Bac Ninh's solutions promote the 86,000 billion project

Vân Trường |

The Ring Road 4 project - Hanoi Capital Region through Bac Ninh province is facing some difficulties in site clearance and supply of embankment materials.

According to the People's Committee of Bac Ninh province, the Ring Road 4 project - Hanoi Capital Region, the section passing through Bac Ninh province is being focused on resources to strive for completion before December 31, 2025 under the direction of the Prime Minister.

However, Bac Ninh province is facing difficulties due to the scarce supply of earth filling materials on the market, while the demand for the project is very large. It is estimated that from now until June 30, 2025, the project will need about 1.34 million m3 of earth filling.

Faced with that situation, the People's Committee of Bac Ninh province has just issued a document requesting the People's Committee of Bac Giang province to consider and create conditions to allow investors and project contractors to access and register their needs for supplying earth filling materials at a number of mines in Bac Giang province.

The mines that meet the project's requirements include: Planned material mines are Ho Gom and Ho Gao mines (Bac Lung commune, Luc Nam district); Deo Hoi mine (Dam village, Vu Xa commune, Luc Nam district); Bot and Ho Va mines (Cam Ly commune, Luc Nam district);

The mines currently being exploited are Ho Dung soil mine (Mo Tho village, Minh Duc commune, Viet Yen town); Nui Khong soil mine (Mo Tho village, Minh Duc commune, Viet Yen town) and a number of other mines licensed for exploitation.

The People's Committee of Bac Ninh province commits that the investor and project contractors will fully comply with regulations on ensuring traffic safety, environmental sanitation and other legal regulations during the process of transporting materials.

Regarding difficulties in site clearance, in the December work program, the People's Committee of Bac Ninh province assigned the Department of Natural Resources and Environment and the Department of Finance to preside over and coordinate in reviewing difficulties and obstacles and proposing solutions to remove them, in order to implement the Ring Road 4 Project to ensure progress as committed by the province.

The project to build Ring Road 4 - Hanoi Capital Region belongs to the group of important national projects, with a total length of 112.8km (including 58.2km through Hanoi, the remaining 9.7km connecting to Hanoi - Ha Long Expressway and the part passing through Hung Yen and Bac Ninh provinces).

The total preliminary investment of the project is 85,813 billion VND, the total volume of site clearance is about 1,386 hectares, on the route to build 3 large bridges over the Red River, Duong River and 8 other intersections.

The 35.3km Beltway 4 project of the Capital region passes through Bac Ninh including 4 districts and towns: Bac Ninh city, Thuan Thanh town and Que Vo, Gia Binh district.

Vân Trường
TIN LIÊN QUAN

The Ministry of Culture requests clarification on the information about fireworks displays in Hue

|

HUE - The Department of Culture requested the Department of Culture and Sports of Hue City to verify the act of fireworks display at Ky Dai on the evening of May 3.

Ukraine launches massive attacks, Russia dismantles wave of UAVs and Western missiles

|

The Russian Defense Ministry announced the successful interception of more than 500 UAVs from Ukraine in the context of the 3-day ceasefire in effect.

Ukraine still maintains the proposal for a 30-day ceasefire

|

President Volodymyr Zelensky said Ukraine would continue to maintain its proposal for a 30-day ceasefire with Russia.

The new papal throne has not yet been elected after the first round of voting

|

Black smoke rose from the chimney of Sistine monastery on the evening of May 7, marking the first round of voting that did not produce results, the new papal remains un select.

Gold price update on the morning of May 8: Declining due to profit-taking wave

|

Gold price update on the morning of May 8 fell due to profit-taking and increased risk-off sentiment. Investors are waiting for the FED Chairman's speech to clarify the upcoming policy direction.

A series of public offices in Ninh Binh are being handled after many years of abandonment

|

Ninh Binh - After many years of abandonment, the surplus public offices due to administrative unit arrangement have been handled, meeting the function of use.

Dự án khu du lịch Thiên Thai ở Bắc Ninh chậm tiến độ

Vân Trường |

Bắc Ninh - Triển khai từ năm 2007 nhưng đến nay, dự án khu du lịch Thiên Thai (xã Đông Cứu, huyện Gia Bình) chưa thể hoàn thành.

Bắc Ninh kết thúc hoạt động 1 sở, sáp nhập 8 sở khi tinh gọn

Trần Tuấn |

Từ 17 cơ quan chuyên môn thuộc UBND tỉnh Bắc Ninh, sau khi sáp nhập sẽ còn 12 đơn vị.

Bắc Ninh lập phương án tinh gọn bộ máy

Trần Tuấn |

UBND tỉnh Bắc Ninh cho biết, tỉnh đang xây dựng phương án sắp xếp các cơ quan thuộc UBND tỉnh để trình các cấp có thẩm quyền.