Dai Ngai 2 Bridge strives to open to traffic to welcome the April 30 grand ceremony

PHƯƠNG ANH |

Soc Trang - Hundreds of workers and engineers are working hard day and night at the Dai Ngai 2 bridge construction site, determined to complete the key project on the occasion of the April 30 holiday.

These days, the atmosphere at Dai Ngai 2 bridge construction site is extremely bustling. Each group of workers is installing the bridge deck, other groups are completing the railings, inside the tunnel, workers are also urgently stretching cables, everyone is urgently completing the project on the 30th of April.

Cong nhan dang thi cong phan lan can cau Dai Ngai 2. Anh: Phuong Anh
Workers are constructing the railing of Dai Ngai 2 bridge. Photo: Phuong Anh

Mr. Nguyen Van Hieu - Dat Phuong Group Joint Stock Company - said that the unit is in charge of the span in the middle of the bridge. Up to now, all the main tasks have been basically completed, only the railings, cleaning and concrete pavement of the bridge surface are left.

"Seeing the bridge connecting Cu Lao Dung district between the Hau River and the mainland of Soc Trang province, everyone was happy and soon let people easily travel," said Mr. Hieu.

Mr. Phung Vu Phuong - a construction worker at Dai Ngai 2 bridge project - said that these days, the weather is hot but the brothers are still sticking to the project. Everyone tries their best to keep up with the traffic, right on April 30th to open the technical traffic.

"Working on this bridge, we witnessed people crossing both sides of the river having to take a ferry, taking a long time to wait. Therefore, we are aware of our responsibility, so we should try and complete it soon so that people can travel more easily," said Mr. Phuong.

Mr. Nguyen Duc Long - Executive Director and Commander of the Dai Ngai 2 bridge project - said that from the first days of construction, the unit has focused all resources, equipment, vehicles, machinery and finance; arranged to work in 3 shifts, 4 teams, working through holidays, holidays and difficult weather days. The progress was 6 months ahead of schedule and the bridge was completed on April 30 in accordance with the commitment to Soc Trang province.

Cau Dai Ngai 2 co chieu dai 862m, tong cong 13 nhip, 91 dam cau (moi dam nang hon 80 tan, dai gan 40m) rieng nhip chinh dai 330m duoc thi cong dang ket cau duc hang. Anh: Phuong Anh
Dai Ngai 2 Bridge is 862 m long, connecting Cu Lao Dung District with the mainland of Soc Trang Province. Photo: Phuong Anh

According to Project Management Board 85 - Investor of Dai Ngai Bridge project, the construction progress of Dai Ngai 2 bridge has reached over 90% (17/17 bridge piers, completed 3/3 corridor spans, completed 13/13 Super-T girder spans) is under construction of the bridge railing and the final span bridge deck. As for the route, the accrete construction has reached 92%, the sand filling construction has reached 79%, and the crushed stone construction has reached 30%.

Mr. Tran Van Nguyen - Chairman of the People's Committee of Cu Lao Dung district - shared: The completion of Dai Ngai 2 bridge not only solves the traffic problem but is also an important driving force to promote the development of the local agricultural economy, especially in attracting businesses to invest in high-tech agriculture and tourism, which will be the driving force to promote the comprehensive development of the district.

The Dai Ngai bridge project has a total length of more than 15 km, with a total cost of nearly VND 8,000 billion. The starting point intersects with National Highway 54, in Hung Hoa commune (Tieu Can district, Tra Vinh province). The end point intersects with Nam Song Hau National Highway, in Long Duc Commune (Long Phu District, Soc Trang Province). The project includes 2 main bridge works, Dai Ngai 1 and Dai Ngai 2 bridges.

Dai Ngai 2 bridge crosses the Hau river adjacent to Tran De estuary, connecting Cu Lao Dung district with the National Highway Nam Song Hau. After completion, it will replace ferry travel, helping to shorten travel time and enhance the ability to transport goods between provinces.

PHƯƠNG ANH
TIN LIÊN QUAN

Tet holiday on Dai Ngai 2 bridge construction site before closing day

|

Soc Trang - Even though it is New Year's holiday, at Dai Ngai 2 bridge, hundreds of workers are still working hard to ensure the progress of the closing.

Strong earthquake in Tonga just a few days after Myanmar earthquake

|

A 7.1-magnitude earthquake near Tonga prompted an initial Tsunami warning but was later lifted.

The Cong Viettel beat Hoang Anh Gia Lai to advance to the semi-finals of the National Cup

|

On the evening of March 30, The Cong Viettel defeated Hoang Anh Gia Lai with a score of 2-0 to win a ticket to the semi-finals of the 2024-2025 National Cup.

Updated gold price at the end of session 30.3: Profit despite surfing

|

Updated gold price at the end of the session on March 30: The difference between buying and selling is at a high level, investors still make a profit even if investing in the short term.

The army and police set out to support overcoming the consequences of the earthquake

|

The delegation of officers and soldiers of the Ministry of National Defense and the Ministry of Public Security have set out to support Myanmar in overcoming the consequences of the earthquake.

Waiting for the end of living with wastewater in industrial parks

|

Quang Tri - The lives of people living next to industrial parks have been disrupted by wastewater. Meanwhile, the wastewater treatment plant has not yet come into operation

Soc Trang informs about selecting people when arranging commune level

|

Soc Trang - Soc Trang province will arrange and assign according to the spirit of "from selecting people", retaining capable officials.

Early retirement policy due to streamlining according to Decree 67

|

How is the policy for people retiring early due to staff streamlining regulated, what new contents are mentioned in Decree 67?

Tet holiday on Dai Ngai 2 bridge construction site before closing day

PHƯƠNG ANH |

Soc Trang - Even though it is New Year's holiday, at Dai Ngai 2 bridge, hundreds of workers are still working hard to ensure the progress of the closing.

2 tháng nữa sẽ lắp dầm cầu vượt sông Hậu cho cầu Đại Ngãi 2

PHƯƠNG ANH |

Dự kiến tháng 11.2024, nhà thầu sẽ tiến hành lắp dầm cầu Đại Ngãi 2.

Cầu Đại Ngãi gần 8.000 tỉ đồng nối Trà Vinh và Sóc Trăng chính thức khởi công

PHƯƠNG ANH |

Ngày 15.10, Bộ Giao thông Vận tải phối hợp với UBND 2 tỉnh Trà Vinh và Sóc Trăng chính thức khởi công Gói thầu 11-XL - Dự án đầu tư xây dựng cầu Đại Ngãi 2 trên Quốc lộ 60 thuộc địa phận các tỉnh Trà Vinh và Sóc Trăng. Dự lễ khởi công có Thủ tướng Chính phủ Phạm Minh Chính, lãnh đạo các bộ, ban, ngành Trung ương, địa phương các tỉnh Trà Vinh, Sóc Trăng, Hậu Giang, Vĩnh Long...