5 years waiting for 10-lane road, capital of nearly 1,500 billion VND in Hanoi

HỮU CHÁNH |

Hanoi - Construction started in 2019 and was expected to be completed after 2 years, but to date, the project to build Tay Thang Long road, more than 3km long and costing nearly 1,500 billion VND, is still unfinished.

In 2019, Hanoi started the Tay Thang Long Road Construction Project (section from Pham Van Dong Street to Van Tien Dung Street, Bac Tu Liem District), with a total investment of nearly 1,500 billion VND.

According to the plan, the route is about 3.2km long, with a cross-section of 60.5m and 10 lanes, passing through Co Nhue 2 and Minh Khai wards. A bridge will be built across the Nhue River.

At the time of commencement, the Hanoi People's Committee assessed that the investment in the construction of the Tay Thang Long route (from Pham Van Dong to Van Tien Dung) was a next step in completing the Tay Thang Long route according to the planning, contributing to the completion of the framework traffic system, promoting the development of urban infrastructure and socio-economic development of Bac Tu Liem district and Hanoi capital.

According to the original plan, the project would be completed and put into use in 2021. Up to now, 3 years have passed the deadline, but the project has only reached about 50% progress and there is no completion date yet.

Lao Dong's investigation shows that the main reason for the project's delay is due to many difficulties and problems in site clearance.

Up to now, there are still hundreds of households whose residential land was confiscated in Co Nhue 2 ward that have not agreed to hand over the land to the project. People believe that the compensation price for residential land is not satisfactory, not enough to buy resettlement houses arranged by the State.

Currently, Bac Tu Liem district is coordinating with relevant departments and branches to focus on removing obstacles to soon complete site clearance and speed up project progress.

d
The starting point of the project is at Pham Van Dong Street (Co Nhue 2 Ward, Bac Tu Liem, Hanoi). Photo: Huu Chanh
Diem cuoi du an tai nut giao duong Van Tien Dung (phuong Minh Khai). Anh: Huu Chanh
The end point of the project is at the intersection of Van Tien Dung Street (Minh Khai Ward). Photo: Huu Chanh
s
After 5 years of construction, the section from Noi Bridge to Van Tien Dung Street has taken shape. Photo: Huu Chanh
d
The 60.5m cross-section of the road includes 2 main roadways, 2 service roads, 2 separation sections between the main roadway and service roads, and sidewalks. Photo: Huu Chanh
Nguoi dan da co the luu thong o ben trai tuyen.
Box culverts are scattered along the route. Many sections have been paved with stone pavements, but weeds have grown wildly, spoiling the urban beauty. Currently, people can travel on the left side of the route (from Noi Bridge to Van Tien Dung). Photo: Huu Chanh
a
Some manhole covers on both sides of the road are missing or have temporary covers, causing safety concerns. Photo: Huu Chanh
Ben phai tuyen van la cong truong ngon ngang, nhieu doan chua hoan thanh xay dung. Anh: Huu Chanh
On the right side of the route is still a messy construction site, with many sections yet to be completed. Photo: Huu Chanh
Cong truong du an doan qua Hoc vien Canh sat nhan dan thi cong dang do.
The construction site of the project section passing the People's Police Academy is unfinished, littered with sand, dirt, and construction materials. "It's dusty when it's sunny, and muddy when it's rainy, affecting people's lives. I hope the project will be completed soon so people can suffer less," said Le Huy (34 years old, Bac Tu Liem). Photo: Huu Chanh
Nhieu doan duoc nguoi dan tan dung lam noi trong rau. Anh: Huu Chanh
Many sections are used by people to grow vegetables. Photo: Huu Chanh
Mot ho sau tren tuyen chua duoc san lap, tiem an nguy hiem cho nguoi dan khi qua day. Anh: Huu Chanh
A deep hole on the road has not been filled in, posing a potential danger to people passing through. This area has also become a garbage collection point. Photo: Huu Chanh
Doan tu den nut giao Pham Van Dong phan lon van chua duoc thi cong do vuong mat bang. Anh: Huu Chanh
The section from Noi Bridge to Pham Van Dong intersection has just been constructed, a nearly 350m long section, adjacent to the People's Committee of Co Nhue 2 Ward. The remaining section has not been implemented due to land acquisition problems. Photo: Huu Chanh
Trong anh la vi tri xay dung cau qua song Nhue. Anh: Huu Chanh
In the photo is the construction site of the bridge over the Nhue River. Photo: Huu Chanh
Mot mo cau da duoc xay dung tu lau, cac hang muc khac chua duoc trien khai. Anh: Huu Chanh
The bridge abutment section has been completed up to the abutment top wall and reinforced from the cone, other items have not been implemented yet. Photo: Huu Chanh
Don vi thi cong da duc hang chuc phien dam nhung cung bo khong suot nhieu nam. Anh: Huu Chanh
The construction unit has completed casting 48 I33 beam slabs. Photo: Huu Chanh
Cong hop ngon ngang tren tuyen. Anh: Huu Chanh
Concrete blocks litter the route. Photo: Huu Chanh
Nhieu doan thanh noi tap the duc cua nguoi dan. Anh: Huu Chanh
Many sections have become exercise areas for people. Photo: Huu Chanh
Van con hang tram ho dan thuoc phuong Co Nhue 2 chua duoc giai phong mat bang. Day la nguyen nhan chinh khien du an dinh tre suot nhieu nam qua. Anh: Huu Chanh
There are still hundreds of households in Co Nhue 2 Ward who have not agreed to hand over the land for the project. This is the main reason why the project has been stalled for many years. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

More good news about the road project connecting Tay Ho with Son Tay town

|

Hanoi is focusing on clearing the ground to complete the second section and is about to invest in building the fourth section of the 33km-long Tay Thang Long axis road, connecting Tay Ho with Son Tay.

Hanoi's Ring Road 4 passes through a land lot auctioned at 14 times the starting price

|

Hanoi - Ring Road 4 is gradually taking shape next to the auctioned land lot worth over 100 million VND/m2, 14 times the starting price in Tien Yen commune, Hoai Duc district.

Hanoi faces major obstacles in site clearance for Ring Road 4

|

Hanoi - Difficulties in applying regulations when determining land origin, price differences between departure and arrival... are hindering the progress of site clearance for the Ring Road 4 project.

Live futsal football Vietnam vs Australia

|

Live broadcast of the match between Vietnam and Australia's futsal team in the semi-finals of the 2024 Southeast Asian Championship, taking place at 3:00 p.m. today (November 8).

Factory devastated after fire in Song Cong industrial park

|

Thai Nguyen - Most of the factory, covering tens of thousands of square meters, was burned down after the fire at Song Cong I Industrial Park.

Audiences are "helpless" and have to find black market tickets to see Say Hi Brother

|

Concert Anh trai say hi opened ticket sales for 1 day, but many audiences are worried because they cannot buy tickets.

Hanoi land auctions are expected to remain hot, with many new records to come

|

Hanoi - Experts say that currently, land products are gradually becoming scarce. Therefore, it is predicted that in the coming time, auctioned land will continue to receive attention.

Waiting wearily for the 1,700 billion VND cancer hospital to restart

|

Can Tho - The construction investment project of the City Oncology Hospital has been suspended for a long time, causing losses and needs to be resolved soon...

More good news about the road project connecting Tay Ho with Son Tay town

HỮU CHÁNH |

Hanoi is focusing on clearing the ground to complete the second section and is about to invest in building the fourth section of the 33km-long Tay Thang Long axis road, connecting Tay Ho with Son Tay.

Hanoi's Ring Road 4 passes through a land lot auctioned at 14 times the starting price

Hữu Chánh |

Hanoi - Ring Road 4 is gradually taking shape next to the auctioned land lot worth over 100 million VND/m2, 14 times the starting price in Tien Yen commune, Hoai Duc district.

Hanoi faces major obstacles in site clearance for Ring Road 4

HỮU CHÁNH |

Hanoi - Difficulties in applying regulations when determining land origin, price differences between departure and arrival... are hindering the progress of site clearance for the Ring Road 4 project.