Expressway project through Soc Trang province is 9.3% behind schedule

PHƯƠNG ANH |

Soc Trang - Component 4 project of Chau Doc - Can Tho - Soc Trang expressway section through Soc Trang province reached 14.2% of contract value.

According to Project Management Board 2 (Soc Trang province) - Investor of the Chau Doc - Can Tho - Soc Trang Expressway Component 4 Project through Soc Trang province (Project) - construction progress to date has reached 14.2% of the contract value, 9.3% behind schedule. The 4 bid packages of the Project have reached 11.6 - 19.7% of the contract value.

Cong nhan thi cong Du an thanh phan 4 cao toc Chau Doc - Can Tho - Soc Trang doan qua tinh Soc Trang. Anh: Phuong Anh
Workers constructing the Chau Doc - Can Tho - Soc Trang Expressway Component 4 project through Soc Trang province. Photo: Phuong Anh

Soc Trang Province has also put into operation 6 river sand mines as fill materials for the Project. Up to now, nearly 212,300m3 of sand have been brought to the construction site. The maximum volume of sand expected to be supplied to the Project by June 2025 is 2.03/6.6 million m3 of sand.

As for the B1.3 sea sand mine, the province has issued a confirmation board. The Ministry of Natural Resources and Environment is submitting it to the Prime Minister for direction so that the Ministry can hand over the sea area to Construction Corporation No. 1 for exploitation.

The investor also recommended that the Department of Natural Resources and Environment of Soc Trang province consider increasing the exploitation capacity of 2 sand mines (MS01, MS04) to the maximum and promptly implement the exploitation procedures of mine MS11 to promptly supply sand for the Project.

At the same time, it is recommended that the Department of Natural Resources and Environment consider advising the Provincial People's Committee to transfer the B1.2 sea sand mine currently supplying the Can Tho - Ca Mau expressway project to supply Component Project 4 of the Chau Doc - Can Tho - Soc Trang expressway construction investment project, phase 1.

Ong Lam Hoang Nghiep (ao soc) - Pho Chu tich Thuong truc UBND tinh Soc Trang kiem tra tien do du an cao toc doan qua tinh Soc Trang. Anh: Phuong Anh
Mr. Lam Hoang Nghiep (striped shirt) - Permanent Vice Chairman of Soc Trang Provincial People's Committee inspects the progress of the expressway project through Soc Trang province. Photo: Phuong Anh

On November 13, at the inspection of the implementation status and progress of the project, Standing Vice Chairman of the People's Committee of Soc Trang province Lam Hoang Nghiep requested that contractors increase human resources and equipment, urgently speed up construction progress; supplement mining and transportation equipment to exploit the approved capacity of sand mines. Relevant departments and branches need to speed up procedures for exploiting the remaining sand mines... to ensure disbursement of all allocated capital in 2024.

On October 18, the People's Committee of Soc Trang launched a competition to accelerate the construction progress of key projects of the province (including the Chau Doc - Can Tho - Soc Trang Expressway Component 4 Project) to achieve achievements to welcome the Party Congresses at all levels, term 2025-2030.

For Component Project 4, strive to achieve an average output of VND 250 billion/package by December 31, 2024, disbursing at least 95% of the Central Budget capital assigned in 2024. By December 12, 2025, achieve an average output of VND 1,000 billion/package, disbursing at least 95% of the Central Budget capital assigned in 2025.

PHƯƠNG ANH
TIN LIÊN QUAN

Restricting traffic through National Highway 61C to install expressway overpass

|

Hau Giang - National Highway 61C (Chau Thanh A district) will restrict traffic from October 29 to November 1 to carry out construction of the expressway overpass girder.

Accelerating the completion of highways and beltways connecting the West and Southeast regions

|

By the end of this year, two sections of the Ben Luc - Long Thanh expressway will be opened to traffic, with the entire route expected to be completed in 2025. Ho Chi Minh City Ring Road 3 is also accelerating progress, with plans to open each section in 2025 and complete the entire route in 2026.

Peak results of 15 days and nights of highway construction in Soc Trang

|

Soc Trang - From August 15 to August 31, 2024, the construction output of 4 packages of the Chau Doc - Can Tho - Soc Trang expressway component 4 project reached 116 billion VND.

Ho Chi Minh City requests review of Cambridge International certificates

|

Ho Chi Minh City People's Committee requires units to inspect and review officials who have declared the use of foreign language certificates named "Cambridge International".

SPT Company must pay nearly 500 million VND after tax inspection

|

Thanh Hoa Provincial Tax Department has requested SPT Architecture Joint Stock Company to pay nearly 500 million VND due to incorrect tax declaration.

Tens of thousands of people flock to watch the Ngo boat racing festival in Soc Trang

|

Mekong Delta - From November 14-15, 60 boat teams from provinces and cities in the Mekong Delta will compete in the Ngo Boat Race with fierce and exciting matches.

My Boss Expressed His Love Even Though He Knew I Was Getting Married (Part 1)

|

Hour 9 - The female employee is expressed her feelings by her manager when she is about to get married. What will this girl decide?

8pm News: Merging many wards in 6 central districts of Hanoi

|

News at 8pm on November 14: Hanoi merged many wards in 6 central districts; Arrested and took statements from singer Chi Dan, model An Tay...

Restricting traffic through National Highway 61C to install expressway overpass

Tạ Quang |

Hau Giang - National Highway 61C (Chau Thanh A district) will restrict traffic from October 29 to November 1 to carry out construction of the expressway overpass girder.

Accelerating the completion of highways and beltways connecting the West and Southeast regions

MINH QUÂN |

By the end of this year, two sections of the Ben Luc - Long Thanh expressway will be opened to traffic, with the entire route expected to be completed in 2025. Ho Chi Minh City Ring Road 3 is also accelerating progress, with plans to open each section in 2025 and complete the entire route in 2026.

Peak results of 15 days and nights of highway construction in Soc Trang

PHƯƠNG ANH |

Soc Trang - From August 15 to August 31, 2024, the construction output of 4 packages of the Chau Doc - Can Tho - Soc Trang expressway component 4 project reached 116 billion VND.