Boarding school in Lao Cai border accelerates to reach the finish line before the new school year

Đinh Đại |

Lao Cai - Boarding school in Muong Khuong commune with hundreds of workers working overtime to stick to the progress to put the project into use soon.

At the beginning of May, in Muong Khuong commune, hundreds of workers and many machines and equipment are simultaneously constructing on the large construction site of the Muong Khuong Primary and Secondary Boarding School project.

The atmosphere of urgent labor covers the entire construction site to speed up the progress of items before the rainy season and in time to serve the new school year.

Hàng trăm lao động hối hả thi công trường phổ thông nội trú ở xã biên giới Mường Khương, tỉnh Lào Cai. Ảnh: Đinh Đại
Hundreds of workers are rushing to construct a boarding school in Muong Khuong border commune, Lao Cai province. Photo: Dinh Dai

Through research, the project was started in November 2025, with a total investment of more than 215 billion VND.

The project will build many synchronous items such as classroom blocks, dormitories, administration areas, multi-purpose buildings, along with technical infrastructure, fire prevention and fighting systems...

Information from the Lao Cai Provincial Construction Investment Project Management Board, currently the ground leveling work has reached about 80% of the embankment volume, basically reaching the baseline of all building blocks. The rock breaking item for the dormitory area has also been completed, creating ground for continuing to deploy synchronous construction.

Hình hài một số khối nhà đã hoàn thiện khung thô. Ảnh: Đinh Đại
The shape of some building blocks that have completed the rough frame. Photo: Dinh Dai

At the construction site, there are currently about 350 - 400 workers and many construction teams working continuously in shifts. Many heavy machinery and equipment are mobilized to the maximum to ensure the overall progress of the project.

At the administration building block, the construction unit has completed concrete pouring of the technical floor of the roof, and is deploying construction, plastering and installation of electrical and plumbing systems to complete the 1st and 2nd floors.

In the classroom area, the Primary School block has completed pouring technical roof concrete, teams are focusing on building plastering and completing electricity and water.

Phối cảnh trường học tại xã Mường Khương sau khi hoàn thành. Ảnh: Đinh Đại
Perspective of the school in Muong Khuong commune after completion. Photo: Dinh Dai

The subject classroom block is processing and installing reinforced planks for the technical roof, and at the same time completing the lower floors. Meanwhile, the secondary school block is deploying molds and reinforced planks for the 3rd floor.

Dormitory areas are also gradually taking shape clearly. Some blocks have entered the stage of building walls, completing electricity and water and roofing; many other items are under construction on the 3rd floor to ensure overall progress...

Nhiều khối nhà khác cũng cấp tốc hoàn thiện. Ảnh: Đinh Đại
Many other building blocks are also being urgently completed. Photo: Dinh Dai

In parallel with that, fire prevention and fighting systems, termite protection, light electricity and drainage ditches are also being deployed simultaneously.

Witnessing the project taking shape day by day, local people expressed their excitement because this is a project expected to change the learning conditions for students in border areas.

Mr. Sung A Senh, a resident of Muong Khuong commune, shared that in the past, many students from afar had to travel hard or stay temporarily to study. Building a spacious boarding school will help parents feel more secure, and students have stable and safe learning conditions.

Khi đưa vào sử dụng, ngôi trường mới sẽ tạo môi trường học tập tốt hơn cho học sinh vùng biên. Ảnh: Đinh Đại
When put into use, the new boarding school will create a better learning environment for students in border areas. Photo: Dinh Dai

Talking to Lao Dong Newspaper, Mr. Phan Van Vinh - official of the Lao Cai Provincial Construction Investment Project Management Board said that the investor is closely coordinating with contractors to accelerate construction during the favorable weather period.

Teams are arranged to work continuously in each direction, prioritizing completing the main items before the rainy season.

Many building blocks have entered the plastering and electrical and plumbing completion stages. We regularly inspect the site, urge and supervise the quality to ensure technical and safety of the project.

The project is striving to be completed and handed over by the end of August to be ready for the new school year," Mr. Vinh informed.

When completed, the school is expected to create better learning conditions for highland students, especially children of ethnic minorities in the Muong Khuong border area, contributing to improving the quality of education in the locality.

Đinh Đại
RELATED NEWS

Dien Bien allocates more than 1,422 billion VND to build 9 inter-level boarding schools

|

Dien Bien - The Provincial People's Committee has just allocated more than 1,422 billion VND for 9 multi-level boarding school projects in 9 border communes.

Lang Son is supplemented with more than 450 billion VND to build boarding schools in border areas

|

Lang Son is allocated an additional 450 billion VND to implement 4 multi-level boarding school projects in border communes.

Lai Chau starts construction of 6 inter-level boarding schools, accommodating about 1,000 students

|

Lai Chau - On the morning of March 19, 6 inter-level boarding schools of primary and secondary school simultaneously started construction and broke ground.

Live football U17 Vietnam women vs U17 Australia women at the Asian tournament

|

Live match between U17 Vietnam women's team and U17 Australia women's team in the quarterfinals of the AFC U17 Championship, taking place at 2:00 PM today (May 11).

Officially increase temporary fees for using roads and sidewalks for parking, highest 400,000 VND

|

Hanoi - Temporary fee for using roads and sidewalks for car parking is highest at 400,000 VND/m2/month; parking bicycles and motorbikes is highest at 220,000 VND/m2/month.

Shocked witnesses recount the time the karaoke bar in Hanoi caught fire

|

Hanoi - The fire at Volume Club karaoke bar (Tu Liem ward) broke out on the morning of May 11, causing black smoke to cover the area.

Initial cause of the passenger car plunging into An Khe pass abyss

|

Gia Lai - A truck going down An Khe Pass suddenly lost its brakes and crashed strongly into a passenger car, causing the vehicle to plunge into a deep abyss, killing 1 person and injuring 2 others.

Dien Bien allocates more than 1,422 billion VND to build 9 inter-level boarding schools

QUANG ĐẠT |

Dien Bien - The Provincial People's Committee has just allocated more than 1,422 billion VND for 9 multi-level boarding school projects in 9 border communes.

Lang Son is supplemented with more than 450 billion VND to build boarding schools in border areas

Khánh Linh |

Lang Son is allocated an additional 450 billion VND to implement 4 multi-level boarding school projects in border communes.

Lai Chau starts construction of 6 inter-level boarding schools, accommodating about 1,000 students

QUANG ĐẠT |

Lai Chau - On the morning of March 19, 6 inter-level boarding schools of primary and secondary school simultaneously started construction and broke ground.