The appearance of an important route in Hanoi after 2 years of construction

HỮU CHÁNH |

Hanoi - After 2 years of construction, Le Quang Dao Street has reached 90% of the progress and is on the "sprint" to complete the entire route in May.

In February 2023, the investment project of Le Quang Dao road construction lasted with a length of 2.6 km was started. The project has a total investment of more than VND 700 billion, invested by Nam Tu Liem District People's Committee.

The building has a starting point at Le Quang Dao intersection - Thang Long Boulevard (Nam Tu Liem District), the end point in Duong Noi urban area (Ha Dong district).

According to the design, the route will have an inter -regional standard, with a speed of 60km/h. Typical cross -sectional scale 40m, meeting 6 lanes.

Talking to labor, representative of Nam Tu Liem District Construction Investment Project Management Board said that under the contract signed between the investor and the contractor, the construction time of Le Quang Dao street project was extended 810 days.

After 2 years from the commencement date, up to now, the project volume is about 90%, the progress is still guaranteed according to the plan.

The section from the intersection of Thang Long Boulevard to the intersection with Dai Mo road (Provincial Road 70) is 1.9km long, which has allowed temporary vehicles from January 22. This paragraph has basically completed items such as lighting, trees, traffic signs ...

Mr. Bui Huu Nghia (35 years old, Dai Mo ward, Nam Tu Liem) said that he wanted to go through My Dinh, he had to go to Sa Double.

However, small double roads, crowded cars should often occur congestion. It took more than 20 minutes for more than 20 minutes to get out of the congestion on this road to enter Thang Long Boulevard to come to My Dinh.

After the project of Le Quang Dao street extended the traffic in part, the distance from Mr. Nghia's house to the workplace on Nguyen Hoang Street became closer.

"The new road is clear, from my house to the office for more than 6km to take only about 15 minutes" - Mr. Nghia said.

With the remaining route about 700m long, the contractor mobilizes the maximum machinery and construction workers continuously 3 shifts and 4 crews, ensuring the progress of the project completed and technical traffic in May 5.2025.

The project when completed will help shorten the travel time between Nam Tu Liem and Ha Dong districts, reduce traffic pressure loads for many roads in the region, contributing to the socio -economic development of the Capital.

Diem dau du an tai nut giao voi duong gom Dai lo Thang Long. Anh: Huu Chanh
The first point of Le Quang Dao project is extended at the intersection with Thang Long Boulevard Road (Nam Tu Liem District, Hanoi). Photo: Huu Chanh
Tu ngay 22.1, co quan chuc nang da cho phep thong xe doan tuyen tu nut giao Dai lo Thang Long den nut giao duong tinh 70 (Dai Mo) voi chieu dai khoang 1,9km. Anh: Huu Chanh
From January 22, the authorities have allowed the intersection of the route from Thang Long Boulevard to the intersection of Provincial 70 Road (Dai Mo) with a length of about 1.9km. Photo: Huu Chanh
He thong chieu sang, cay xanh, via he tren doan tuyen nay da co ban hoan thien. Anh: Huu Chanh
Lighting systems, trees, sidewalks on this section have basically completed. Photo: Huu Chanh
He thong chua chay, bien bao tren doan tuyen 1,9km da hoan thanh lap dat. Anh: Huu Chanh
Fire fighting system, traffic signs on the 1.9km route have been completed and installed. Photo: Huu Chanh
Nguoi dan su dung via he de di bo, tap the duc. Anh: Huu Chanh
People use sidewalks to walk, exercise. Photo: Huu Chanh
Mat cat ngang tuyen duong la 40m, dap ung 6 lan xe. Anh: Huu Chanh
The cross -section of the road is 40m wide, meeting 6 lanes. Photo: Huu Chanh
Trong anh la nut giao duong Le Quang Dao voi duong tinh 70. Anh: Huu Chanh
In the photo is the intersection of Le Quang Dao street with provincial road 70. Photo: Huu Chanh
Doan cuoi tuyen dang duoc nha thau tap trung thi cong hoan thien. Anh: Huu Chanh
The end of the route is being completed by the contractor. Photo: Huu Chanh
s
The entrance to the project site. Photo: Huu Chanh
Vat lieu xay dung duoc tap ket de phuc vu viec thi cong. Anh: Huu Chanh
Construction materials are gathered for construction. Photo: Huu Chanh
May moc lam viec tren cong truong du an, chieu 9.2. Anh: Huu Chanh
Machinery works on the construction site at the end of the route, afternoon 9.2. Photo: Huu Chanh
Theo ke hoach, toan tuyen se thong xe ky thuat vao thang 5.2025, sau 27 thang thi cong. Anh: Huu Chanh
According to the plan, Le Quang Dao Street will last for technical traffic in May 525, after 27 months of construction. Photo: Huu Chanh
Tuyen duong khi hoan thanh se giup ket noi quan Nam Tu Liem va Ha Dong thuan loi, giup giam un tac cho nhieu tuyen duong trong khu vuc. Anh: Huu Chanh
The entire route will help connect Nam Tu Liem and Ha Dong districts to help reduce congestion for many roads in the area. Photo: Huu Chanh

HỮU CHÁNH
TIN LIÊN QUAN

4 intersections in Hanoi are about to build a tunnel, capital of more than 5,100 billion

|

Hanoi will spend more than 5,100 billion dong to build underground tunnels at 4 large intersections to reduce traffic congestion, increase the connection.

Pi digital money is priced, Pi players still find it difficult to sell

|

Pi Digital currency has been officially listed, however, many "Pi players" despite owning thousands of Pi digital currency have not been able to participate in buying and selling.

Mr. Nguyen Van Duoc becomes Chairman of the Ho Chi Minh City People's Committee

|

HCMC - With the majority of votes, Mr. Nguyen Van Duoc - Deputy Secretary of the HCMC Party Committee was elected to hold the position of Chairman of the HCMC People's Committee for the 2021 - 2026 term.

Ho Chi Minh City exempts tuition fees for all students

|

Ho Chi Minh City spends 653 billion VND to exempt tuition fees for all preschool children under 5 years old and high school students from public and non-public from the 2025-2026 school year.

There is a mechanism to remove project obstacles in Ho Chi Minh City, Da Nang, Khanh Hoa

|

The National Assembly has issued a Resolution on specific mechanisms and policies to remove obstacles in projects and land according to the inspection conclusions in Ho Chi Minh City, Da Nang and Khanh Hoa.

Hanoi finalizes the time to announce the third exam subject for grade 10

|

Hanoi - The Department of Education and Training has just informed about the announcement time of the third exam subject in the 10th grade exam.

Đường nghìn tỉ ở Hà Nội "khựng" lại trước vạch đích

HỮU CHÁNH |

Hà Nội - Dự án đường nghìn tỉ ở Hoài Đức đạt 80% tiến độ nhưng tạm ngừng thi công do vướng mắc giải phóng mặt bằng.

4 intersections in Hanoi are about to build a tunnel, capital of more than 5,100 billion

HỮU CHÁNH |

Hanoi will spend more than 5,100 billion dong to build underground tunnels at 4 large intersections to reduce traffic congestion, increase the connection.

Loạt dự án đình trệ nhiều năm ở Hà Nội sẽ hoàn thành 2025

HỮU CHÁNH |

Hà Nội - Dự án đường trục phía Nam, Vành đai 1 Hoàng Cầu - Voi Phục, cầu vượt nút giao đường 70 dự kiến sẽ hoàn thành trong năm 2025 sau nhiều năm chậm trễ.