Vinh Long - On April 22, Standing Vice Chairman Thai Thu Xuong visited and encouraged workers constructing the Trade Union social housing project in Giao Long commune.

Reporting to the working delegation, Mr. Phan Dang Nguyen - Deputy General Director of Corporation 789 (Ministry of National Defense) said that the project currently has 151 personnel, of which 125 workers directly construct. The unit has arranged a rest area for workers far away, and the surrounding area has eateries to meet daily living needs.

According to Mr. Nguyen, fuel price fluctuations in the past time have caused the value of the package to increase by about 25 - 35% compared to the time of signing, causing many difficulties for contractors. Up to now, the project progress has reached about 23% compared to the plan. The unit proposed that the General Confederation consider adjusting the contract according to regulations to ensure costs and maintain construction.

Bà Thái Thu Xương phát biểu tại buổi thăm, động viên công nhân Dự án nhà ở xã hội Công đoàn ở Vĩnh Long. Ảnh: Hoàng Lộc
Ms. Thai Thu Xuong speaks at the visit and encouragement to workers of the Trade Union Social Housing Project in Vinh Long. Photo: Hoang Loc

At the visit, Ms. Thai Thu Xuong - Standing Vice President of the Vietnam General Confederation of Labor visited and inquired about living and working conditions, and the organization of overtime and shift increases to ensure progress. She emphasized the requirement for the construction unit to pay attention to labor safety and ensure a working environment for workers.

She also requested the Provincial Labor Federation and local authorities to closely monitor the salary and bonus situation of workers to promptly coordinate with the construction unit. Request the locality to continue to coordinate and create favorable conditions for the construction unit to complete the project on schedule.

For contractors, it is necessary to ensure environmental sanitation, strengthen labor safety and traffic safety propaganda, and limit the situation of using alcohol and beer after work hours.

Regarding the proposal to adjust the value of the bidding package, she received it and assigned the Trade Union Project Management Board to consider and advise the Presidium of the General Confederation to decide.

HOÀNG LỘC
RELATED NEWS

Social housing helps workers settle down, conveniently work and live

|

Vinh Long - Social housing is becoming a practical need of workers as it helps stabilize housing, facilitates going to work and daily activities of families.

Accelerate construction of Trade Union Social Housing project in Vinh Long

|

Vinh Long - Giao Long social housing project has reached about 20% progress, workers work overtime, overcoming sun and rain, and is expected to be completed in 2027.

Vinh Long Trade Union social housing reaches about 20% of volume, efforts to overcome difficulties in construction

|

Vinh Long - The Trade Union social housing project in Giao Long commune reached about 20% of the volume, overcoming construction difficulties, ensuring completion progress according to plan.

The Inspection Committee of the Journalists Association highly appreciates the operating results of the Journalists Association of Lao Dong Newspaper

|

According to the annual inspection and supervision plan for 2026, on April 22, the Inspection Board of the Vietnam Journalists Association had a working session with the Journalists Association of Lao Dong Newspaper.

Many Meritorious Artists and People's Artists have quit their profession and become freelancers due to injuries

|

National Assembly Deputy Trinh Thuy Mui shared that many artists who are proficient in their profession, meritorious artists, and people's artists have quit their profession and gone to other freelance jobs.

Long Thanh Airport recruits 400 personnel for commercial operation at the end of 2026

|

Dong Nai - Airports Corporation of Vietnam (ACV) is recruiting 400 personnel to work at Long Thanh airport when this project goes into commercial operation at the end of 2026.

Russia proposes receiving Iranian uranium: The most difficult relocation problem in history

|

Russia proposes receiving Iran's high-enriched uranium to reduce the risk of nuclear escalation in the context of undiminished US-Iran tensions.

National Assembly deputies talk about films "Red Rain", "Little Wolfoo", MV "Northern Bling"

|

National Assembly deputies cited the films "Red Rain", "Little Wolfoo", MV "Northern Bling" and said that traditional culture can become an attractive creative material.

Social housing helps workers settle down, conveniently work and live

HOÀNG LỘC |

Vinh Long - Social housing is becoming a practical need of workers as it helps stabilize housing, facilitates going to work and daily activities of families.

Accelerate construction of Trade Union Social Housing project in Vinh Long

HOÀNG LỘC |

Vinh Long - Giao Long social housing project has reached about 20% progress, workers work overtime, overcoming sun and rain, and is expected to be completed in 2027.

Vinh Long Trade Union social housing reaches about 20% of volume, efforts to overcome difficulties in construction

HOÀNG LỘC |

Vinh Long - The Trade Union social housing project in Giao Long commune reached about 20% of the volume, overcoming construction difficulties, ensuring completion progress according to plan.