The Lang Van super project, Da Nang will complete site clearance in April

Nguyễn Linh |

Da Nang - The Lang Van project is expected to complete site clearance in April, later than the original plan.

The Lang Van Tourism and Resort Complex Project in Da Nang, a super project with a total investment of nearly VND44,000 billion, is facing difficulties in the process of site clearance. Mr. Vo Nguyen Chuong - Deputy Director of the Department of Agriculture and Environment of Da Nang - said that the project site clearance will be completed in April, later than originally expected in early April.

According to Mr. Chuong, the two main problems leading to this delay are the implementation mechanism and land transfer of the people. This is the first time the city has to apply compulsory enforcement and counting measures for such a large -scale project. Normally, coercion is only applied in case the people disagree with the compensation and site clearance plan. The application of compulsory enforcement and counting measures requires thorough preparation of legal and practical, and at the same time need to ensure the legitimate rights of the people affected.

The Lang Van project is expected to become a driving force for Da Nang's economic and social development, contributing to the city's double-digit economic growth target. The project is implemented in Hoa Hiep Bac ward, Lien Chieu district, on an area of nearly 512.2 hectares, with a population of about 19,000 people. The project was approved by the Prime Minister to adjust the investment policy on November 20, 2024.

The goal of the project is to build a complex including commercial and service works, develop eco-tourism combined with low-density accommodation, associated with nature conservation. The project aims to serve the tourism and living needs of local people and domestic and foreign tourists, with a civilized and modern architectural space.

The People's Committee of Da Nang City has approved the land use boundary diagram, adjusting the detailed planning of 1/500 scale for the project. Vinpearl Joint Stock Company was chosen by the People's Committee of Da Nang City to be the project investor on August 27, 2016 and was allocated land and leased land with an area of ​​more than 10 million m2 to implement phase 1 on September 27, 2016. The remaining area of ​​the project has been approved for land use plan, detailed planning of 1/500 scale and approval of investment policies.

Nguyễn Linh
TIN LIÊN QUAN

Da Nang speeds up site clearance for Lang Van project

|

Da Nang is making efforts to complete site clearance for the Lang Van Tourism and Resort Complex project (nearly 44,000 billion VND) in early April.

Da Nang published a newspaper to find landowners of Village project

|

Village project in Da Nang has just been adjusted to 512ha, removing 63ha of natural forest.

Signing the Protocol on export of chili, passion fruit, bird's nest ... to China

|

The Ministry of Agriculture and Environment has signed the Protocol on the export of chili, passion fruit, bird's nest, rice bran to China, and agrees to cooperate in environmental protection and science.

The Mobile Police Command praised, honoring 80 advanced examples

|

Hanoi - Mobile Police Command (Ministry of Public Security) praised and honored 80 advanced individuals in the emulation movement "For national security".

A dairy business admits the advertisement, must apologize

|

While information about hundreds of fake milk brands were exposed, causing a stir in the public opinion, another dairy company had advertising behavior, had to apologize.

Construction broke water pipes, thousands of households lacking water

|

Nghe An - The process of expanding construction of National Highway 46, underground water pipeline broke, causing thousands of households in Kim Lien commune to fall into the situation of losing their daily life for many days.

Proposing notice of not executing death penalty to the person requested to extradite

|

The Draft Law on Conductors has just submitted to the Standing Committee of the National Assembly for the opinion on the notice of not executing the death penalty for the person requested to extradite.

Feedback of the Pickleball card violation in Long Bien after the Lao Dong Newspaper's reflection

|

Hanoi - After the Lao Dong newspaper reflects the status quo of many violating pickleball items in Long Bien has not been dismantled, the People's Committee of Phuc Loi ward has responded.

Da Nang speeds up site clearance for Lang Van project

Nguyễn Linh |

Da Nang is making efforts to complete site clearance for the Lang Van Tourism and Resort Complex project (nearly 44,000 billion VND) in early April.

Da Nang published a newspaper to find landowners of Village project

Nguyễn Linh |

Village project in Da Nang has just been adjusted to 512ha, removing 63ha of natural forest.

Đà Nẵng chuyển đất rừng cho dự án Làng Vân, khu công nghiệp chậm tiến độ

THÙY TRANG |

Sáng 15.11, Hội đồng Nhân dân TP Đà Nẵng đã tổ chức kỳ họp chuyên đề. Tại đây, các đại biểu đã thống nhất thông qua việc chấp thuận chủ trương chuyển mục đích sử dụng rừng sang mục đích khác với 4 dự án, trong đó có dự án khu du lịch Làng Vân và Khu công nghiệp Hòa Ninh đang bị chậm tiến độ.