400 billion VND project in Da Nang disaster area, urgent on paper, messy on the ground

Hoàng Bin |

Da Nang - As an emergency reconstruction project after natural disasters, but after many years, the nearly 400 billion VND traffic road is still unfinished, causing people to face many difficulties.

Hoàng Bin
RELATED NEWS

400 billion VND emergency traffic project in Da Nang is slow due to a series of bottlenecks

|

Da Nang - Sluggish construction contractors, loose management, and continuous changes in focal points have caused the nearly 400 billion VND traffic reconstruction project in Da Nang mountainous area to be delayed for a long time.

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

|

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

2 years behind schedule, the 575 billion VND road project in Ha Tinh is still facing 11 households

|

Ha Tinh - The Ham Nghi extended road project is behind schedule and has to be extended for another 2 years, and is currently gradually removing site obstacles to hand over to the construction contractor.

Ngan Pho riverbank landslide, people anxiously wait for "ha ba" dyke to save their houses

|

Ha Tinh - Serious landslides along the Ngan Pho River have caused dozens of households in Son Giang commune to live in anxiety, wearyly waiting for the dyke to resist the "ghost" swallowing land.

Large whales return to hunting in Gia Lai waters

|

Gia Lai - A large whale individual appeared hunting near Nhon Ly beach (Quy Nhon Dong ward), creating a fascinating natural scene.

Wood workshop in Duong Lam ancient village catches fire fiercely at dawn

|

According to people's reflections, a wood workshop in the ancient village of Duong Lam area caught fire fiercely.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

400 billion VND emergency traffic project in Da Nang is slow due to a series of bottlenecks

Nhóm PV |

Da Nang - Sluggish construction contractors, loose management, and continuous changes in focal points have caused the nearly 400 billion VND traffic reconstruction project in Da Nang mountainous area to be delayed for a long time.

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

Nhóm PV |

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

2 years behind schedule, the 575 billion VND road project in Ha Tinh is still facing 11 households

TRẦN TUẤN |

Ha Tinh - The Ham Nghi extended road project is behind schedule and has to be extended for another 2 years, and is currently gradually removing site obstacles to hand over to the construction contractor.