Construction broke water pipes, thousands of households lacking water

QUANG ĐẠI |

Nghe An - The process of expanding construction of National Highway 46, underground water pipeline broke, causing thousands of households in Kim Lien commune to fall into the situation of losing their daily life for many days.

The project of renovating and upgrading National Highway 46 of Vinh - Nam Dan city has a total investment of VND 500 billion, invested by the Project Management Board 85 (Ministry of Construction) as an investor, Hoa Hiep Co., Ltd is a construction unit. The incident occurred in the area of ​​Mau 3 hamlet (Kim Lien commune) when the machine leveled the ground, breaking the water supply pipeline from the White Bridge Water Plant.

According to the people's reflection, dehydration has lasted for 3 days, affecting the daily life of more than 2,800 households. Some households have to buy bottles, ask well water from neighbors, or take advantage of rainwater to hold in the hot weather.

Hang nghin ho dan xa Kim Lien, huyen Nam Dan bi thieu nuoc sinh hoat. Anh: Quoc Huy
Thousands of households in Kim Lien commune, Nam Dan district have shortage of domestic water. Photo: Quoc Huy

"The whole neighborhood of nearly 300 households did not have clean water. My family had to catch rainwater to use, very miserable. Hope the parties will soon overcome," said N.D.H, the people of Lien Mau 1 hamlet, pressing.

Noted at the scene, the broken pipeline area has not been overcome. Some machines continue construction, while the water supply unit, contractor and investor have not made a clear repair move.

Mr. Nguyen Quang Loc - Chairman of Kim Lien Commune People's Committee confirmed the incident and said that he had contacted the water supply unit, currently "waiting for coordination". Meanwhile, the representative of the project management board said that the underground water pipeline has not been handed over the full ground, so it arises in construction.

The people of Kim Lien commune are looking forward to the parties involved early to overcome to have clean water to use again.

QUANG ĐẠI
TIN LIÊN QUAN

Withdrawing water for golf course nearly VND 400 billion in Thai Nguyen

|

Thai Nguyen - Glory Golf Project in Pho Yen City has a total investment of VND 388 billion, after a long time of construction has basically completed.

Construction site of park and lake over 20ha wide in Long Bien

|

Hanoi - Excavators, windbreakers and dozens of workers are constructing items at the park and lake project of more than 20 hectares in Long Bien.

Signing the Protocol on export of chili, passion fruit, bird's nest ... to China

|

The Ministry of Agriculture and Environment has signed the Protocol on the export of chili, passion fruit, bird's nest, rice bran to China, and agrees to cooperate in environmental protection and science.

The Mobile Police Command praised, honoring 80 advanced examples

|

Hanoi - Mobile Police Command (Ministry of Public Security) praised and honored 80 advanced individuals in the emulation movement "For national security".

A dairy business admits the advertisement, must apologize

|

While information about hundreds of fake milk brands were exposed, causing a stir in the public opinion, another dairy company had advertising behavior, had to apologize.

Construction broke water pipes, thousands of households lacking water

|

Nghe An - The process of expanding construction of National Highway 46, underground water pipeline broke, causing thousands of households in Kim Lien commune to fall into the situation of losing their daily life for many days.

Proposing notice of not executing death penalty to the person requested to extradite

|

The Draft Law on Conductors has just submitted to the Standing Committee of the National Assembly for the opinion on the notice of not executing the death penalty for the person requested to extradite.

Feedback of the Pickleball card violation in Long Bien after the Lao Dong Newspaper's reflection

|

Hanoi - After the Lao Dong newspaper reflects the status quo of many violating pickleball items in Long Bien has not been dismantled, the People's Committee of Phuc Loi ward has responded.

Tỉnh lộ 166 ở Yên Bái như vũng trâu đầm, 4 năm chưa thi công xong 6km đường

Văn Đức - Bảo Nguyên |

Yên Bái - Tỉnh lộ 166 đang trong quá trình thi công cùng với việc mỗi ngày hàng trăm lượt xe trọng tải lớn lưu thông khiến đường lầy lội mỗi khi mưa xuống.

Withdrawing water for golf course nearly VND 400 billion in Thai Nguyen

Lam Thanh |

Thai Nguyen - Glory Golf Project in Pho Yen City has a total investment of VND 388 billion, after a long time of construction has basically completed.

Construction site of park and lake over 20ha wide in Long Bien

KHÁNH AN - HỮU CHÁNH |

Hanoi - Excavators, windbreakers and dozens of workers are constructing items at the park and lake project of more than 20 hectares in Long Bien.