Promoting the progress of site clearance for a road worth more than 4,900 billion VND in Hung Yen

Lương Hà |

Hung Yen - Localities are focusing on accelerating site clearance for the road project worth more than 4,900 billion VND.

On March 11, Mr. Lai Van Hoan - Vice Chairman of the Provincial People's Committee - chaired a meeting to listen to the Management Board of Construction Investment Project No. 2 and related units and localities report on the progress of site clearance (GPMB) of the investment project to build a road from Thai Binh ward to Hung Ha commune connecting to Pho Hien ward.

According to the report; the project has a length of 24.8km; total investment of more than 4,900 billion VND from the provincial budget and central budget support. Project implementation period is 2025 - 2028.

The project is divided into 2 phases of investment, in which phase 1 from National Highway 10 intersection to Dong Tu intersection is 18.86km long; phase 2 from Dong Tu intersection to the end of the route is 5.94km long. For phase 1, construction units are implementing 2 main bidding packages including building the Tra Ly river overpass and constructing the road section.

Regarding site clearance, by March 2026, 17.09km/18.86km had been completed, equivalent to 83.34ha/93.36ha; the remaining 1.77km (10.62ha) has not been completed, mainly related to converted land and some households' residential land, production and business land in localities such as Nam Tien Hung, Tien Hung and Hung Ha.

Concluding the meeting, Vice Chairman of Hung Yen Provincial People's Committee Lai Van Hoan requested departments, branches, localities and construction units to strengthen coordination, focus on removing difficulties, accelerate site clearance progress, complete resettlement areas and relocate technical infrastructure.

The Vice Chairman of the Provincial People's Committee assigned the Land Fund Development Center No. 2 to coordinate with Hung Yen Power Company to urgently develop a plan to relocate the power grid infrastructure within the project area; the Department of Agriculture and Environment to coordinate with contractors and the Project Management Board to remove difficulties in filling material sources, and accelerate procedures for allocating specialized material mines for construction.

In addition, localities strengthen propaganda and mobilize people to agree to hand over land; contractors mobilize human resources and equipment to accelerate construction progress, ensuring quality, safety and project implementation progress.

Lương Hà
RELATED NEWS

Leaders of Quang Ngai Provincial People's Committee urge progress in site clearance for VSIP project of over 1,100 ha

|

Quang Ngai - The VSIP project is being accelerated in site clearance. The Provincial People's Committee requests to ensure people's rights and hand over 360ha in 2026.

Hanoi focuses efforts on site clearance to build a road nearly 3.8km long and 21m wide

|

Hanoi - Phuc Tho commune strives to complete site clearance work in March 2026 to construct the Provincial Road 416 project, nearly 3.8km long and 21m wide.

Accelerate site clearance for Ninh Binh - Hai Phong expressway through Hung Yen

|

Hung Yen - The Ninh Binh - Hai Phong expressway project (CT. 08) section passing through Hung Yen province is being urgently cleared by localities.

Two "woodblocks - trấn trạch seals" artifacts at Phu Tien Huong of unknown origin

|

Ninh Binh - Two artifacts called "woodblocks - trấn trạch seals" being kept at Tien Huong palace have been identified as having no records or origin.

Ho Chi Minh City adjusts Thu Thiem planning to build a new administrative center, 99-story tower

|

Ho Chi Minh City adjusts the planning of Thu Thiem to build a new Political - Administrative Center, a 99-story financial tower, and adjusts the location of the Children's Palace and the Opera House.

Ministry of Education announces 6 adjustments in the 2026 high school graduation exam regulations

|

Circular No. 13/TT-BGDDT amending and supplementing a number of articles of the High School Graduation Exam Regulations has 6 outstanding new articles, according to the announcement of the Ministry of Education and Training.

The second largest oil refinery in the country operates effectively to ensure gasoline and oil supply

|

Dung Quat Oil Refinery is operating at a capacity of 124-125%, contributing to ensuring gasoline and oil supply and stabilizing the domestic market.

Elderly voters in Hanoi follow every piece of information about the election day

|

Hanoi - The atmosphere of the election day is bustling, spreading from major streets to every small alley, making many people clearly feel solemnity and excitement.

Leaders of Quang Ngai Provincial People's Committee urge progress in site clearance for VSIP project of over 1,100 ha

ĐÔNG GIANG |

Quang Ngai - The VSIP project is being accelerated in site clearance. The Provincial People's Committee requests to ensure people's rights and hand over 360ha in 2026.

Hanoi focuses efforts on site clearance to build a road nearly 3.8km long and 21m wide

SÓNG HỮU |

Hanoi - Phuc Tho commune strives to complete site clearance work in March 2026 to construct the Provincial Road 416 project, nearly 3.8km long and 21m wide.

Accelerate site clearance for Ninh Binh - Hai Phong expressway through Hung Yen

Mai Hương - Lương Hà |

Hung Yen - The Ninh Binh - Hai Phong expressway project (CT. 08) section passing through Hung Yen province is being urgently cleared by localities.