Long Bien - Gia Lam bridge project after 15 months of construction

HỮU CHÁNH |

Hanoi - After 15 months of construction, some items of the project to build a railway and road bridge across the Duong River, with a capital of nearly 1,850 billion VND, have taken shape.

In July 2023, the Ministry of Transport (MOT) started construction of two railway bridges and a road bridge across the Duong River (part of the Duong River waterway transport upgrade project), replacing the old Duong Bridge for joint railway and road operations.

The Duong River waterway upgrade project is located in Thuong Thanh and Duc Giang wards (Long Bien district) and Yen Vien town (Gia Lam district, Hanoi).

The project has a total investment of more than 1,840 billion VND, of which the cost of site clearance in phase one is 650 billion VND, with the Railway Project Management Board (Ministry of Transport) as the investor.

On September 5, 2023, the contractor began construction at the site. According to the contract between the investor and the contractor, the project will be constructed in 840 days (28 months), expected to be completed in early 2026.

At the time of the project’s commencement, the Ministry of Transport’s leaders said that the old railway bridge had low clearance, which was a bottleneck on the waterway from Hai Phong to Viet Tri. The railway bridge shared the road, causing potential traffic jams and accidents.

When completed, Duong railway bridge will increase the capacity of waterway transport on waterway corridor No. 1, ensuring safety for waterway vehicles and helping the railway run smoothly.

Separating the road bridge from the railway bridge also improves traffic conditions connecting across the Duong River on the northern arterial route of Hanoi.

Some pictures on the project site:

Cau duong bo va duong dan co diem dau tai nut giao cau Duong cu tren duong Ngo Gia Tu, thuoc quan Long Bien; diem cuoi tai nut giao giua duong Ha Huy Tap voi duong Phan Dang Luu, huyen Gia Lam, cach cau Duong cu khoang 100m ve phia ha luu. Anh: Huu Chanh
The road bridge and approach road start at the old Duong bridge intersection on Ngo Gia Tu street, Long Bien district; end at the intersection between Ha Huy Tap street and Phan Dang Luu street, Gia Lam district, about 100m downstream from the old Duong bridge. Photo: Huu Chanh
Cau duong bo dai 382m, ket hop day vang, rong 18,5m, tinh khong duoi cau 4,75m. Duong dan dai 318m, van toc thiet ke 80km/h, 6 lan xe co gioi, 2 lan xe hon hop, giai doan phan ky truoc mat quy mo 4 lan xe co gioi.
The road bridge is 382m long, combined with a cable-stayed bridge, 18.5m wide, with a clearance under the bridge of 4.75m. The approach road is 318m long, with a design speed of 80km/h, 6 motor lanes, 2 mixed lanes, and in the immediate phase, the scale will be 4 motor lanes. Photo: Huu Chanh
Ngay 5.12, tren cong truong cau duong bo qua song Duong, cac loai may moc, sa lan, vat lieu xay dung... tap ket phuc vu cong tac thi cong. Anh: H.Chanh
On December 5, at the construction site of the road bridge across the Duong River, machinery, barges, construction materials... were gathered to serve the construction work. Photo: Huu Chanh
. Anh: H.Chanh
Contractors are constructing two bridge piers in the middle of the Duong River. Photo: H.Chanh
Nhom cong nhan lam viec tren cong truong du an. Anh: Huu Chanh
A group of workers working on the project site. Photo: Huu Chanh
Cau duong sat va duong dan dai 1km theo ly trinh duong sat hien huu, cach cau Duong cu ve phia thuong luu khoang 16,5m, trung vi tri dau tu xay dung duong sat do thi Ha Noi tuyen so 1. Anh: Huu Chanh
The railway bridge and approach road are 1km long according to the existing railway route, about 16.5m upstream from the old Duong bridge, coinciding with the investment location for the construction of Hanoi urban railway line No. 1. Photo: Huu Chanh
au duong sat co 6 nhip dam thep va dan thep dai 280m, duoc xay dung dam bao cho duong sat kho long 1.000mm va 1.435mm; toc do thiet ke 80km/h. Kho gioi han thong thuyen duoc phan ky dau tu voi tinh khong thong thuyen 7m, giai doan hoan thien 9,5m.
The railway bridge has 6 steel girder spans and a 280m long steel frame, built to ensure railways with 1,000mm and 1,435mm gauge; design speed 80km/h. The limited clearance is invested in stages with a clearance of 7m, and 9.5m in the completion stage. Photo: Huu Chanh
Mot so tru cau duong sat da hinh thanh. Anh: Huu Chanh
The bridge has a pedestrian corridor on the right side of the route. The 720m-long approach road is a single-track railway with a gauge of 1,000mm and 1,435mm; the design speed is 80km/h. After 15 months of construction, some of the railway bridge piers across the Duong River have been formed. Photo: Huu Chanh
s
The construction board is placed at the beginning of Duong bridge (Gia Lam district side). Photo: Huu Chanh
Den thoi diem hien tai, hai cau duong bo va duong sat qua song Duong moi chi trien khai o khu vuc song. Cac khu vuc nha dan hai ben song thuoc dien giai phong mat bang hien chua di doi. Anh: Huu Chanh
Up to now, the two road and railway bridges across the Duong River have only been deployed in the river area. Residential areas on both sides of the river that are subject to site clearance have not yet been relocated. Photo: Huu Chanh
CAU-DUONG-MOI-0
In the photo are many households in Duc Giang ward, Long Bien district that have not had their land cleared. Photo: Huu Chanh
Hai cau duong bo va duong sat qua song Duong du kien se hoan thanh vao nam 2025, thay the cho cau Duong cu khai thac chung duong sat va duong bo. Anh: Don vi thiet ke
The two road and railway bridges across the Duong River are expected to be completed in 2026, replacing the old Duong Bridge, which will operate as a joint road and railway bridge. Photo: Design unit
HỮU CHÁNH
TIN LIÊN QUAN

Overloaded inner-city roads in Hanoi await rescue of Red River overpass

|

Hanoi - The bridge project across the Red River has not been built yet, putting traffic pressure on the main road in the inner city.

Choose the right investment method to speed up the progress of the Red River bridge

|

To meet the future development needs of Hanoi, the construction of a new bridge system across the Red River is extremely necessary and urgent.

Red River Bridge is buckling under the load

|

Hanoi - The current bridge system over the Red River in Hanoi's inner city is currently suffering from traffic volume many times greater than its original design. Meanwhile, the plan to start construction of new bridges such as Tu Lien and Tran Hung Dao has not yet been clearly implemented.

Appointing 1 Lieutenant General and 1 Colonel to new positions

|

Lieutenant General Do Xuan Tung was appointed by the Prime Minister to hold the position of Deputy Director of the General Department of Politics of the Vietnam People's Army.

Mr. Dong Van Thanh is the Secretary of Hau Giang Provincial Party Committee

|

Hau Giang - Mr. Dong Van Thanh - Chairman of the Provincial People's Committee holds the position of Provincial Party Secretary, term 2020-2025.

Tickets to watch Vietnam team are being sold at 4-5 times the price

|

The "black market" ticket prices for two matches of the Vietnam team at the ASEAN Cup 2024 at Viet Tri Stadium (Phu Tho) increased 4-5 times compared to the original ticket prices.

Environmental protection from community initiatives

|

Many good models and practices from individuals and groups have actively contributed to the process of collecting, classifying and treating waste to protect the environment.

Deadline for submitting mandatory transfer plan of 2 banks

|

The Government requested the State Bank of Vietnam to urgently submit a plan for the compulsory transfer of two specially controlled banks, before December 20.

Overloaded inner-city roads in Hanoi await rescue of Red River overpass

NHÓM PV |

Hanoi - The bridge project across the Red River has not been built yet, putting traffic pressure on the main road in the inner city.

Choose the right investment method to speed up the progress of the Red River bridge

NHÓM PV |

To meet the future development needs of Hanoi, the construction of a new bridge system across the Red River is extremely necessary and urgent.