Latest progress on land recovery for road construction worth more than 9,590 billion VND in Hanoi

SÓNG HỮU |

Hanoi - Wards and communes are accelerating the progress of land recovery and site clearance to expand National Highway 6, Ba La - Xuan Mai section, with a total investment of more than 9,590 billion VND.

The project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section, has a total length of 21.7 km, passing through many communes and wards in Hanoi. The project started construction at the end of 2022, with a total investment of more than 9,590 billion VND.

The project through Chuong My ward has a length of 3.658 km, with a total recovered area of about 21.1 ha/814 land plots.

As of May 6, site clearance (GPMB) has achieved initial results: the ward has handed over to the investor 1.62/3,658 km (reaching 44.28%), equivalent to 9.21 ha with 194/814 land plots.

In which, the area of Chuc Son town (old) and Tien Phuong commune (old) achieved a high handover rate, mainly public land and agricultural land; especially the Bien Giang ward area (old) progress is still slow, reaching about 10.2%. Currently, about 1.45 km is under construction.

Regarding inventory work, 787/814 land plots have been investigated and surveyed; 100% land recovery notices have been issued. However, there are still some cases that have not coordinated inventory, have not confirmed the origin of land, affecting the overall progress. The total volume to be implemented is 620/814 plots.

s
Construction site of National Highway 6 expansion project, Ba La - Xuan Mai section. Photo: Song Huu

Local authorities have also pointed out difficulties and obstacles in the implementation process such as: Some land areas have not clearly identified the origin and owners due to the process of buying and selling through many generations of owners; some households have not agreed with the compensation plan; the disclosure of the plan has not been completed; the resettlement land fund is still limited...

Leaders of Chuong My ward have directed relevant units to specifically review each case that still has problems, develop a clear handling roadmap, strengthen coordination, mobilize maximum resources, strive to accelerate the site clearance progress, ensuring completion before June 30, 2026 according to the city's direction.

s
The National Highway 6 - Ring Road 4 intersection item is under construction, April 2026. Photo: Song Huu

The project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section passing through Phu Nghia commune has a length of about 7.8 km. The total area to be recovered for site clearance is 29.65 ha with 1,366 land plots.

Statistics as of May 5, Phu Nghia Commune People's Committee has issued 1,366/1,366 land acquisition notices. In which, 100% of plots have been investigated, inventoried, supplemented information, confirmed land origin and completed draft plans for support, compensation and resettlement. The Commune People's Committee has also approved 866 plans; has issued land acquisition decisions for 640 plots.

The total recovered area for the project of renovating and upgrading National Highway 6, Ba La - Xuan Mai section in Phu Nghia commune is 25.29/29.65ha, reaching over 85% of the land area to be recovered.

With the goal of completing site clearance for the project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section passing through the commune in the second quarter of 2026, the Site Clearance Steering Committee and Phu Nghia Commune People's Committee directed the Commune Economic Department to coordinate with the Hanoi Traffic Works Project Management Board to continue appraising the compensation, support and resettlement plan and are expected to complete it in May 2026. At the same time, approve the plan, proceed to pay and issue decisions to recover land for site clearance for the remaining 4.36 ha.

s
National Highway 6 is narrow and often congested. Photo: Song Huu

In Xuan Mai commune, the project passing through the area has a length of 6.53 km, the total land acquisition area is 38.58 ha with 1,804 land plots, related to about 1,376 households and individuals.

In which, residential land of households accounts for 917 plots with an area of 8.31 ha; in addition, there are also agricultural land, public land, national defense and security land and land of many agencies and organizations.

As of May 5, the whole commune has completed measurement and inventory work and is implementing land origin identification, preparing and appraising compensation, support, and resettlement plans. The total area handed over reached 24.9 ha, equivalent to 64.5%.

Notably, over 550 households have voluntarily handed over land, in which many households, although not eligible for compensation and support, are still willing to dismantle works and hand over land for the common development purpose.

SÓNG HỮU
RELATED NEWS

Commune in Hanoi recovers land for 3 projects, there are still cases of disagreement

|

Hanoi - The process of land acquisition to implement 3 projects in Dan Hoa commune still faces some difficulties and obstacles, including households that have not agreed.

There are cases where land origin confirmation has not been coordinated, affecting the progress of upgrading National Highway 6

|

Hanoi - According to Chuong My Commune People's Committee, there are currently cases where there is no coordination in counting and confirming the origin of land, affecting the progress of the National Highway 6 upgrade project.

60m wide road project in Hanoi: Commune requests people to comply with land acquisition policy

|

Hanoi - Phu Nghia commune requests people to comply with the policy of land recovery and hand over land for the National Highway 6 expansion project according to regulations.

Hanoi recovers land from 102 organizations and households in the inner city to build a project around Re Quat Lake

|

Hanoi - Khuong Dinh Ward will recover 15,343.5 m2 of land related to 102 organizations, households, and individuals to implement a project to build technical infrastructure around Re Quat Lake.

Hanoi diverts traffic at La Thanh - Nguyen Chi Thanh intersection from May 18

|

Hanoi adjusts traffic organization at La Thanh - Nguyen Chi Thanh intersection from May 18 to serve the construction of overpasses under the Ring Road 1 project.

Retired life of "golden hour artist" Tu Oanh, People's Artist Bui Bai Binh

|

Stage and film artists such as People's Artist Bui Bai Binh, People's Artist Lan Huong, Tu Oanh... after retiring become sought-after, continuously participating in projects.

Energy transition, develop green transportation to promote sustainable growth

|

Energy saving, energy transition and green transportation development are important solutions to promote sustainable growth.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Commune in Hanoi recovers land for 3 projects, there are still cases of disagreement

SÓNG HỮU |

Hanoi - The process of land acquisition to implement 3 projects in Dan Hoa commune still faces some difficulties and obstacles, including households that have not agreed.

There are cases where land origin confirmation has not been coordinated, affecting the progress of upgrading National Highway 6

Anh Tuấn |

Hanoi - According to Chuong My Commune People's Committee, there are currently cases where there is no coordination in counting and confirming the origin of land, affecting the progress of the National Highway 6 upgrade project.

60m wide road project in Hanoi: Commune requests people to comply with land acquisition policy

SÓNG HỮU |

Hanoi - Phu Nghia commune requests people to comply with the policy of land recovery and hand over land for the National Highway 6 expansion project according to regulations.

Hanoi recovers land from 102 organizations and households in the inner city to build a project around Re Quat Lake

SÓNG HỮU |

Hanoi - Khuong Dinh Ward will recover 15,343.5 m2 of land related to 102 organizations, households, and individuals to implement a project to build technical infrastructure around Re Quat Lake.