Overcoming terrain difficulties, accelerating the construction of boarding schools in Tuyen Quang

Việt Bắc |

6 Tuyên Quang border boarding school projects are accelerating construction, overcoming terrain difficulties to complete before the 2026-2027 school year.

In the last days of June 2026, at the construction site of the Tuyen Quang border boarding school project, thousands of workers and machinery are rushing to construct to meet the progress.

6 inter-level boarding primary and secondary school projects in Tuyen Quang are being implemented in border communes Thanh Thuy, Minh Tan, Pho Bang, Son Vi, Xin Man and Pa Vay Su.

PV recorded at the construction site of Minh Tan Inter-level Boarding Primary and Secondary School, nearly 500 officials and workers are working continuously according to the motto of 3 shifts, 4 crews. Up to now, all 12 newly built building blocks and 3 renovated building blocks have completed the rough construction. Construction units are implementing items such as plastering walls, tiling, and auxiliary infrastructure.

Mr. Nguyen Trung Kien - Project Commander (Tu Lap Construction Co., Ltd.) informed: "By the beginning of June, the project had reached more than 60% of the plan. The unit has always mobilized from 400 to 600 officials and workers at the construction site, working continuously, divided into many shifts, many construction teams including holidays.

A bustling construction atmosphere also appeared at the construction site of the Thanh Thuy Inter-level Boarding Primary and Secondary School project. Currently, all 10/10 building blocks have been deployed simultaneously, reaching more than 70% of the volume, and 400 workers are working regularly at the construction site.

Similarly, in Pho Bang, Son Vi, Xin Man and Pa Vay Su communes, thousands of officials and workers are mobilized on construction sites. Projects to date have achieved from more than 40% to 60% of the workload.

With the goal of completion before August 2026, all projects are forced to accelerate progress and construction time is rushed. In addition to difficulties in time pressure, the demand for skilled labor in border areas is also becoming a challenge. To ensure progress, contractors are forced to mobilize labor from many localities. Labor costs in border communes at times reach 650 to 750 thousand VND/day of work.

The terrain of the dangerous highlands also has a significant impact on the progress of the projects. The construction process also generates geological factors beyond expectations. Report of the Project Management Board for Construction Investment of Tuyen Quang province, at some projects such as Son Vi, Xin Man, the ground leveling process has caused landslides and the appearance of groundwater veins, posing a potential risk of affecting the foundation and the construction slope system.

According to Mr. Luong Van Doan - Director of the Project Management Board for Construction Investment of Tuyen Quang province, the investor always proactively removes arising problems at the site, regularly checks the contractor's capacity and organizes construction supervision. In particular, contractors are required to carry out construction in accordance with design and technical standards. The quality of materials and equipment put into the project must be ensured. Acceptance, payment, and management of contracts are ensured according to regulations.

Contractors increase large-capacity machinery, supplement manpower for items with large volumes. Construction progress is built in detail weekly, item by item. At the same time, organize overtime, increase construction teams to compensate for volume and shorten implementation time.

In addition to 6 projects being promoted for construction progress, Tuyen Quang is also carrying out investment procedures for 11 inter-level boarding schools, phase 2 in the communes: Ban May, Thang Tin, Lao Chai, Tung Vai, Nghia Thuan, Can Ty, Bach Dich, Thang Mo, Sa Phin, Lung Cu and Dong Van. Currently, 10/11 projects have submitted feasibility study reports for appraisal, of which the Dong Van School project has been approved by the People's Committee of Tuyen Quang province.

Việt Bắc
RELATED NEWS

Changing contract form, 23 boarding school catering staff face difficulties

|

After changing the contract form, many boarding school staff in Quang Tri sharply reduced their income, 3 months of summer without salary.

Nghe An urges progress of inter-level boarding school projects

|

Nghe An - Leaders of the Provincial People's Committee direct to accelerate the construction of inter-level boarding schools.

Cao Bang focuses efforts on building 11 boarding schools in border areas

|

Cao Bang assigns 11 members of the Provincial Party Committee Standing Committee to be in charge of 11 boarding schools, urging progress before the new school year.

Awakening the tourism potential of the Hoa Binh lake area needs more "push"

|

The tourism potential of the Hoa Binh lake area is very large, but there is still a lack of infrastructure, planning and appropriate mechanisms to attract investment and sustainable development.

Ministry of Education and Training guides the fastest and most accurate lookup of 2026 high school graduation exam scores

|

The Ministry of Education and Training has guided candidates on how to look up high school graduation exam scores in 2026 quickly and most accurately.

Hanoi pilots low emission zones from July 1, 2026 in some areas of Ring Road 1

|

Hanoi will pilot low-emission zones in some areas of Ring Road 1 to reduce pollution and promote green traffic.

Avoiding functional forces, personal data traders transfer to online markets

|

Without direct transactions, without meeting customers, but just spending money, personal data can be easily bought and sold at unbelievably cheap prices.

Changing contract form, 23 boarding school catering staff face difficulties

HƯNG THƠ |

After changing the contract form, many boarding school staff in Quang Tri sharply reduced their income, 3 months of summer without salary.

Nghe An urges progress of inter-level boarding school projects

QUANG ĐẠI |

Nghe An - Leaders of the Provincial People's Committee direct to accelerate the construction of inter-level boarding schools.

Cao Bang focuses efforts on building 11 boarding schools in border areas

Long An |

Cao Bang assigns 11 members of the Provincial Party Committee Standing Committee to be in charge of 11 boarding schools, urging progress before the new school year.