More than 700 households have not yet handed over the land for the Ho Chi Minh City Ring Road 2 project

MINH QUÂN |

HCMC - The two sections of the Eastern Ring Road 2, nearly 6 km long, will start construction on December 19, but there are still more than 700 households that have not handed over the site.

On December 11, the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) said that the construction of the two sections of Ring Road 2 will start from December 19.

Section 1 is more than 3.5 km long, from Phu Huu Bridge to Vo Nguyen Giap Avenue and Section 2 is nearly 2.5 km long, from Vo Nguyen Giap Avenue to Pham Van Dong.

The total investment of the two projects is nearly 13,900 billion VND, of which compensation and site clearance costs account for the majority; construction costs are only about 19%.

Both sections are being cleared by Ho Chi Minh City with a scale of 67 m.

On the recovered land, the city will build parallel roads on both sides (each road is 17 m wide, with a scale of 3 lanes) and intersections, the vacant land in between will be reserved for future expansion.

2 doan Vanh dai 2 phia Dong can thu hoi dat 1.150 ho dan.  Anh: Anh Tu
The two sections of the Eastern Ring Road 2 need to reclaim land from 1,150 households. Photo: Anh Tu

Section 1 has a total reclaimed area of over 47 hectares, affecting 888 cases, including 870 households and 18 organizations in Tang Nhon Phu, Phuoc Long, Thu Duc wards.

To date, the Traffic Department has received the premises of 250 cases. About 1.2 km of site at the beginning and end of the route is eligible for construction. In particular, the middle of the route is still not cleared synchronously, so it will be difficult to organize continuous construction.

Vanh dai 2 se di qua khu vuc nut giao Binh Thai tren duong Vo Nguyen Giap.  Anh: Anh Tu
Ring Road 2 will pass through Binh Thai intersection on Vo Nguyen Giap Street. Photo: Anh Tu

Section 2 has a reclaimed area of 13.5 hectares, affecting 262 cases, including 253 households and 9 organizations (Thu Duc ward). There are currently 143 cases of land handover.

The Traffic Department said that some locations in section 2 have not yet received compensation or have not yet handed over land, making it possible for the project to only construct the sections with available land in 2025.

The two sections of Ring Road 2 are expected to be completed and put into operation in 2027. When completed, the route will strengthen connections with main traffic routes, seaport systems and contribute to traffic flow, reducing congestion in the inner city of Ho Chi Minh City.

The 64 km long Ho Chi Minh City Ring Road 2 is currently 14 km unfinished, divided into 4 sections.

In addition to the two eastern sections that will start construction on December 19, section 3 from Pham Van Dong Street to Go Dua intersection, 2.7 km long, has been implemented since 2017 but is still unfinished.

Section 4, 5.3 km long in the south of the city, connecting from National Highway 1 to Nguyen Van Linh Street, has not yet been submitted to the competent authority for investment approval.

MINH QUÂN
RELATED NEWS

People are busy moving their homes to prepare for the start of construction of Ring Road 2 in Ho Chi Minh City

|

Ho Chi Minh City is speeding up the site clearance process, many households are rushing to relocate in time to hand over land, preparing to start the Ring Road 2 project by the end of 2025.

The 2.7 km long project on Ho Chi Minh City Ring Road 2 is still unfinished, becoming a place for livestock farming

|

HCMC - Section 3 of Ho Chi Minh City Ring Road 2 through Thu Duc City with a total capital of more than VND 2,700 billion is still unfinished, some places are being exploited for livestock farming.

HCMC speeds up closure of Ring Road 2, rescues inner-city traffic jams

|

HCMC - After 18 years of planning, Ho Chi Minh City Ring Road 2, 64 km long, is still 14 km unfinished, the city is accelerating to soon close this vital route.

Completing personnel, preparing for the 16th National Assembly term

|

The Vice Chairman of the Delegation Work Committee affirmed that the improvement of personnel at the 10th Session is a necessary preparation step for the 16th National Assembly term.

Complete construction of Long Thanh airport air traffic control tower

|

Dong Nai - Vietnam Air Traffic Management Corporation (VATM) has completed 100% of preparations for the first flights at Long Thanh airport.

SEA Games 33 U22 Vietnam men's football rankings, Best Group B

|

Updated rankings of Group B men's football at the 33rd SEA Games, in which U22 Vietnam ranked first.

Red book procedures are more transparent thanks to AI Center

|

Hanoi - With the AI Center, people are directly supported with procedures related to red books, ensuring transparency.

Gasoline prices drop across the board from 3:00 p.m. this afternoon, December 11

|

Gasoline prices have decreased simultaneously from 3:00 p.m. today, December 11, after adjustments by the Ministry of Industry and Trade - Ministry of Finance.

People are busy moving their homes to prepare for the start of construction of Ring Road 2 in Ho Chi Minh City

TÚ QUỲNH |

Ho Chi Minh City is speeding up the site clearance process, many households are rushing to relocate in time to hand over land, preparing to start the Ring Road 2 project by the end of 2025.

The 2.7 km long project on Ho Chi Minh City Ring Road 2 is still unfinished, becoming a place for livestock farming

Tâm Tú |

HCMC - Section 3 of Ho Chi Minh City Ring Road 2 through Thu Duc City with a total capital of more than VND 2,700 billion is still unfinished, some places are being exploited for livestock farming.

HCMC speeds up closure of Ring Road 2, rescues inner-city traffic jams

MINH QUÂN |

HCMC - After 18 years of planning, Ho Chi Minh City Ring Road 2, 64 km long, is still 14 km unfinished, the city is accelerating to soon close this vital route.