests Grab to clarify fares, fees, and discounts

|

The National Competition Committee (Ministry of Industry and Trade) is conducting a review and verification of reflections related to Grab's price and fee policies.

Case of former principal collecting 15,000 VND/sidetime tutoring: Parents say students benefit

|

Parents affirmed that their children benefited and there was no damage in the case of the former Principal of Ba Dinh Secondary School collecting 15,000 VND/sidetime tutoring.

Deploying land recovery from 2,210 households and individuals in Hanoi to build roads 60-80m wide

SÓNG HỮU |

Hanoi - 2. 210 households and individuals in Thanh Tri commune are subject to land acquisition and site clearance to implement the Ring Road 3.5 project.

Deploying land acquisition to expand key roads in Hanoi to 90m

SÓNG HỮU |

Hanoi - Many localities are implementing land acquisition and site clearance steps to expand National Highway 1A to 90m.

Information on land acquisition and site clearance to build and expand roads to 120m in Hanoi

SÓNG HỮU |

The road connecting Gia Binh airport with Hanoi Capital is 41.3km long, of which the section through Hanoi is 13.55km long. Land acquisition and site clearance are being implemented.