Still facing site clearance issues, Ba Lai 6 bridge is still accelerating construction

HOÀNG LỘC |

Vinh Long - Ba Lai 6 bridge reached about 25% of the volume, still facing site clearance issues in Luong Hoa commune, but construction is still being accelerated.

The Ba Lai 6 bridge project was started at the end of 2025, expected to be completed in mid-2027. After more than half a year of construction, the project has reached about 25% of the volume. Currently, the biggest bottleneck of the project is still site clearance work on the bank of Luong Hoa commune.

According to records, there are currently 2 households in Luong Hoa commune that have not completed procedures to receive compensation. Although they have agreed on the policy of land recovery and agreed to hand over the site, the households are still waiting for a decision approving the compensation level for crops on the recovered land area.

As one of the 2 households still facing problems, Ms. Pham Thi Kim Ngan (Luong Hoa commune, Vinh Long province) said that her family fully supports the policy of implementing the project. However, she hopes that functional agencies will soon issue a decision to compensate for the crops so that they can receive money and complete the handover procedures.

Công tác giải phóng mặt bằng Dự án Cầu Ba Lai 6 phía bờ xã Lương Hòa vẫn còn vướng hai hộ dân. Ảnh: Hoàng Lộc
Site clearance work for the Ba Lai 6 Bridge project on the banks of Luong Hoa commune is still facing obstacles for 2 households. Photo: Hoang Loc

Mr. Ho Van Tri - Vice Chairman of Luong Hoa Commune People's Committee - said that the locality has 10 households whose land was recovered for the project. As of July 14, 8 households had been disbursed compensation money, and 2 households were only entangled in the content of determining the level of crop support outside the limit, so they have not received the money.

According to Mr. Tri, the commune has proposed to the Provincial People's Committee to consider removing the above content in order to soon complete site clearance work. When the bottleneck is resolved, the entire site will be handed over for the contractor to synchronously implement the remaining items.

Leaders of Luong Hoa Commune People's Committee assessed that when Ba Lai 6 Bridge and the connecting road are completed, traffic between Phu Thuan Industrial Park and Phong Nam Industrial Park will be more convenient. The project also connects with CT33 road (when completed) and 57C road, creating an important traffic axis serving industrial development.

Mr. Tri added that the locality is promoting the expansion of Phong Nam 2 Industrial Park with the orientation of developing a new phase of about 75ha. Completed transport infrastructure will create a great advantage in attracting businesses, forming a production and logistics linkage chain.

Nhà thầu huy động nhiều nhân lực, máy móc thi công Cầu Ba Lai 6 tại khu vực đã có mặt bằng sạch. Ảnh: Hoàng Lộc
The contractor mobilized a lot of manpower and machinery to construct Ba Lai 6 Bridge in the area that has cleared the site. Photo: Hoang Loc

While the ground on the Luong Hoa side is still problematic, the banks of Chau Hung commune have completed handover. Taking advantage of favorable conditions, the contractor mobilized manpower, equipment, and organized many construction teams to compensate for progress and ensure the plan committed to the investor.

Talking to Lao Dong Newspaper, Mr. Mai Viet Cuong - Director of the Ba Lai 6 Bridge Project Management Board - said that the unit has fully implemented all construction fronts according to the plan. Up to now, the project has reached about 25% of the volume, of which Chau Hung side has clean ground, and Luong Hoa side will add more construction fronts as soon as they are handed over.

Ba Lai 6 bridge is nearly 400m long, 22.5m wide with a total investment of 600 billion VND, built with permanent reinforced concrete structure. When completed (expected in mid-2027), the project will connect Giao Long Industrial Park, Giao Long port, Phong Nam Industrial Park and key economic regions, expand development space, promote trade and attract investment for Vinh Long province.

HOÀNG LỘC
RELATED NEWS

Ba Lai 6 bridge is waiting to untie the site bottleneck to accelerate towards the finish line

|

Vinh Long - Ba Lai 6 Bridge still has two households that have not agreed on crop compensation, creating bottlenecks before the goal of accelerating project completion.

Removing site obstacles, 2 Ba Lai bridge projects accelerate to compensate for progress

|

Vinh Long - Ba Lai bridge projects are being constructed in a rolling manner by contractors, increasing many spans, working 3 shifts continuously to compensate for progress after site clearance problems.

Vinh Long Party Secretary directs to remove obstacles for key irrigation projects

|

Vinh Long - Provincial Party Secretary Tran Van Lau requested to remove obstacles, accelerate site clearance, and ensure the progress of key irrigation projects.

Lao Cai connects businesses, opens up development space from investment promotion conference

|

Lao Cai - Preparations for the Investment Promotion Conference have been completed, ready to welcome thousands of delegates and businesses seeking cooperation and investment opportunities.

Plan to arrange and merge schools of provinces and cities

|

Many provinces and cities have issued plans to implement the arrangement and reorganization of educational institutions according to Resolution No. 180/NQ-CP of the Government.

AI opens up opportunities for films on historical topics of Vietnamese cinema

|

Artificial intelligence (AI) is creating strong changes for the film industry, from creativity, production to distribution and promotion of works.

Ba Lai 6 bridge is waiting to untie the site bottleneck to accelerate towards the finish line

HOÀNG LỘC |

Vinh Long - Ba Lai 6 Bridge still has two households that have not agreed on crop compensation, creating bottlenecks before the goal of accelerating project completion.

Removing site obstacles, 2 Ba Lai bridge projects accelerate to compensate for progress

HOÀNG LỘC |

Vinh Long - Ba Lai bridge projects are being constructed in a rolling manner by contractors, increasing many spans, working 3 shifts continuously to compensate for progress after site clearance problems.

Vinh Long Party Secretary directs to remove obstacles for key irrigation projects

HOÀNG LỘC |

Vinh Long - Provincial Party Secretary Tran Van Lau requested to remove obstacles, accelerate site clearance, and ensure the progress of key irrigation projects.