Following the direction of Vietnam Electricity Group and Northern Power Corporation to mobilize maximum resources to support the recovery of the power grid damaged by storm No. 5 (Kajiki), Quang Ninh Power Company has urgently established a Shock Team of 45 members.
At exactly 5:00 a.m. on August 26, the team set off to support Ha Tinh province.

The shock team is a team of engineers and skilled workers with a lot of experience in incident handling, natural disaster prevention and search and rescue.
The starting lineup brought all the means of transporting workers, cranes, specialized tools and essential materials such as temporary iron pillars to be ready to deploy work on site.
Before departure, Mr. Nguyen Thanh Tinh - Director of Quang Ninh Power Company assigned the task, requiring the shock force to work with the highest spirit of effort, overcome all difficulties to complete the assigned tasks, while ensuring absolute labor safety and traffic safety.
Previously, on August 25, storm No. 5 made landfall in the Nghe An - Ha Tinh area with strong winds, causing widespread heavy rain. Natural disasters caused many power lines and transformer stations in the North Central region to have problems, causing disruptions in power supply to customers.
In Ha Tinh, two 110kV lines (Cam Xuyen - Ky Anh 2 and T500 - Huong Khe) were broken, many areas stopped and reduced power supply.
In that context, the timely support of human and material resources from Quang Ninh Power Company will contribute significantly to Ha Tinh Power Company's quick overcoming of damage and soon restoring power to people in flood-affected areas.