Chairman of Quang Ngai Provincial People's Committee directs review of contractor capacity

VIÊN NGUYỄN |

Quang Ngai - Chairman of the Provincial People's Committee requests review of the capacity of many contractors; units that do not meet the requirements for progress and capacity will be considered for handling.

On August 20, Quang Ngai Provincial People's Committee informed that Mr. Nguyen Duc Tam - Chairman of Quang Ngai Provincial People's Committee - has just chaired a working session with the Provincial Traffic Construction Investment Project Management Board (Project Management Board) to review the project implementation progress, disbursement of public investment capital in the past and direct key tasks in the coming time.

According to the report of the Project Management Board, the unit is directly managing 61 projects, including: 2 national key projects; 6 key projects of the province; 14 other projects invested by the Board; 8 projects received from Dung Quat Economic Zone Management Board; 31 projects received from district level after dissolution.

Dự án đường Thạch Bích - Thọ Phong (Quảng Ngãi) thi công dang dở vì mặt bằng bàn giao không liền mạch. Ảnh: Viên Nguyễn
Thach Bich - Tho Phong road project (Quang Ngai) is under construction because the handover site is not continuous. Photo: Vien Nguyen

For key projects, the component project of the Quang Ngai - Hoai Nhon section under the North-South Expressway Construction Project in the East phase 2021-2025 has completed the main route and put it into operation from April 2026.

The Project Management Board is continuing to coordinate with relevant units to thoroughly handle arising problems. For the North-South high-speed railway project, the Board is focusing on preparing 38 detailed planning dossiers, including 28 master plan dossiers and 10 1/500 scale detailed planning dossiers for resettlement areas. Up to now, localities have approved 14/28 master plan dossiers and approved 8/10 planning tasks.

For other projects implemented by the Project Management Board, the unit is focusing on accelerating the construction progress of 4 projects, striving to complete the entire project to organize acceptance and handover for use in 2026.

Concluding the meeting, Mr. Nguyen Duc Tam requested the Project Management Board, departments, branches, and localities to change their thinking and working methods, meet the work requirements in the new situation; projects with completion progress in 2026 must be completed, striving to disburse 100% of public investment.

Agencies, units, and localities must proactively and definitively resolve tasks under their authority, without shirking or avoiding, affecting the overall progress. For contents requesting opinions, departments and branches must respond within 3 days, going straight to solutions to remove difficulties and obstacles, not just citing legal regulations. Guidance must be specific and unified so that communes and wards have a basis for implementation.

The Chairman of Quang Ngai Provincial People's Committee requested to review the capacity of all contractors; if contractors do not meet the requirements for progress and capacity, they must be considered and handled, not allowing it to affect the project progress. Contractors who have signed contracts must fulfill their commitments, ensuring quality, technical and project efficiency.

VIÊN NGUYỄN
RELATED NEWS

Revenue from land use fees in Quang Ngai is still low, slow progress

|

Quang Ngai - The province's revenue from land use fees is still low, including revenue from real estate business projects.

Announcing the audit decision in Quang Ngai

|

Quang Ngai - State Audit of Vietnam Region III announces audit decisions, focusing on programs, projects and the management and use of public capital.

Quang Ngai needs to prioritize attracting clean and high-tech industries

|

Quang Ngai - Member of the Politburo, Standing Deputy Prime Minister Pham Gia Tuc requested the province to prioritize attracting clean industry and high technology.

Proposal to reduce 30% tax for businesses with revenue under 10 billion VND

|

The Government proposes a 30% reduction in personal income tax and corporate income tax for business households and businesses with revenue below 10 billion VND.

Heavy rain and tornadoes caused an ancient tree to fall and hit a truck moving on Deo Chuoi Pass

|

Lam Dong - Heavy rain accompanied by tornadoes caused many forest trees and green trees to be uprooted and fallen on National Highway 20, including an ancient tree falling on a truck on Deo Chuoi Pass.

Inspectors point out a series of violations at the Vietnam Academy of Science and Technology

|

The Government Inspectorate has just pointed out many violations in personnel organization and task performance that occurred at the Vietnam Academy of Science and Technology.

Ho Chi Minh City parents run more than 20 km, go to 5-6 places to find textbooks for their children

|

Approaching the school start day, many parents in Ho Chi Minh City have to run dozens of kilometers, finding 5-6 places to gather enough textbooks for their children.

Gold prices surge, people line up to buy, people hesitate to take profits

|

On August 20, domestic gold prices increased sharply. Recorded in Hanoi, many people took advantage of buying gold when prices went up, while some customers considered selling.

Revenue from land use fees in Quang Ngai is still low, slow progress

THANH TUẤN |

Quang Ngai - The province's revenue from land use fees is still low, including revenue from real estate business projects.

Announcing the audit decision in Quang Ngai

ĐÔNG GIANG |

Quang Ngai - State Audit of Vietnam Region III announces audit decisions, focusing on programs, projects and the management and use of public capital.

Quang Ngai needs to prioritize attracting clean and high-tech industries

. |

Quang Ngai - Member of the Politburo, Standing Deputy Prime Minister Pham Gia Tuc requested the province to prioritize attracting clean industry and high technology.