Many IT projects in Da Nang are stalled due to legal issues

Mai Hương |

Da Nang Concentrated Information Technology Park and Software Park No. 2 are projects with investment capital of up to thousands of billions of VND but have not yet come into operation due to many difficulties.

Many legal problems

Danang IT Park is located in Hoa Lien commune (Hoa Vang district, Danang) invested by Danang Information Technology Park Development Joint Stock Company. This place was expected to become one of the best information technology development communities in Asia in Danang city following the model of "Silicon Valley" of the United States.

However, the entire area is currently deserted, with many areas of land in this project left vacant and overgrown with grass.

In addition, some buildings and structures have been completed but after a period of disuse, they have been covered with grass and vines; some items in the project have shown signs of deterioration.

Not only Danang IT Park, Software Park No. 2 Project, located in Hai Chau district, although completed the construction of the rough structure and infrastructure for nearly 2 years, has not been put into use yet, due to legal problems...

Software Park No. 2 has a total area of ​​over 28,000m2, and was started in October 2022 by the Danang Civil and Industrial Construction Investment Project Management Board as the investor. After completion, the project is expected to provide about 6,000 direct IT jobs. However, before that, the Government had not issued legal regulations and legal corridors on assets and infrastructure of public assets in the IT sector.

Hien trang o “thung lung Silicon” cua TP Da Nang. Anh: Mai Huong
Current situation in the "Silicon Valley" of Da Nang City. Photo: Mai Huong

Speed ​​up investment implementation progress

According to the representative of the investor of Da Nang Concentrated Information Technology Park, after investing and completing the infrastructure of phase 1 of the project in March 2019, the company sent a document to the City Party Committee, People's Council, and People's Committee of Da Nang City to consider continuing to allocate land for phase 2. From there, creating conditions for businesses to soon synchronously deploy the project, linking both phases to avoid wasting time and optimally exploiting business activities at the project.

During the handover and implementation of phase 2 of the project, the company will continue to invest and put into operation the expert area and ecological park to provide convenient services for experts, staff and partners working at the Information Technology Park.

At the Software Park No. 2 Project, after a recent inspection, Secretary of the Da Nang City Party Committee Nguyen Van Quang requested the Da Nang Civil and Industrial Construction Investment Management Board to continue to speed up the investment progress and complete the Project.

In addition, the leaders of Da Nang City requested the Department of Information and Communications to quickly deploy work related to the establishment of a project to exploit assets and information infrastructure of the Da Nang Software Park Concentrated Information Technology Zone.

Along with that, it is necessary to specify policies to call for businesses to invest in Software Park No. 2. In particular, it is necessary to pay attention to innovative businesses and semiconductor microchips, aiming to build a sustainable information technology ecosystem in Da Nang.

Mai Hương
RELATED NEWS

Proposal to handle trucks that are too bulky and cause sand to splash

|

Ha Tinh The government of Bac Hong Linh ward will issue a document recommending control and handling the situation of trucks carrying more than enough goods into bins causing sand to spill on National Highway 1.

HCMC builds 5 bridges larger than VND175,000 billion, ending ferry problems

|

Ho Chi Minh City is about to build a road and a sea overpass connecting Can Gio - Vung Tau, Can Gio bridge, Cat Lai bridge, Phu My 2 bridge, Dong Nai 2 bridge, with a total investment of about 175,000 billion VND.

Fishing boat sinks, 4 fishermen saved

|

Quang Tri - 4 fishermen in distress when their fishing boat sank at sea near Hon La Island were rescued safely.

After the severe flood, Lam Dong farmers struggle to restore dragon fruit gardens

|

Lam Dong - After the floodwaters receded, many farmers began their journey to restore their dragon fruit gardens.

Tropical depression level 8 is about to enter the East Sea, latest forecast of path

|

According to the meteorological agency, the tropical depression is forecast to maintain the intensity of level 6 gusting to level 8 in the next 24 to 48 hours.

Da Nang invests more than 34.6 billion VND in Son Thuy beach project

Mai Hương |

Da Nang invested more than 34.6 billion VND to build the project of Park, Sea Sports Club and Son Thuy beach, Hoa Hai ward, Ngu Hanh Son district.

Da Nang opens job fair for workers

Nguyễn Linh |

Da Nang - Thousands of job opportunities for workers in the city at the Job Fair for demobilized soldiers and workers in Lien Chieu district in 2024.

Da Nang cannot close all residential roads across the railway yet

Nguyễn Linh |

Da Nang - There are currently 10 residential crossings across the railway that cannot be closed because they are serving traffic while waiting for investment in the construction of a service road.