Beltway 4 through Bac Ninh must be completed by the end of 2025

Trần Tuấn |

Inspecting the progress at the construction site, Prime Minister Pham Minh Chinh requested that the section of Ring Road 4 passing through Bac Ninh be completed by the end of 2025.

On the morning of September 22, during his working program in Bac Ninh, Prime Minister Pham Minh Chinh inspected the progress of the investment project to build Ring Road 4 - Hanoi Capital Region through Bac Ninh and presented gifts to workers at the construction site.

The Ring Road 4 - Capital Region project, belonging to the group of important national projects, passes through 3 provinces and cities (Hanoi, Hung Yen and Bac Ninh), connecting the Hanoi - Lao Cai and Noi Bai - Ha Long expressways with a length of 112.8 km and a total investment of phase 1 of about 85.8 trillion VND. The project started construction in June 2023.

The section through Bac Ninh province has a route length of 35.3 km, including 25.6 km of Ring Road 4 and 9.7 km of the route connecting Ring Road 4 with Noi Bai-Ha Long Expressway. The total investment is 5,274 billion VND.

According to the Resolution of the National Assembly, Bac Ninh is assigned to implement 2 component projects: The component project of compensation, support, and resettlement in Bac Ninh province and the component project of construction of parallel roads in Bac Ninh province.

Thu tuong Chinh phu Pham Minh Chinh dong vien ky su, cong nhan tren cong truong tai thi xa Thuan Thanh. Anh: Nhat Bac
Prime Minister Pham Minh Chinh encouraged engineers and workers at the construction site in Thuan Thanh town. Photo: Nhat Bac

According to the report of Bac Ninh province, regarding the site clearance work, the province has currently handed over 364/374 hectares, accounting for 97.2% of the total site area to the investor, and the remaining 2.8% of the residential land area is expected to be handed over by the end of November 2024. Provincial leaders are resolutely directing the completion of 11 resettlement projects.

Along with that, strive to complete the relocation of technical infrastructure from December 2024 to February 2025, and complete the relocation of high-voltage power systems in February-March 2025.

Regarding the construction organization, the project is divided into 3 packages and organized 24 construction teams. Immediately after the Prime Minister's direction, Bac Ninh province strengthened its direction, removed difficulties and obstacles, and required contractors to work in 3 shifts and 4 teams to speed up the project implementation progress, striving from September to November 2024, to increase the total construction output to more than 400 billion VND, basically completing the project in 2025 (for the sections that have been handed over the site in 2023) and the remaining items in 2026, striving to complete the whole project in April 2026, 7 months ahead of schedule.

However, the biggest difficulty at present is the supply of sand and earth for filling because Bac Ninh does not have any material mines, so it cannot be proactive. Regarding this issue, the province has established an interdisciplinary working group to proactively contact neighboring provinces such as Bac Giang, Lang Son, and Phu Tho to access supply sources.

Thu tuong Chinh phu Pham Minh Chinh tang qua, dong vien ky su, cong nhan tren cong truong. Anh: Nhat Bac
Prime Minister Pham Minh Chinh presents gifts and encourages engineers and workers at the construction site. Photo: Nhat Bac

Checking the progress and encouraging engineers and workers at the construction site in Thuan Thanh town, Prime Minister Pham Minh Chinh directed Bac Ninh province to focus on completing the site clearance so that construction can be carried out as soon as it is available; actively relocating technical works such as power transmission poles; and working and coordinating with other localities to ensure the supply of raw materials.

Clearly stating the view of encouraging local businesses to participate in the project but under one responsible contractor, the Prime Minister requested contractors to mobilize machinery and human resources to work in 3 shifts, "eat and sleep quickly", and work through Tet and holidays.

The locality needs to mobilize the entire political system under the leadership of the Party Committee, military forces, police, youth, women, veterans, trade unions, people... to participate in doing what can be done with the project management board and contractors.

Tinh Bac Ninh yeu cau cac nha thau thi cong 3 ca, 4 kip nham day nhanh tien do thuc hien du an. Anh: Nhat Bac
Bac Ninh province requires contractors to work in 3 shifts and 4 shifts to speed up the project implementation progress. Photo: Nhat Bac

During the construction process, the consulting and supervising force must increase inspection and supervision to ensure quality and progress, and promptly carry out payment and settlement work.

The Prime Minister requested to further shorten the progress, by December 31, 2025, the project section through Bac Ninh province must be completed. The project's early completion will open up new development space. Bac Ninh people and businesses will enjoy it; therefore, leadership and direction must "clearly define the people, the work, the responsibilities, the implementation time, the effectiveness, and the products".

Trần Tuấn
RELATED NEWS

Nguyen Thi Oanh equalizes a record of 15 gold medals in SEA Games athletics

|

The victory in the 3,000m final overcoming obstacles helped Nguyen Thi Oanh equal the record of 15 gold medals in the SEA Games athletics.

Updated gold price at the end of the session on December 16: Deep decrease of 1.6 million VND/tael

|

Updated gold price at the end of the session on December 16: Domestic and world gold both decreased in today's trading session.

Police exposed the tricks of drivers to avoid AI cameras

|

Hanoi - Many drivers use all kinds of methods to cover and blur their license plates to bypass the AI camera.

Accelerating site clearance, Ring Road 1 gradually emerges

|

Hanoi - The site clearance of Ring Road 1 from Hoang Cau to Voi Phuc is in the acceleration phase, with continuous machinery and openings.

After 7 years of sluggish progress, the Cho Mai - Tan My road project in Hue has just completed the asphalt paving

|

HUE - The Cho Mai - Tan My road project with a total investment of nearly 200 billion VND, over 4km long, has just completed asphalt paving after many years of slow construction.

HCMC asks for opinions from 4 ministries on the project of road and overpass connecting Can Gio - Vung Tau

|

Ho Chi Minh City asks for opinions from 4 ministries on the project of the road and overpass connecting Can Gio - Vung Tau proposed by Vingroup, nearly 15 km long, expected to start construction in June 2026.

Live SEA Games 33 today (16.12)

|

Live updated the competitions of the Vietnam Sports Delegation at today's 33rd SEA Games (December 16).

SEA Games 33 Medal Schedule on December 16

|

Updated total medal table of the 33rd SEA Games on December 16.

Tín hiệu đáng mừng trên công trường Vành đai 4 Hà Nội

HỮU CHÁNH |

Hà Nội - Vành đai 4 đoạn qua huyện Sóc Sơn, Mê Linh đang được đẩy nhanh tiến độ thi công. Nhà thầu đã thảm những mét đường nhựa đầu tiên trên công trường dự án.

Hà Nội tăng 110 tỉ đồng cho quận Hà Đông để giải phóng mặt bằng Vành đai 4

KHÁNH AN |

Với nguồn ngân sách Trung ương trong nước, Hà Nội điều chỉnh tăng 110 tỉ đồng cho quận Hà Đông để thực hiện nhiệm vụ giải phóng mặt bằng dự án thành phần 1.1 xây dựng Vành đai 4 - Vùng Thủ đô.

Hình ảnh Vành đai 4 Vùng Thủ đô sau một năm thi công

HỮU CHÁNH |

Tròn một năm từ này khởi công, hình hài "siêu dự án" Vành đai 4 Vùng Thủ đô đã trở nên rõ nét. Hiện các nhà thầu đang đẩy nhanh thi công, đưa công trình về đích đúng tiến độ.