According to Lao Dong's research, Erex Japan Joint Stock Company is investing in 2 projects in Yen Bai province. Of which, the Erex Sakura Yen Bai Biomass Fuel Factory Project started construction in July 2023, on an area of over 6 hectares in Bac Van Yen Industrial Cluster, Dong Cuong Commune, Van Yen District.
The project has a total investment of 509 billion VND to produce 150,000 tons of energy Compressors and 150,000 tons of wood chips/year. According to the plan, the project will be completed and put into operation in the third quarter of 2025
Next is the Yen Bai 1 Biomass Power Plant Project, with a total estimated investment of over VND 2,900 billion on an area of nearly 11 hectares in Bac Van Yen Industrial Cluster, with a designed capacity of 50 MW of biomass power/year. The factory is expected to start operation in early 2027.
In late May, present at Bac Van Yen Industrial Cluster (Dong Cuong Commune, Van Yen District), Lao Dong Newspaper reporters recorded a large area being leveled.
At the construction site, many machines have been gathered for construction, and drainage and embankment items are being constructed and installed.




However, many locations have not been filled, the leveling points have interrupted the section with the section without the section. In addition, the wastewater treatment system, traffic infrastructure of the Industrial Cluster are not complete, there is no power grid system...
According to the investigation, the Erex Sakura Yen Bai Biomass Fuel Factory Project has completed the signing of a land lease contract after nearly 2 years of implementation, was granted a land use right certificate, and completed the 3-hectare site clearance work...
Currently, the project is completing land procedures, preparing land lease applications and issuing an Expanded Land Use Rights Certificate. The project is still facing difficulties and problems in land recovery and compensation.
For the Yen Bai 1 Biomass Power Plant Project, there are still some problems and difficulties in the dossier to adjust the project investment policy; the connection road from Provincial Road 163 has not been completed.




Some other reasons for the delay are due to the lack of route for the 110kV transmission line; no connection of wastewater to the plant; negotiation of signing a power purchase agreement (PPA) takes a lot of time due to the application of a new price framework after the current FIT power purchase price mechanism is canceled...
In addition, due to problems in site clearance related to the road surrounding the thermal power plant area... both of these trillion-dong projects are behind schedule compared to the plan.
To remove difficulties and speed up the implementation of projects of Erex Joint Stock Company, the People's Committee of Yen Bai province recently held a meeting between investors, provincial leaders, departments, branches and local authorities.
Mr. Ngo Hanh Phuc - Vice Chairman of Yen Bai Provincial People's Committee suggested that relevant departments, branches, members of the working group together with Van Yen District People's Committee should promptly focus on removing difficulties and speeding up the progress of projects of Erex Japan Joint Stock Company.
In particular, relevant departments and branches and Van Yen District People's Committee support investors in completing procedures on environment and land according to regulations; urgently completing site clearance, ensuring technical infrastructure systems... Striving to start construction of the Biomass Power Plant in October 2025, practically achieving achievements to celebrate the Party Congress at all levels.