Hanoi faces major obstacles in site clearance for Ring Road 4

HỮU CHÁNH |

Hanoi - Difficulties in applying regulations when determining land origin, price differences between departure and arrival... are hindering the progress of site clearance for the Ring Road 4 project.

19 points left, sticky rice and beans

Component project 2.1 builds a parallel road to Hanoi's Ring Road 4, about 57km long, passing through localities including Soc Son, Me Linh, Dan Phuong, Hoai Duc districts, Ha Dong district, Thanh Oai and Thuong Tin districts.

According to Lao Dong's records at the project site in early November 2024, 4 construction packages were simultaneously deployed by contractors on the handed-over area with 32 construction points (23 road points, 9 bridge points).

The contractor is implementing weak ground treatment, bridge construction and semi-hollow asphalt concrete pavement items.

Mot doan tuyen song hanh Vanh dai 4 qua huyen Me Linh, Ha Noi dang tham nhua mat duong. Anh: Huu Chanh
A parallel section of Ring Road 4 through Me Linh District, Hanoi is being paved with asphalt. Photo: Huu Chanh

According to the Hanoi Traffic Construction Investment Project Management Board, by the end of October 2024, component project 2.1 had achieved an output of about 36.86%.

However, currently, there are many interruptions and "poor" points along the route (about 19 sections have not been handed over with a length of about 4.38km).

q
A residential area in Tan Chau village (Chu Phan commune, Me Linh) has not been relocated. Photo: Huu Chanh

In Package No. 9 - the largest package of the Ring Road 4 project, the contractor's construction scope still has 12 points of land acquisition problems, including 10 points in Hoai Duc and 2 points in Dan Phuong. The constructions blocking the land are mainly residential areas, factories, underground and above-ground technical infrastructure.

"The local site clearance progress is slowing down, which could affect the contractor's construction progress, while Hanoi requires the entire parallel route to be completed by 2025," Nguyen Hoang Hai, Commander of Package 9, told Lao Dong.

Similarly, some sections of the site in package No. 8, building a parallel road through Soc Son and Me Linh districts; package No. 10 through Ha Dong and Thanh Oai districts and package No. 11 through Thuong Tin have not been handed over to the contractor by the locality.

Many problems waiting to be solved

According to the Hanoi Traffic Construction Investment Project Management Board, the site clearance work for the section of Ring Road 4 passing through Hanoi has been approved and the land acquisition has reached 98.15%, with the remaining 14.77 hectares having not yet completed site clearance. Grave relocation has reached 97.65%.

Regarding land clearance for residential land, currently, the remaining land volume is mainly residential land in 5 districts: Ha Dong, Me Linh, Dan Phuong, Hoai Duc, Thanh Oai facing difficulties due to problems in applying the 2024 Land Law and current regulations.

Besides, there are difficulties in determining the origin of the land, and the big difference between the starting and ending prices. For example, in Thanh Oai, people do not agree; Dan Phuong has not approved the price.

Hon 100 ho dan thon Khe Ngoai 2 (xa Van Khe, Me Linh) chua duoc giai phong mat bang. Anh: Huu Chanh
Many households in Khe Ngoai 2 village (Van Khe commune, Me Linh) have not had their land cleared. Photo: Huu Chanh

Regarding land clearance for agricultural land, agency land, and other land, currently the volume of land with unapproved plans is mainly concentrated in Ha Dong district and part of Hoai Duc district.

The reason is due to difficulties in determining the origin of land, determining the depreciation period of business assets...

Ha Noi dat muc tieu hoan thanh du an song hanh Vanh dai 4 dai 57km, qua 7 quan huyen trong nam 2025. Anh: Huu Chanh
Hanoi aims to complete the 57km parallel project of Ring Road 4, passing through 7 districts in 2025. Photo: Huu Chanh

The Project Management Board believes that in order to complete the parallel road project in 2025, site clearance work must be completed by localities in 2024.

The agency affirmed that it will coordinate with departments, branches and localities to focus on resolving difficulties, strive to complete the relocation of underground and above-ground technical infrastructure items in the fourth quarter of 2024, complete site clearance and hand over the entire site of the section through Hanoi in 2024.

HỮU CHÁNH
TIN LIÊN QUAN

Important milestone of 57km, 6-lane project through Hanoi

|

Hanoi - Many parallel sections of Ring Road 4 have been paved with asphalt, marking an important milestone in the construction of Component Project 2.1.

Unexpected images of people traveling on Hanoi's Ring Road 4

|

Hanoi - Many parallel routes of Ring Road 4 have been paved, people can use them for commuting and exercising.

Progress of nearly 113km route through 3 northern provinces and cities

|

62 construction sites were simultaneously deployed by contractors, speeding up the progress of the nearly 113km long route, passing through 3 northern provinces and cities.

Many infrastructure construction projects are stuck due to raw materials

|

In addition to large projects and national key projects, infrastructure construction projects across the country are being stalled due to material problems.

Increased protection for Mr. Trump and Ms. Harris during the US election

|

During the 2024 US presidential election, security was increased around the residences of Donald Trump and Kamala Harris as well as around the White House and the Capitol.

Timely rescue of a fisherman in an accident at sea

|

Ba Ria - Vung Tau - On the morning of November 5, the Command of Coast Guard Region 3 said it had just provided timely first aid to a fisherman of fishing boat BV 4643 TS who had an accident at sea.

What did the commune chairman say about sand mining causing landslides on the Cong River bank

|

Thai Nguyen - The sand and gravel mining activities of Mai Linh Construction Company Limited are taking place vigorously right next to the Cong River bank, causing landslides that need to be clarified.

Tornado appeared in Quang Tri during heavy rain

|

Quang Tri - The tornado appeared when it was raining heavily, fortunately it happened in a short time, so the damage was insignificant.

Important milestone of 57km, 6-lane project through Hanoi

HỮU CHÁNH |

Hanoi - Many parallel sections of Ring Road 4 have been paved with asphalt, marking an important milestone in the construction of Component Project 2.1.

Unexpected images of people traveling on Hanoi's Ring Road 4

HỮU CHÁNH |

Hanoi - Many parallel routes of Ring Road 4 have been paved, people can use them for commuting and exercising.

Progress of nearly 113km route through 3 northern provinces and cities

HỮU CHÁNH |

62 construction sites were simultaneously deployed by contractors, speeding up the progress of the nearly 113km long route, passing through 3 northern provinces and cities.