400 billion VND project in Da Nang disaster area, urgent on paper, messy on the ground

Hoàng Bin |

Da Nang - As an emergency reconstruction project after natural disasters, but after many years, the nearly 400 billion VND traffic road is still unfinished, causing people to face many difficulties.

Hoàng Bin
RELATED NEWS

400 billion VND emergency traffic project in Da Nang is slow due to a series of bottlenecks

|

Da Nang - Sluggish construction contractors, loose management, and continuous changes in focal points have caused the nearly 400 billion VND traffic reconstruction project in Da Nang mountainous area to be delayed for a long time.

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

|

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

400 billion VND project in Da Nang disaster area, urgent on paper, messy on the ground

|

Da Nang - As an emergency reconstruction project after natural disasters, but after many years, the nearly 400 billion VND traffic road is still unfinished, causing people to face many difficulties.

Asian ships have tickets through Hormuz, thanks to diplomacy with Iran

|

Some Asian countries have reached agreements with Iran to allow some ships to pass through the Strait of Hormuz safely.

Live football U20 Vietnamese women vs U20 Bangladesh women at the 2026 Asian U20 women's tournament

|

Live football match between Vietnam U20 women's team and Bangladesh U20 women's team in the group stage of the 2026 AFC U20 Women's Championship at 8:00 PM tonight (April 7).

Stock market liquidity continues to decline

|

The stock market had a slight recovery session but lacked spreading momentum.

Live Vietnam futsal team vs Timor-Leste at Southeast Asian tournament

|

Live football match of Vietnam futsal team against Timor-Leste in the 2nd match of Group A of the 2026 Southeast Asian Futsal Championship at 5:30 PM today (April 7).

400 billion VND emergency traffic project in Da Nang is slow due to a series of bottlenecks

Nhóm PV |

Da Nang - Sluggish construction contractors, loose management, and continuous changes in focal points have caused the nearly 400 billion VND traffic reconstruction project in Da Nang mountainous area to be delayed for a long time.

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

Nhóm PV |

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

Chậm tiến độ 2 năm, dự án đường 575 tỉ đồng ở Hà Tĩnh vẫn vướng 11 hộ dân

TRẦN TUẤN |

Hà Tĩnh - Dự án đường Hàm Nghi kéo dài bị chậm tiến độ phải gia hạn thêm 2 năm, hiện đang dần được gỡ vướng mặt bằng để bàn giao cho nhà thầu thi công.