Considering fines for Phu Thinh Social Housing project behind schedule

Duy Tuấn |

The leaders of Binh Thuan province proposed to consider sanctioning the investor of the Phu Thinh Social Housing Apartment Complex project for implementing the project late according to the set schedule.

On the afternoon of February 19, Permanent Vice Chairman of Binh Thuan Provincial People's Committee Phan Van Dang chaired a working session with relevant departments, branches and Phan Thiet City People's Committee to propose a direction to handle the slow progress of social housing delivery to people at the Phu Thinh Social Housing Apartment Complex project, Hung Long ward (now Binh Hung ward), Phan Thiet city.

Phu Thinh Social Housing Apartment Project of Phu Thinh Real Estate Investment and Trading Company Limited with a land area of 8,591.27 m2, total investment capital of VND 868.3 billion. The project has a scale of 3 20-storey apartment blocks with 712 apartments (540 social housing apartments, 142 commercial apartments). After starting construction in January 2020, the project is expected to complete the construction items and put into use by June 2024. However, up to now, the project has been ahead of schedule, but has not yet completed construction and has not handed over the house to the buyer.

According to the report of the Department of Construction at the meeting, on January 14, 2025, representatives of departments and branches organized a field inspection at the project. Through inspection, the project has completed the rough construction and is in the process of completing 3 blocks A, B, C. At the time of inspection, the project had no construction.

It is known that this is a social housing development project to serve the housing needs of low-income people, the investor has sold and collected money from customers but has not yet handed over the houses according to the signed contract. This has made many customers buying houses in the project worried and filed a class action lawsuit.

Phu Thinh Company believes that the company has not yet paid or is obliged to deposit to ensure the project's implementation, with the reason that the company has paid a huge amount of money to compensate for site clearance for the project, this amount is larger than the investment deposit cost of the project. According to this company, in mid-February 2025, it will strive to speed up the construction progress to meet the committed schedule.

At the same time, this investor recommended that the People's Committee of Phan Thiet city and departments and branches pay attention to implementing the construction of Road No. 2 in the project in sync with the project that has been committed by the People's Committee of Phan Thiet city, as a basis for disbursing credit capital for project construction.

Du an Khu chung cu can ho nha o xa hoi Phu Thinh bi cham tien do. Anh: Duy Tuan
The Phu Thinh Social Housing Apartment Project is behind schedule. Photo: Duy Tuan

Permanent Vice Chairman of Binh Thuan Provincial People's Committee Phan Van Dang requested relevant departments and branches to quickly arrange a direct working session with Phu Thinh Company to urge and remind the company to focus on human and material resources to implement this project.

The leaders of the Provincial People's Committee also requested the Department of Planning and Investment to review whether Phu Thinh Company has not made a deposit due to fulfilling its obligation to compensate for site clearance for project construction in accordance with the provisions of law or not. At the same time, consider administratively sanctioning the company for being slow to implement the project according to the set schedule and having a detailed report on the project progress sent to the Provincial People's Committee.

The Department of Construction focuses on monitoring and urging Phu Thinh Company to implement the project's construction progress. Accordingly, it is necessary to focus on completing each block of houses to create changes in the progress of the project.

Phan Thiet City People's Committee was assigned to speed up the implementation of route No. 2 in the project and urgently complete the investment policy dossier connecting route No. 2 to Ton Duc Thang Street to submit to competent authorities.

Duy Tuấn
TIN LIÊN QUAN

Social housing projects for Binh Thuan workers to register

|

Many workers and laborers in Binh Thuan want to register to buy or rent social housing to have a place to live and conveniently go to work.

Progress of 5 social housing projects in Binh Thuan

|

Binh Thuan currently has 5 social housing projects and housing for industrial park workers approved for investment by the Provincial People's Committee, which have been and are being implemented with about 8,588 apartments.

Live football Hoang Anh Gia Lai 0-0 Hanoi: First half

|

Live match between Hoang Anh Gia Lai and Hanoi in round 14 of V.League 2024-2025, taking place at 5:00 p.m. today (February 21).

Warning of the risk of fire and explosion from drying clothes during the wet season

|

The Northern provinces are in humid weather conditions. Therefore, the demand for people to use clothes dryers is increasing.

Finding solutions to better care for union members and workers

|

Hanoi - On February 21, the Presidium of the Vietnam General Confederation of Labor held the 10th conference, term XIII, chaired by Mr. Nguyen Dinh Khang - Member of the Party Central Committee, President of the Vietnam General Confederation of Labor. One of the contents discussed is to find solutions to organize implementation to increasingly better care for the material and spiritual life of union members and workers...

Surprised by Mr. Trump's support rate after 1 month in office

|

US President Donald Trump is facing a not-so-comfortable reality: support for him is declining after 1 month in office.

Big fire at hotpot restaurant and pharmacy in Ho Chi Minh City

|

HCMC - The fire broke out from a hotpot restaurant and then spread to a pharmacy next door on Huynh Tan Phat Street, District 7, burning down many properties.

Investor apologizes, promptly handles the incident when digging the metro tunnel

|

The incident of additives during the digging of the Nhon - Hanoi Railway Station metro tunnel floating onto the ground is being urgently handled and the cause is being verified.

Social housing projects for Binh Thuan workers to register

Duy Tuấn |

Many workers and laborers in Binh Thuan want to register to buy or rent social housing to have a place to live and conveniently go to work.

Progress of 5 social housing projects in Binh Thuan

Duy Tuấn |

Binh Thuan currently has 5 social housing projects and housing for industrial park workers approved for investment by the Provincial People's Committee, which have been and are being implemented with about 8,588 apartments.

Nhiều dự án nhà ở xã hội tại Bà Rịa - Vũng Tàu chậm tiến độ

Thành An |

Bà Rịa - Vũng Tàu - Dự kiến phát triển 12.798 căn nhà ở xã hội giai đoạn 2023-2025, song đến hết 2024 chỉ có thể bố trí 313 căn nhà ở xã hội.