Many IT projects in Da Nang are stalled due to legal issues

Mai Hương |

Da Nang Concentrated Information Technology Park and Software Park No. 2 are projects with investment capital of up to thousands of billions of VND but have not yet come into operation due to many difficulties.

Many legal problems

Danang IT Park is located in Hoa Lien commune (Hoa Vang district, Danang) invested by Danang Information Technology Park Development Joint Stock Company. This place was expected to become one of the best information technology development communities in Asia in Danang city following the model of "Silicon Valley" of the United States.

However, the entire area is currently deserted, with many areas of land in this project left vacant and overgrown with grass.

In addition, some buildings and structures have been completed but after a period of disuse, they have been covered with grass and vines; some items in the project have shown signs of deterioration.

Not only Danang IT Park, Software Park No. 2 Project, located in Hai Chau district, although completed the construction of the rough structure and infrastructure for nearly 2 years, has not been put into use yet, due to legal problems...

Software Park No. 2 has a total area of ​​over 28,000m2, and was started in October 2022 by the Danang Civil and Industrial Construction Investment Project Management Board as the investor. After completion, the project is expected to provide about 6,000 direct IT jobs. However, before that, the Government had not issued legal regulations and legal corridors on assets and infrastructure of public assets in the IT sector.

Hien trang o “thung lung Silicon” cua TP Da Nang. Anh: Mai Huong
Current situation in the "Silicon Valley" of Da Nang City. Photo: Mai Huong

Speed ​​up investment implementation progress

According to the representative of the investor of Da Nang Concentrated Information Technology Park, after investing and completing the infrastructure of phase 1 of the project in March 2019, the company sent a document to the City Party Committee, People's Council, and People's Committee of Da Nang City to consider continuing to allocate land for phase 2. From there, creating conditions for businesses to soon synchronously deploy the project, linking both phases to avoid wasting time and optimally exploiting business activities at the project.

During the handover and implementation of phase 2 of the project, the company will continue to invest and put into operation the expert area and ecological park to provide convenient services for experts, staff and partners working at the Information Technology Park.

At the Software Park No. 2 Project, after a recent inspection, Secretary of the Da Nang City Party Committee Nguyen Van Quang requested the Da Nang Civil and Industrial Construction Investment Management Board to continue to speed up the investment progress and complete the Project.

In addition, the leaders of Da Nang City requested the Department of Information and Communications to quickly deploy work related to the establishment of a project to exploit assets and information infrastructure of the Da Nang Software Park Concentrated Information Technology Zone.

Along with that, it is necessary to specify policies to call for businesses to invest in Software Park No. 2. In particular, it is necessary to pay attention to innovative businesses and semiconductor microchips, aiming to build a sustainable information technology ecosystem in Da Nang.

Mai Hương
RELATED NEWS

9th Hour No. 194: Stuck in the Past - Part 2

|

Hour 9 - The young widow suddenly becomes moved by the man in the same situation. Where will her struggle between love and morality go?

Live football Man City vs Liverpool in the FA Cup quarterfinals

|

The match between Man City and Liverpool in the FA Cup quarter-finals, takes place at 6:45 PM on April 4 (Vietnam time).

Land acquisition from 9 communes and wards in Dong Nai to open a road connecting Long Thanh airport

|

Dong Nai - The project of compensation, support, resettlement, and site clearance for DT. 770B road recovers about 271.6 ha of land.

Iran accuses 2 neighboring countries of aiding the US and Israel

|

The Iranian Foreign Ministry believes that some Middle Eastern countries may have directly supported the military campaign of the US and Israel targeting this country.

Early summer, young people invite each other to cycle around West Lake after work

|

Hanoi - Cool summer afternoon weather makes the cycling trend around West Lake return, attracting many young people to come to exercise and relax after a long day.

President Trump declares Britain is no longer America's "best ally

|

US President Donald Trump affirmed that the United Kingdom is not currently the best ally of the US after disagreements over the military campaign in Iran.

Proactively innovate and effectively implement emulation movements

|

On the morning of April 4, the Bloc of Emulation of socio-political organizations and Union organizations organized a Conference to summarize the activities of the Bloc of Emulation in 2025.

Da Nang invests more than 34.6 billion VND in Son Thuy beach project

Mai Hương |

Da Nang invested more than 34.6 billion VND to build the project of Park, Sea Sports Club and Son Thuy beach, Hoa Hai ward, Ngu Hanh Son district.

Da Nang opens job fair for workers

Nguyễn Linh |

Da Nang - Thousands of job opportunities for workers in the city at the Job Fair for demobilized soldiers and workers in Lien Chieu district in 2024.

Da Nang cannot close all residential roads across the railway yet

Nguyễn Linh |

Da Nang - There are currently 10 residential crossings across the railway that cannot be closed because they are serving traffic while waiting for investment in the construction of a service road.