What is in the Phong Chau bridge sections that are about to be demolished?

Tô Công |

Phu Tho - The remaining part of Phong Chau bridge, mainly on the side of Phung Nguyen commune, Lam Thao district, is being prepared to be demolished by functional units.

According to the reporter of Lao Dong Newspaper on November 5, with the remaining Phong Chau bridge (sections with steel trusses and other structures), Phung Nguyen commune side still has spans 1 to 5 with a total length of about 210 m; Van Xuan commune side still has about 20 m.

Mat bang xung quanh cau da duoc chuan bi de phuc vu cong tac pha do, thu don. Anh: To Cong.
The area around the bridge has been prepared for demolition and cleanup. Photo: To Cong.

According to observations, the remaining parts of Phong Chau bridge from top to bottom still have full items such as railings, lighting, bridge deck, steel beams, reinforced concrete beam structures, bridge piers, and bridge abutments.

Phan cau Phong Chau con lai se co nhieu hang muc phai pha do. Anh: To Cong.
The remaining Phong Chau bridge will have many items that need to be demolished. Photo: To Cong.

Previously, after a survey, the authorities determined that span N5 was tilted outwards towards the Red River (with signs of subsidence at pier T6); spans 2, 3, and 4 showed signs of being twisted and tilted in the direction of the Red River's flow, and the expansion joints (connecting spans) were stretched much further than the original design.

Mot so may moc, phuong tien da duoc dua toi hien truong de chuan bi pha do phan cau Phong Chau con lai. Anh: To Cong.
Some machinery and vehicles have been brought to the scene to prepare for the demolition of the remaining Phong Chau bridge. Photo: To Cong.

To serve the demolition and clearance of the remaining parts of Phong Chau bridge, and prepare the necessary conditions to start construction of the new Phong Chau bridge (to be started in December 2024), the authorities have completed the site preparation, and some equipment and machinery have been brought to the site.

Tau hut cat duoc huy dong hien truong de phuc vu cong tac truc vot nhip N6 dang nam duoi song, bi phu sa vui lap. Anh: To Cong.
A sand dredger was mobilized to the scene to serve the salvage work of span N6 lying under the river, buried by silt. Photo: To Cong.

As reported, after the collapse of Phong Chau bridge on September 9, the authorities have salvaged the entire N7 span along with many structures and vehicles under the river; they are currently working to bring N6 span from the river to shore (in the middle of the river, about 50 meters downstream from the bridge).

Tô Công
TIN LIÊN QUAN

Preparing to demolish the remaining section of Phong Chau bridge

|

Phu Tho - The remaining section of Phong Chau bridge at risk of collapse, mainly in Phung Nguyen commune, Lam Thao district, is being prepared to be demolished and cleared.

Additional 800 billion VND to build new Phong Chau bridge

|

Add 800 billion VND to the Ministry of Transport to implement the investment project to build the new Phong Chau bridge, the project must be completed by December 31, 2025 at the latest.

The water level of the Red River through Phong Chau Bridge changes continuously

|

Phu Tho - The water level of the Red River passing through Phu Tho province changes continuously, the sand dunes in the Phong Chau bridge area gradually disappear after the water rises.

Vietnam Airlines plane has just had to make emergency landing in India to rescue passengers

|

Informing Lao Dong Newspaper on the evening of July 7, a representative of Vietnam Airlines said that the airline had just had to make an emergency landing in India to rescue passengers.

Plan to help people save costs when metro tickets increase from 1.8

|

Hanoi - Tickets for the two metro lines will increase from August 1, 2025, the highest at 40%.

Dragon fruit garden owner in Lam Dong hires technology bodyguards to steal

|

Lam Dong - Many dragon fruit gardens have hired a 24/7 garden surveillance camera service to promptly prevent theft of electric wires and light bulbs.

Motorbikes still overflow into the car lane on Pham Van Dong Street, traffic police on duty to remind

|

Hanoi - The situation of motorbikes entering the lane reserved for cars on Pham Van Dong Street is still happening.

President granted amnesty to those sentenced to prison and life imprisonment on the occasion of National Day, September 2

|

A person sentenced to life in prison who has been reduced to prison for a period of 18 consecutive quarters of good or more can be considered and granted amnesty.

Preparing to demolish the remaining section of Phong Chau bridge

Tô Công |

Phu Tho - The remaining section of Phong Chau bridge at risk of collapse, mainly in Phung Nguyen commune, Lam Thao district, is being prepared to be demolished and cleared.

Additional 800 billion VND to build new Phong Chau bridge

PHẠM ĐÔNG |

Add 800 billion VND to the Ministry of Transport to implement the investment project to build the new Phong Chau bridge, the project must be completed by December 31, 2025 at the latest.

The water level of the Red River through Phong Chau Bridge changes continuously

Tô Công - Nguyễn Chuyên |

Phu Tho - The water level of the Red River passing through Phu Tho province changes continuously, the sand dunes in the Phong Chau bridge area gradually disappear after the water rises.