Many industrial cluster projects in Hai Phong face site clearance obstacles

Hoàng Khôi |

Hai Phong - Vice Chairman of the City People's Committee Le Trung Kien chaired a meeting to listen to reports on site clearance for industrial park and cluster projects in the area.

At the meeting, representatives of the Department of Industry and Trade and the Economic Zone Management Board reported in detail on the implementation progress at 5 industrial clusters including Cua Hoat - Quan Thang, Cong Hoa, Luong Dien, Thang Long, Toan Thang and other key industrial parks such as Ngu Phuc, Binh Giang and Tien Cuong - Hoa Binh.

Accordingly, the Toan Thang Industrial Cluster project (Gia Phuc commune) has basically completed the land area according to the plan, and is expected to hand over the remaining areas by the end of April 2026. Projects such as Cua Hoat - Quan Thang Industrial Cluster or Luong Dien still have problems related to overlapping with national grid infrastructure projects, model new rural projects and difficulties in determining land origin, old land lease dossiers in the locality...

After listening to the opinions at the meeting, in his concluding speech, Vice Chairman of the City People's Committee Le Trung Kien emphasized the urgent requirement to accelerate the progress of site clearance to implement industrial park and cluster projects. In the current context, this is considered a driving force to promote economic growth of the city.

The Vice Chairman of the City People's Committee assigned the Department of Industry and Trade to preside over and coordinate with the Department of Finance to work specifically with each industrial cluster to unify the signing of progress commitments and legal conditions. The Department of Construction accelerates the appraisal and approval of design drawings. The Economic Zone Management Board reviews all problems related to site clearance to accelerate progress and soon deploy infrastructure investment for projects. The Department of Natural Resources and Environment closely directs the approval of environmental impact assessment. The Department of Science and Technology should soon complete the application of management and monitoring of site clearance progress so that the city can monitor progress online.

Vice Chairman of the City People's Committee Le Trung Kien directed localities to prioritize implementing maximum compensation for agricultural land to support people to soon change careers and stabilize their lives. The Department of Finance reviews and proposes a mechanism for decentralizing resettlement work for localities to create proactiveness, avoiding shirking responsibility between management boards and communes and wards, helping to shorten the time to hand over land to people. In particular, city leaders noted that localities should focus highly on key projects, considering site clearance as a basis for evaluating the level of task completion of leaders of departments, branches, and localities...

Hoàng Khôi
RELATED NEWS

Hai Phong prioritizes nearly 43 billion VND for training officials and teachers in 2026

|

Hai Phong - The City People's Committee has just issued a plan to train and foster to improve the qualifications and capacity of teachers and education management officials in the period 2026-2030.

Groundbreaking ceremony for a craft village industrial cluster project in Thuy Nguyen, Hai Phong

|

Hai Phong - April 6, Hai Phong broke ground on the project to invest in construction and business of technical infrastructure of Thuy Nguyen mechanical and casting craft village industrial cluster.

Close-up of the 500 billion VND sea dike reinforcement project in Ninh Binh to be completed soon

|

Ninh Binh - The Hai Thinh sea dike landslide reinforcement and treatment project with a total capital of about 500 billion VND has reached about 97% of the volume, about to reach the finish line before the rainy and storm season.

400 billion VND project in Da Nang disaster area, urgent on paper, messy on the ground

|

Da Nang - As an emergency reconstruction project after natural disasters, but after many years, the nearly 400 billion VND traffic road is still unfinished, causing people to face many difficulties.

Asian ships have tickets through Hormuz, thanks to diplomacy with Iran

|

Some Asian countries have reached agreements with Iran to allow some ships to pass through the Strait of Hormuz safely.

Live football U20 Vietnamese women vs U20 Bangladesh women at the 2026 Asian U20 women's tournament

|

Live football match between Vietnam U20 women's team and Bangladesh U20 women's team in the group stage of the 2026 AFC U20 Women's Championship at 8:00 PM tonight (April 7).

Stock market liquidity continues to decline

|

The stock market had a slight recovery session but lacked spreading momentum.

Live Vietnam futsal team vs Timor-Leste at Southeast Asian tournament

|

Live football match of Vietnam futsal team against Timor-Leste in the 2nd match of Group A of the 2026 Southeast Asian Futsal Championship at 5:30 PM today (April 7).

Hai Phong prioritizes nearly 43 billion VND for training officials and teachers in 2026

Hoàng Khôi |

Hai Phong - The City People's Committee has just issued a plan to train and foster to improve the qualifications and capacity of teachers and education management officials in the period 2026-2030.

Groundbreaking ceremony for a craft village industrial cluster project in Thuy Nguyen, Hai Phong

Hoàng Khôi |

Hai Phong - April 6, Hai Phong broke ground on the project to invest in construction and business of technical infrastructure of Thuy Nguyen mechanical and casting craft village industrial cluster.

Close-up of the 500 billion VND sea dike reinforcement project in Ninh Binh to be completed soon

Lương Hà |

Ninh Binh - The Hai Thinh sea dike landslide reinforcement and treatment project with a total capital of about 500 billion VND has reached about 97% of the volume, about to reach the finish line before the rainy and storm season.