The bridge connecting Long Bien with Gia Lam is behind schedule, no completion date has been set

HỮU CHÁNH - ĐẶNG TIẾN |

Hanoi - The slow handover of the site has caused the road bridge project across the Duong River to not be completed in 2025 as planned and the completion date has not been set.

The Duong Bridge construction project was approved by the Ministry of Transport (now the Ministry of Construction) in 2022, with a total investment of more than VND1,800 billion. The project consists of two main components including a railway bridge and a road bridge across the Duong River.

These two bridges are built in parallel, about 100m apart. In which, the railway bridge is located upstream (right of the old Duong bridge), while the road bridge is located downstream (left of the old Duong bridge), in the North - South direction.

Mr. Mai Xuan Tan, Project Management Director of the Duong River Waterway Upgrade Project (New Duong Bridge Construction Project), Railway Project Management Board - Ministry of Construction said that the project started in July 2024. Up to now, the upstream railway bridge construction component is being implemented on schedule.

Meanwhile, at the road bridge project, the contractor is currently constructing piers T4 and T5 located in the middle of the riverbed (not affecting the above-ground ground). It is expected that by the end of the second quarter of 2025, these items will be basically completed.

However, up to now, the contractor has not yet handed over more than 49 hectares of land to implement the overall project. This has caused the contractor to not be able to construct the overpass and approach roads at both ends of Long Bien and Gia Lam.

"The road bridge across the Duong River does not have land for the construction of approach bridges and approach roads, especially the pillars as symmetrical to pillars T4 and T5, so it is impossible to deploy the canopy casting, so from July 2025, the project must stop construction - Mr. Tan said.

According to the Railway Project Management Board, up to now, the People's Committees of Long Bien and Gia Lam districts have only handed over a small part of the site, about 4,000m2 (mainly public land, flower gardens, and trees). Most of the remaining land with more than 49 hectares has not yet been cleared.

Previously, according to the plan agreed by Hanoi City and the Ministry of Construction, in the first quarter of 2024, localities must complete the handover of land. However, by the end of the first quarter of 2025, the site has not been handed over on schedule as committed.

Facing this situation, the Ministry of Construction held a meeting with the leader of the Hanoi People's Committee. At the meeting, Vice Chairman of Hanoi People's Committee Duong Duc Tuan requested Long Bien District and Gia Lam District to accelerate the progress, complete the procedures, including the construction of the resettlement area to relocate the affected households, ensuring the handover of the entire ground in May 525.

However, according to Mr. Tan, this requirement is very difficult to implement because up to now, the arrangement of resettlement areas for more than 140 households has not been completed by the two localities.

Based on the site clearance plan provided by the People's Committees of Long Bien and Gia Lam districts, the expected completion time is the fourth quarter of 2025. Therefore, the Railway Project Management Board assessed that the project could not be completed on schedule in 2025 and the implementation deadline must certainly be adjusted.

The leaders of the People's Committees of the two localities said that the project has a very large volume of land acquisition, especially in the access road and overpass section, related to the relocation of more than 140 households. Therefore, arranging housing funds and building resettlement areas requires more time.

Currently, the People's Committees of Long Bien and Gia Lam districts are coordinating with relevant units to review procedures and issue necessary decisions to speed up site clearance, and promptly hand over the entire remaining land to the project.

Some images of the project to build a road bridge across the Duong River:

Cau duong bo duoc xay dung vinh cuu bang be tong cot thep va be tong cot thep du ung luc, ket hop day vang. Anh: Huu Chanh
The road bridge is permanently built with reinforced concrete and prestressed reinforced concrete, combined with cable-stayed. Photo: Huu Chanh
Cau co chieu dai 700 met, rong 18 met tuong duong 6 lan xe, van toc thiet ke 80 km/h. Anh: Huu Chanh
The bridge is 700m long, 18m wide, equivalent to 6 lanes, with a design speed of 80 km/h. Photo: Huu Chanh
ssa
Currently, the road bridge project is constructing piers T4 and T5 in the riverbed. Photo: Huu Chanh
s
Construction site of the road bridge project across the Duong River. Photo: Huu Chanh
s
A residential area in Giang Bien ward (Long Bien district) has not been cleared. Photo: Huu Chanh
Mat bang giao cham khien du an khong the ve dich nam 2025 theo ke hoach. Anh: Huu Chanh
The slow handover of the site has prevented the project from reaching the finish line in 2025 as planned. Photo: Huu Chanh
Doi voi hop phan xay cau duong sat qua song Duong o phia thuong luu cau Duong cu hien dang duoc nha thau trien khai theo ke hoach. Anh: Huu Chanh
The construction component of the railway bridge across the Duong River upstream of the old Duong Bridge is currently being implemented by the contractor according to the plan. Photo: Huu Chanh
HỮU CHÁNH - ĐẶNG TIẾN
RELATED NEWS

Progress of site clearance for 3 key transport projects in Hoang Mai

|

Hanoi - Hoang Mai District is reclaiming land and handing over land to build 3 key traffic projects in the area.

Hanoi opens 6-lane road, begins construction of intersection worth nearly VND2,400 billion

|

Hanoi - The city has just opened the road connecting Nam Tu Liem and Ha Dong districts, and at the same time started construction of an important intersection in Hoai Duc district.

Current status of the intersection in Ha Dong before building an overpass to reduce congestion

|

Hanoi - An overpass worth nearly VND880 billion will be built at the intersection of Le Trong Tan Street and National Highway 6 with the expectation of helping to reduce congestion and increase connectivity.

High tides inundate about 500 houses in Ly Son Special Zone

|

High tides rose more than 4m in Ly Son on the evening of November 6, causing 500 houses to be flooded, and the authorities urgently responded.

Lao Dong Newspaper won the National Press Award for the development of Vietnamese culture

|

On the evening of November 6, at Ho Guom Theater (Hanoi), the 3rd National Press Award Ceremony "For the Development of Vietnamese Culture" took place. Lao Dong Newspaper won 1 Encouragement Prize.

Storm No. 13 gusts to level 12 but is not a typhoon

|

On the evening of November 6, storm No. 13 officially made landfall in the coastal area from Quang Ngai to Dak Lak very strongly, but it did not have to be a typhoon.

Quang Ngai authorities strive to protect people in the midst of storm No. 13

|

Quang Ngai - Storm No. 13 has made landfall in Quang Ngai with strong gusts of wind. Sa Huynh coastal ward has urgently evacuated more than 600 households.

Fierce tornado in Quang Ngai causes dozens of houses to lose roofs

|

Quang Ngai - A powerful tornado swept through Long Phung commune on the afternoon of November 6, sweeping away the corrugated iron roofs, damaging dozens of houses.

Progress of site clearance for 3 key transport projects in Hoang Mai

HỮU CHÁNH |

Hanoi - Hoang Mai District is reclaiming land and handing over land to build 3 key traffic projects in the area.

Hanoi opens 6-lane road, begins construction of intersection worth nearly VND2,400 billion

HỮU CHÁNH |

Hanoi - The city has just opened the road connecting Nam Tu Liem and Ha Dong districts, and at the same time started construction of an important intersection in Hoai Duc district.

Current status of the intersection in Ha Dong before building an overpass to reduce congestion

HỮU CHÁNH |

Hanoi - An overpass worth nearly VND880 billion will be built at the intersection of Le Trong Tan Street and National Highway 6 with the expectation of helping to reduce congestion and increase connectivity.