Progress of site clearance for a 120-180m wide road project in Hanoi

SÓNG HỮU |

Hanoi - The progress of site clearance for a 6.7km long, 120-180m wide road is being accelerated by the locality according to the city's direction.

The investment project to build the Thang Long Avenue expressway, the section connecting National Highway 21 to the Hanoi - Hoa Binh expressway, started in October 2023.

The project has a total investment of 5,249 billion VND, invested by the Hanoi Civil Works Construction Investment Project Management Board. The city plans to complete a 6.7km long road with a cross-section of 120-180m in 2026.

According to the assessment of the Hanoi People's Committee, the project implementation will gradually complete the entire Hanoi - Hoa Binh expressway; develop and expand Hanoi Capital to the West, meeting the increasing transportation demand; and be a driving force for the development of Hoa Lac satellite city and the Western satellite city chain.

Hoa Lac Commune People's Committee said that the project to build the Thang Long Avenue expressway, the section connecting National Highway 21 to the Hanoi - Hoa Binh expressway through the commune, has a total of 688 land plots to be recovered, with a total area of about 60.56 ha.

In which, before the implementation of the 2-level local government model, site clearance work had been deployed and completed by all levels of government for 188 land plots.

From July 1, 2025, after implementing the 2-level local government model, the remaining 500 land plots of the project will be directly assigned by the City to Hoa Lac Commune People's Committee to organize site clearance work, with the required completion schedule before February 15, 2026.

This is a very large workload, urgent time, high requirements for progress and legality, requiring the synchronous and drastic involvement of the entire socio-political system.

a
Leaders of Hoa Lac commune regularly go to the field to inspect the current situation, direct the removal of obstacles; meet, propagate, mobilize, and dialogue with households in site clearance. Photo: TTĐT Hoa Lac commune

By January 29, Hoa Lac commune had completed 100% counting of all 500/500 allocated land plots, contributing to completing the counting of 688/688 plots of the entire project, clearly showing the spirit of responsibility, determination and drastic action of the commune Party Committee and government in performing the tasks assigned by the City.

In the process of implementation, many households have shown a high consensus spirit, proactively handing over the site before approving the compensation plan, with 6.63 ha/43 plots of 36 households, showing consensus and support for the policy of land recovery to serve the capital's key project.

In parallel with the inventory work, the commune's specialized agencies are urgently completing dossiers, publicizing plans, pricing, and paying compensation, support, and resettlement according to regulations, ensuring the progress of site clearance as required by the City.

SÓNG HỮU
RELATED NEWS

Land clearance for National Highway 6: Hanoi sets deadline to complete in 3 wards

|

Hanoi requests Yen Nghia, Duong Noi, and Kien Hung wards to complete site clearance for National Highway 6, Ba La - Xuan Mai section, in accordance with the progress commitment.

Long Bien accelerates site clearance for Tran Hung Dao bridge

|

Hanoi - Long Bien Ward strengthens dialogue and specific explanations so that people understand clearly, feel secure and agree to implement the site clearance of Tran Hung Dao bridge.

9th Hour No. 190: Short Happiness - Part 2

|

Hour 9 - Husband's career advancement suddenly strays to adultery. Facing cruel betrayal while being happy, how will the wife handle it?

Voters in mountainous Da Nang reflect on the worry of landslides, hoping to escape poverty sustainably

|

Da Nang - Voters hope that the commitments of National Assembly candidates will not only stop at promises but become long-term actions for mountainous areas.

US responds to news of Russia providing locations of US warships and aircraft to Iran

|

The Pentagon affirmed that US forces are monitoring the activities of Russia and Iran amid escalating conflict in the region.

Road worth over 1,300 billion VND in Hanoi completed all items in March

|

Hanoi - Ring Road 2.5 project, Dam Hong - National Highway 1A section, 1.6km long, with a total capital of over 1,300 billion VND, will complete all items in March 2026.

Ho Chi Minh City traffic police ambush and film violating motorbikes

|

Ho Chi Minh City - Traffic police deploy ambushes, filming many motorbikes intentionally crossing the railway when red lights and barriers have lowered, posing a risk of traffic accidents.

The mother burst into tears when she first heard her child call "mother" after 3 years of waiting

|

During the days of persistently accompanying her congenitally hearing impaired child, the mother burst into tears when she first heard her child call "mother" after 3 years.

Land clearance for National Highway 6: Hanoi sets deadline to complete in 3 wards

Minh Hạnh |

Hanoi requests Yen Nghia, Duong Noi, and Kien Hung wards to complete site clearance for National Highway 6, Ba La - Xuan Mai section, in accordance with the progress commitment.

Long Bien accelerates site clearance for Tran Hung Dao bridge

KHÁNH AN |

Hanoi - Long Bien Ward strengthens dialogue and specific explanations so that people understand clearly, feel secure and agree to implement the site clearance of Tran Hung Dao bridge.

Phường Thanh Xuân chưa hoàn thành giải phóng mặt bằng dự án đường Nguyễn Tuân

SÓNG HỮU |

Hà Nội - Dự án mở rộng đường Nguyễn Tuân (phường Thanh Xuân) đang vướng một nhà tập thể 2 tầng liên quan đến 6 hộ dân.