HCMC clears 466 households, widens 25m road, 4 lanes in District 12

MINH QUÂN |

HCMC - District 12 is speeding up the land acquisition progress of 466 households in Tan Thoi Hiep ward to widen Tan Thoi Hiep 21 road from 6 - 7m to 25m.

On June 22, the People's Committee of District 12 announced that the project to upgrade and expand Tan Thoi Hiep 21 road is over 1.7km long and 25m wide, with a total reclaimed land area of about 15,480m2.

The project affects 466 households, of which 407 cases have agreed to hand over the land and receive compensation, reaching a rate of 87.3%. The total amount paid to households is more than 855 billion VND.

According to the People's Committee of District 12, there have been 238 cases of house repairs to hand over the site. The project is expected to start construction on June 24.

However, there are still some households that have not coordinated in compensation and site clearance and have not repaired their houses to hand over on schedule.

District 12 is continuing to mobilize the remaining households to promptly agree to receive compensation, support and hand over the site, to ensure the project is implemented on schedule.

Duong Tan Thoi Hiep 21 (Quan 12). Anh: Anh Tu
Tan Thoi Hiep 21 Street (District 12). Photo: Anh Tu

The Tan Thoi Hiep 21 road expansion project is expected to be completed and put into use in 2026.

When completed, the route will help increase traffic capacity, solve flooding problems, improve drainage systems and beautify the urban beauty of the area.

This is one of the important traffic routes in District 12, connecting two major roads, National Highway 1 and Duong Thi Muoi, but the current status of the road surface is narrow, degraded and often congested and flooded due to the lack of a complete drainage system.

Hien trang duong Tan Thoi Hiep 21. Anh:  Anh Tu
Current status of Tan Thoi Hiep 21 Street. Photo: Anh Tu

The project to upgrade and expand Tan Thoi Hiep 21 road was approved by the Ho Chi Minh City People's Council in 2015, with a total cost of more than 403 billion VND.

Initially, the road was planned to be widened to 16m, however, due to problems in compensation and site clearance, after many years, the project has only been able to construct a box culvert section along the route.

By September 2024, the Ho Chi Minh City People's Council had approved an adjustment to the investment policy, raising the total investment to VND 1,364 billion.

This adjustment includes widening the road surface from 16m to 25m, adding compensation costs, resettlement support, and building an additional 320m culvert on Duong Thi Muoi Street.

MINH QUÂN
TIN LIÊN QUAN

HCMC finalizes the start date of the nearly 500 billion VND bridge, improving traffic in the South

|

HCMC - The Rach Tom Bridge project on the main route of Le Van Luong (Nha Be District) with a total investment of nearly 500 billion VND will start construction on June 27.

HCMC is about to build Vam Thuat Bridge, a dream bridge connecting District 12 and Binh Thanh

|

HCMC - The Vam Thuat bridge project connecting An Phu Dong ward (District 12) and ward 13 (Binh Thanh district) is expected to be submitted to the competent authority for approval in 2025.

Ho Chi Minh City road expansion not completed after 8 years, capital increased by 1,364 billion VND

|

HCMC - The Tan Thoi Hiep 21 road expansion project is over 1.7km long with a total investment of VND1,364 billion, expected to be completed in 2026 to reduce traffic jams and flooding.

Driver drives a dangerous car along National Highway 1, traffic police patrol through and immediately support rescue

|

Binh Thuan - A driver was driving a car on National Highway 1 when he fell into a coma and was in critical condition. The traffic police patrol team passing by called an ambulance to assist in the emergency situation.

Glory of Vietnam 2025 - Pride and Aspiration

|

The Vietnam Glory Program in 2025 with the theme "Pride and Aspiration" honors 19 typical advanced collectives and individuals with outstanding achievements in key areas. They are quiet but persistent, creative flowers, committed to contributing to the appearance of Vietnam today.

Iran denies nuclear fortress wiped out after US airstrike

|

Iranian officials denied Mr Trump's claim that three of Iran's key nuclear facilities were wiped out after the airstrikes conducted by the US and Israel.

After 1 week of trial operation of the 2-level government model in Ho Chi Minh City

|

HCMC - About a week from the official operation of the 2-level government model, the new wards are trying to test the apparatus, ensuring progress.

The stock market may see an adjustment

|

With the indicators unable to break out and cash flow showing clear signs of caution, the stock market is likely to have an adjustment.

HCMC finalizes the start date of the nearly 500 billion VND bridge, improving traffic in the South

MINH QUÂN |

HCMC - The Rach Tom Bridge project on the main route of Le Van Luong (Nha Be District) with a total investment of nearly 500 billion VND will start construction on June 27.

HCMC is about to build Vam Thuat Bridge, a dream bridge connecting District 12 and Binh Thanh

MINH QUÂN |

HCMC - The Vam Thuat bridge project connecting An Phu Dong ward (District 12) and ward 13 (Binh Thanh district) is expected to be submitted to the competent authority for approval in 2025.

Ho Chi Minh City road expansion not completed after 8 years, capital increased by 1,364 billion VND

TÚ QUỲNH |

HCMC - The Tan Thoi Hiep 21 road expansion project is over 1.7km long with a total investment of VND1,364 billion, expected to be completed in 2026 to reduce traffic jams and flooding.