The project is located in the area of Buc hamlet and surrounding areas, Van Son commune, Phu Tho province.
The project is selected for investors through open bidding.
Residential area registered to use land area of about 51.65 ha.
The project focuses on preserving and promoting traditional cultural values of the Muong ethnic group.
The project has a total investment capital of 789,923,000,000,000 VND. The total investment capital structure includes:
Construction investment cost: Approximately 696,475,000 VND.
Compensation and support costs for site clearance and resettlement: Approximately 93,448,000 VND.
The source of capital for implementation is the capital of the winning investor, in which the owner's equity of the investor must ensure at least 15% of the total investment capital.
The project's operating term is 50 years from the date of approval of the investment policy.
The project implementation progress is specifically phased through stages:
From the second quarter of 2026 to the end of the fourth quarter of 2026: Prepare and submit to the Provincial People's Committee for consideration and decision on investment policies; organize bidding to select investors; negotiate, complete and sign project contracts or approve investors.
From the first quarter of 2027 to the end of the first quarter of 2031: Implement site clearance compensation; complete investment procedures and construction of works; organize acceptance, audit, finalization and handover of works for use.
From the second quarter of 2031: Complete all items, organize acceptance, hand over and put the entire project into business operation.
Phu Tho Provincial People's Committee assigned the Department of Construction to preside over the organization of bidding to select investors.
The Department of Finance announced the decision on the National System on bidding.
Van Son Commune People's Committee coordinates to update planning, organize site clearance and receive infrastructure operation after handover.
Investors are responsible for financial capacity, compliance with legal regulations on construction, land, environmental protection, fire prevention and fighting, and protection of irrigation systems and water sources in the area.