Many IT projects in Da Nang are stalled due to legal issues

Mai Hương |

Da Nang Concentrated Information Technology Park and Software Park No. 2 are projects with investment capital of up to thousands of billions of VND but have not yet come into operation due to many difficulties.

Many legal problems

Danang IT Park is located in Hoa Lien commune (Hoa Vang district, Danang) invested by Danang Information Technology Park Development Joint Stock Company. This place was expected to become one of the best information technology development communities in Asia in Danang city following the model of "Silicon Valley" of the United States.

However, the entire area is currently deserted, with many areas of land in this project left vacant and overgrown with grass.

In addition, some buildings and structures have been completed but after a period of disuse, they have been covered with grass and vines; some items in the project have shown signs of deterioration.

Not only Danang IT Park, Software Park No. 2 Project, located in Hai Chau district, although completed the construction of the rough structure and infrastructure for nearly 2 years, has not been put into use yet, due to legal problems...

Software Park No. 2 has a total area of ​​over 28,000m2, and was started in October 2022 by the Danang Civil and Industrial Construction Investment Project Management Board as the investor. After completion, the project is expected to provide about 6,000 direct IT jobs. However, before that, the Government had not issued legal regulations and legal corridors on assets and infrastructure of public assets in the IT sector.

Hien trang o “thung lung Silicon” cua TP Da Nang. Anh: Mai Huong
Current situation in the "Silicon Valley" of Da Nang City. Photo: Mai Huong

Speed ​​up investment implementation progress

According to the representative of the investor of Da Nang Concentrated Information Technology Park, after investing and completing the infrastructure of phase 1 of the project in March 2019, the company sent a document to the City Party Committee, People's Council, and People's Committee of Da Nang City to consider continuing to allocate land for phase 2. From there, creating conditions for businesses to soon synchronously deploy the project, linking both phases to avoid wasting time and optimally exploiting business activities at the project.

During the handover and implementation of phase 2 of the project, the company will continue to invest and put into operation the expert area and ecological park to provide convenient services for experts, staff and partners working at the Information Technology Park.

At the Software Park No. 2 Project, after a recent inspection, Secretary of the Da Nang City Party Committee Nguyen Van Quang requested the Da Nang Civil and Industrial Construction Investment Management Board to continue to speed up the investment progress and complete the Project.

In addition, the leaders of Da Nang City requested the Department of Information and Communications to quickly deploy work related to the establishment of a project to exploit assets and information infrastructure of the Da Nang Software Park Concentrated Information Technology Zone.

Along with that, it is necessary to specify policies to call for businesses to invest in Software Park No. 2. In particular, it is necessary to pay attention to innovative businesses and semiconductor microchips, aiming to build a sustainable information technology ecosystem in Da Nang.

Mai Hương
RELATED NEWS

Stone mine "suspended" for 9 months, Gia Lai warns to replace commune leaders

|

Gia Lai - Although licensed, a quarry is still "suspended" for 9 months due to land lease procedures at the commune level.

Hanoi Industrial Meal Company won 148/148 bidding packages, with a total value of 505.8 billion VND

|

Hanoi Industrial Meal Service Joint Stock Company participated and won all 148 bidding packages to supply meals at schools in Hanoi and some northern provinces.

Teachers of Song Hong school nearly 20 months without salary, Phu Tho Department of Home Affairs speaks out

|

Phu Tho - Regarding the case of teachers of Song Hong Intermediate School who have not received salary for nearly 20 months, the Phu Tho Department of Home Affairs has spoken out.

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

|

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

Day and night construction at the construction site of the widest cable-stayed bridge project in Hai Phong

|

Hai Phong - To date, the construction of the nearly 1,500m long cable-stayed main bridge under the Nguyen Trai bridge project has reached about 32% of the progress, striving to reach the finish line in September 2027.

Today the National Assembly considers and decides on personnel and organizational structure

|

According to the Session program, today April 6, the First Session of the 16th National Assembly officially opens.

Xuan Son scores and assists to help Nam Dinh easily beat Ha Tinh

|

On the evening of April 5, Nam Dinh club won 2-0 against Ha Tinh in round 17 of LPBank V.League 2025-2026 with a shining performance from Xuan Son.

Da Nang invests more than 34.6 billion VND in Son Thuy beach project

Mai Hương |

Da Nang invested more than 34.6 billion VND to build the project of Park, Sea Sports Club and Son Thuy beach, Hoa Hai ward, Ngu Hanh Son district.

Da Nang opens job fair for workers

Nguyễn Linh |

Da Nang - Thousands of job opportunities for workers in the city at the Job Fair for demobilized soldiers and workers in Lien Chieu district in 2024.

Da Nang cannot close all residential roads across the railway yet

Nguyễn Linh |

Da Nang - There are currently 10 residential crossings across the railway that cannot be closed because they are serving traffic while waiting for investment in the construction of a service road.