According to reports from localities, units, and Nam Trieu ward, there are currently 3 projects to exchange defense land (5 locations) invested by the Hai Phong Civil Works Construction Investment Project Management Board with a total area of over 42 hectares. The area has 35 households using land without documents, 11 households have expired or are about to expire.
In Thuy Nguyen ward, there are currently 10 projects under site clearance, of which 8 projects are on national defense land and 2 projects are in the new urban area of the North Cam River. The main problem of the projects comes from verifying the origin of land to implement compensation and support.
The Standing Vice Chairman of the City People's Committee Le Anh Quan directed that for the items of technical infrastructure returned such as canals, ditches, and traffic routes in Nam Trieu ward, relevant departments and branches should promptly appraise and determine the investor for the Nam Trieu Ward People's Committee to implement. In particular, the VSIP Hai Phong Urban, Industrial and Service Area Project, currently has not met the needs for site clearance. The city is considering adding a new land fund to speed up progress.
In Thuy Nguyen ward, the Standing Vice Chairman of the City People's Committee requested the Thuy Nguyen Project Management Board to speed up the site clearance progress for the Bac Song Cam project and defense land, striving to complete it in November. For those who do not comply, enforcement will be organized in December, especially the VSIP connection road and the relocation of the gasoline unit to be completed before Tet.