Two Nha Trang coastal projects lease land without auction

Hữu Long |

The two Nha Trang coastal projects were leased land by the locality without auction and were proposed to apply a special mechanism to remove obstacles.

Phu Dong Park has been suspended since 2020

Khanh Hoa Provincial Inspectorate has just issued an inspection conclusion, clarifying a series of shortcomings and violations in the implementation of Phu Dong Park Project and Four Seasons E-Land Entertainment - Service Project.

The Phu Dong Park project is located on Tran Phu Street, invested by Khanh Hoa Tourism Company Limited.

In 2012, Khanh Hoa Provincial People's Committee issued an Investment Certificate to Invest Park Nha Trang Company Limited - a joint venture between Khanh Hoa Tourism Company Limited and foreign partners - to implement a project with a land area of about 24,000m2, with a total investment of 120 billion VND.

In the same year, Khanh Hoa Tourism Company Limited proposed that the Provincial People's Committee reclaim the land that the unit was leasing at Phu Dong Park to lease to Invest Park Nha Trang Company Limited to implement the project according to regulations.

In 2014, Khanh Hoa province issued a decision to reclaim land leased by Khanh Hoa Tourism Company Limited and allocate and lease land to Invest Park Nha Trang Company Limited to implement the project.

The inspection results determined that the land lease for project implementation did not go through auction of land use rights.

The current status of the land includes works including restaurants, toilets, swimming pools, Russian Restaurant, basement of Russian Restaurant and outdoor stage. These items have been temporarily suspended from business operations since March 2020.

Regarding financial obligations, Invest Park Nha Trang Company Limited has so far paid a part of the land rent.

Specifically: total land rent payable: more than 29.5 billion VND; paid amount: nearly 19 billion VND; remaining payable amount: more than 4.8 billion VND; exempted or reduced amount: more than 5.8 billion VND.

Cong vien Phu Dong nhin tu tren cao. Anh: Huu Long
Phu Dong Park seen from above. Photo: Huu Long

Fault due to subjectivity, haste

A similar situation also occurs at the E-Land Four Seasons Entertainment - Service Project, located on the East side of Tran Phu Street (opposite 40 Tran Phu), invested by Nha Trang Four Seasons Company Limited.

The project has a scale of building a restaurant and entertainment service area, with a ground and underground area of about 2,787m2, total investment capital of about 85 billion VND.

According to the inspection agency, the land allocation and lease to implement this project did not go through auction of land use rights.

The responsibility is determined to belong to the People's Committee of Khanh Hoa province (2012's 2015, 2017 period), the Department of Natural Resources and Environment (2012, 2014, 2015, 2017) and related individuals.

According to the inspection conclusion, at the time of the violations, Khanh Hoa province was facing many difficulties in attracting and mobilizing investment capital to develop transport infrastructure, trade - tourism - services, so it was subjective and hasty in implementing projects to promote socio-economic development.

In addition, the laws on land, investment, construction, housing... at that time were not synchronous and overlapped, while being slow to be guided, amended, supplemented...

The above violations are largely due to the fault of state management agencies, some cases are the fault of both management agencies and investors.

Because the project did not organize a land use rights auction to select an investor, it was not in accordance with the provisions of law.

The inspection agency requested the Khanh Hoa Provincial People's Committee to propose to Steering Committee 751 and the Prime Minister to consider and report to competent authorities to allow the application of a special mechanism similar to Resolution 170/2024/QH15.

Accordingly, the application of a special mechanism will help handle continued land use, determine land prices to fully collect financial obligations to the state budget, ensure no loss of public assets, and at the same time remove difficulties and obstacles for coastal projects that have been backlogged for many years.

Hữu Long
RELATED NEWS

Nha Trang International Yard Project Concluded to Illegal Transfer

|

The change of legal status for the Nha Trang International Yard Park Project is a form of investment project transfer, but does not ensure legal regulations.

Reviewing the Sasco hotel project that is behind schedule, lasting nearly 2 decades in Nha Trang

|

People continue to wait for the solution to handle the Sasco Nha Trang Hotel Project, which has lasted for nearly 20 years.

Looking back at the golden land along the coast of Nha Trang after 30 years of land allocation to businesses

|

Khanh Hoa - Ana Mandara Resort is located on Tran Phu Street (Nha Trang), built in 1995. After 30 years, the government has reclaimed the entire land.

Close-up of a concrete grass house at the foot of a volcano in Gia Lai that has just been forced to be demolished

|

Gia Lai forced the suspension and dismantling of the concrete moat house project in Ia Gri village, because the design was not traditional, which was at risk of disrupting the landscape of Chu Dang Ya volcano.

Storm No. 11 weakens when entering Quang Ninh, people's lives gradually return to normal

|

Quang Ninh - Storm No. 11 has weakened, many coastal localities of Quang Ninh have returned to normal activities, students have returned to school, and tourism is still temporarily suspended.

Eating moon cakes for the first time, Western tourists consider them as King cakes

|

Vietnamese mooncakes make a strong impression on international visitors with their especially impressive flavor at first taste.

HCMC considers Vingroup's Can Gio - Vung Tau sea route project

|

Ho Chi Minh City assigned departments and branches to consider Vingroup's Can Gio - Vung Tau sea route project before October 10.

Hanoi urgently requests to adjust teaching plans, many schools welcome students back

|

Instead of announcing a citywide holiday like yesterday, the Hanoi Department of Education and Training has allowed principals to proactively plan their school plans, and some schools have announced welcoming students.

Nha Trang International Yard Project Concluded to Illegal Transfer

Hữu Long |

The change of legal status for the Nha Trang International Yard Park Project is a form of investment project transfer, but does not ensure legal regulations.

Reviewing the Sasco hotel project that is behind schedule, lasting nearly 2 decades in Nha Trang

Hữu Long |

People continue to wait for the solution to handle the Sasco Nha Trang Hotel Project, which has lasted for nearly 20 years.

Looking back at the golden land along the coast of Nha Trang after 30 years of land allocation to businesses

Hữu Long |

Khanh Hoa - Ana Mandara Resort is located on Tran Phu Street (Nha Trang), built in 1995. After 30 years, the government has reclaimed the entire land.