Lang Son to start construction of multi-purpose gymnasium, review to reduce scale phase 2

Khánh Linh |

Lang Son - The province is preparing to start construction of the multi-purpose gymnasium (phase 1) item right in May.

Recently, Vice Chairman of Lang Son Provincial People's Committee Doan Thanh Son chaired a field inspection and a meeting to assess the implementation of the Provincial Sports Complex project.

For phase 1 of the project, the province requests the Provincial Construction Investment Project Management Board to direct contractors to prepare the necessary conditions to start construction of the multi-purpose gymnasium item right in May 2026.

The project progress is currently recording many changes when it has completed peeling off the organic soil layer and constructing ground leveling on 7.04 hectares of land area handed over.

Functional agencies have counted and measured 163/197 affected households and individuals, corresponding to an area of 21.9 hectares.

To date, the total area of land handed over is 12.18 ha. Along with that, 107/125 graves in the project area have been relocated.

Phối cảnh Khu Liên hợp thể thao tỉnh Lạng Sơn được triển khai trên diện tích 28,73 ha, với 11 hạng mục. Ảnh: ĐVCC
Perspective of Lang Son Provincial Sports Complex deployed on an area of 28.73 ha, with 11 items. Photo: DVCC

To ensure construction, provincial leaders requested to focus on completing the drainage item before the 2026 rainy and storm season to limit the risk of localized flooding.

At the same time, Dong Kinh Ward People's Committee must complete the approval of the power line compensation plan no later than May 2026 for Lang Son Power Company to organize relocation.

On the same day, in the meeting to review and develop investment policies for phase 2, provincial leaders requested the Provincial Construction Investment Project Management Board to study a plan to adjust and reduce the number of seats in some stand areas to suit reality.

Materials for running tracks and squares will also be adjusted in a reduction direction but still must ensure quality requirements.

The report on the results of reviewing and preparing investment policy for phase 2 of the project is expected to be completed and submitted to the Standing Committee of the Provincial Party Committee before May 17, 2026.

Khánh Linh
RELATED NEWS

The case of 80kg of cicada carcasses being temporarily seized in Lang Son and the expensive lesson about the "forest goods" business

|

Lang Son - From a clip arguing with words causing a social media storm, the case of 80kg of cicada carcasses being temporarily seized by the Market Management Department has attracted special attention from public opinion.

Lang Son Party Secretary: Will review the head if the wrong subjects are reviewed to remove temporary houses

|

Lang Son - More than 66.6 billion VND has been disbursed to build new and repair 1,339 temporary and dilapidated houses in the province.

Fining dozens of establishments violating food safety and hygiene in Lang Son

|

Lang Son - Market Management Team No. 1 has just fined dozens of establishments violating food safety and hygiene, and at the same time prevented many batches of dirty pig intestines and smuggled sausages.

Live volleyball VTV Binh Dien Long An vs Vietinbank

|

Live volleyball VTV Binh Dien Long An and Vietinbank at VTV9 - Binh Dien Cup 2026, taking place at 8:00 PM today (May 16).

Hanoi diverts traffic at La Thanh - Nguyen Chi Thanh intersection from May 18

|

Hanoi adjusts traffic organization at La Thanh - Nguyen Chi Thanh intersection from May 18 to serve the construction of overpasses under the Ring Road 1 project.

President Trump considers lifting sanctions on Chinese company buying Iranian oil

|

US President Donald Trump shares Chinese President Xi Jinping's opinion on the Strait of Hormuz.

Energy transition, develop green transportation to promote sustainable growth

|

Energy saving, energy transition and green transportation development are important solutions to promote sustainable growth.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

The case of 80kg of cicada carcasses being temporarily seized in Lang Son and the expensive lesson about the "forest goods" business

Khánh Linh |

Lang Son - From a clip arguing with words causing a social media storm, the case of 80kg of cicada carcasses being temporarily seized by the Market Management Department has attracted special attention from public opinion.

Lang Son Party Secretary: Will review the head if the wrong subjects are reviewed to remove temporary houses

Khánh Linh |

Lang Son - More than 66.6 billion VND has been disbursed to build new and repair 1,339 temporary and dilapidated houses in the province.

Fining dozens of establishments violating food safety and hygiene in Lang Son

Khánh Linh |

Lang Son - Market Management Team No. 1 has just fined dozens of establishments violating food safety and hygiene, and at the same time prevented many batches of dirty pig intestines and smuggled sausages.