The project to open a 60m wide road in Hanoi is facing major obstacles

HỮU CHÁNH |

Hanoi - Difficulties in site clearance are hindering the progress of the project to expand National Highway 6 to a length of more than 21km, with an investment capital of VND 8,100 billion.

In December 2022, the Hanoi People's Committee started the renovation of 21.7km of National Highway 6 through Ha Dong and Chuong My districts, of which the section through Chuong My district is 15.8km long and Ha Dong is 5.9km long.

The starting point of the project is located at km14 in Ba La, Ha Dong district; the end point is km38, Xuan Mai town, Chuong My district.

The project has a total investment of 8,100 billion VND from the city budget. Of which, about VND 5,100 billion is for site clearance, VND 2,900 billion is for construction and equipment procurement costs.

According to the design, the expanded rear section has a cross-section of 50-60m, with a design speed of 80km/h. On the route, there is a box culvert (Tuan culvert) and seven bridges including: Mai Linh, Dong Tru, Tan Truong, Quan Lat, Xuan Mai, Song Bui and Nam Lu.

The project has four main intersections, including intersections of different levels (where two or more roads intersect at different elevations) with National Highway 21A, the North-South axis road and Ring Road 4.

a
A section of National Highway 6 through Tien Phuong Commune (Chuong My District, Hanoi) is under construction and expansion. Photo: Huu Chanh

According to the People's Committee of Chuong My district, to implement the project, the locality will have to reclaim about 85.36 hectares, 3,379 affected land plots, through 7 communes and 2 towns including: Chuc Son, Xuan Mai, Tien Phuong, Phu Nghia, Truong Yen, Dong Phuong Yen, Thanh Binh, Dong Son, Thuy Xuan Tien.

On March 11, 2024, the Hanoi People's Committee approved component project 1.2: Compensation, support and resettlement for site clearance in Chuong My district under the investment project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section.

a
A residential area in Phu Nghia commune (Chuong My district) has not been cleared. Photo: Huu Chanh

After the Decision approving the above component project 1.2, the Hanoi Traffic Construction Investment Project Management Board will hand over to the People's Committee of Chuong My district for compensation, support and resettlement.

The District People's Committee has focused on directing the district's functional branches, the People's Committees of communes and towns where the project passes through to carry out compensation, support and resettlement work for the project according to regulations.

By December 12, 2024, the People's Committee of Chuong My district had handed over the site to the Hanoi Traffic Construction Investment Project Management Board and the contractor with an area of about 57.58 hectares, reaching 67.45% (working land and agricultural land) to implement the project.

Cau Tan Truong tren Quoc lo 6 dang duoc trien khai xay dung. Anh: Huu Chanh
Tan Truong Bridge on National Highway 6 is under construction. Photo: Huu Chanh

According to the leader of the People's Committee of Chuong My district, this project in the area is still facing difficulties in determining land origin, the application of site clearance policies and mechanisms is transitioning from the 2013 Land Law to the 2014 Land Law, from Decision No. 10/2017/QD UBND dated March 29, 2017 of the City People's Committee to Decision No. 56/2024/QD UBND dated September 6, 2024 of the City People's Committee regulating a number of contents on compensation, support, and resettlement when the State reclaims land in Hanoi.

In addition, within the scope of site clearance for the project, there are floating infrastructure works that must be moved, reclaimed national defense land to serve the purpose of socio-economic development, and moved graves at cemeteries in Xuan Mai town.

Quoc lo 6 qua quan Ha Dong va huyen Chuong My co mat cat ngang nho hep nhung tiep nhan luong phuong tien rat lon moi ngay. Anh: Huu Chanh
National Highway 6 through Ha Dong and Chuong My districts has a narrow cross-section but receives a large number of vehicles every day. Photo: Huu Chanh

Regarding the above problems, the People's Committee of Chuong My district has reported to the People's Committee of the city, departments and branches for guidance on removing obstacles and trying to complete site clearance in the first quarter of 2026.

In Ha Dong district, the National Highway 6 expansion project with a length of nearly 6km is also being accelerated by relevant parties to hand over the site clearance progress to the project contractor.

HỮU CHÁNH
TIN LIÊN QUAN

Hanoi removes obstacles, promotes Ring Road 2.5 project

|

The Hanoi People's Committee is directing relevant units to remove obstacles to complete the construction of the Ring Road 2.5 section and the overpass on Pham Tu - Provincial Road 70 after many years of delay.

For more than 10 years, it has not been possible to expand the arterial road in Hanoi

|

Hanoi - The project to upgrade and expand Linh Nam road had an investment policy more than 10 years ago but has not been implemented yet due to land clearance problems.

Hanoi builds a major intersection connecting 2 important routes

|

Hanoi - In the period of 2022-2026, the city will deploy the construction of an intersection worth nearly VND 2,400 billion to connect 2 important routes in the area.

Hour 9: The lonely woman - Part 1

|

Hour 9 - A woman was forced to get married, then left empty-handed. Although she rose strongly, in the end, will she find happiness?

Vietnam team is missing 4 players at the first training session in Binh Duong

|

4 players Tien Linh, Quang Hai, Thanh Binh and Bui Hoang Viet Anh were not present in the first training session of the Vietnam team in Binh Duong.

The money-based waste weighing pilot in Ho Chi Minh City is still inadequate

|

HCMC - Currently, Hoc Mon and Binh Chanh districts are applying the pilot of weighing garbage to calculate money. This caused many collectors to react because of inadequacies.

In the Hanoi traffic light control room during rush hour

|

Hanoi - During rush hour, the loudspeaker continues to ring, the atmosphere inside the traffic light control room becomes urgent.

Updated gold price at the end of session 12.3: Breaking the peak of 94 million VND

|

Updated gold price at the end of session 12.3: Domestic gold increased. Plain gold rings broke the 94 million VND/tael mark.

Hanoi removes obstacles, promotes Ring Road 2.5 project

Hữu Chánh |

The Hanoi People's Committee is directing relevant units to remove obstacles to complete the construction of the Ring Road 2.5 section and the overpass on Pham Tu - Provincial Road 70 after many years of delay.

For more than 10 years, it has not been possible to expand the arterial road in Hanoi

HỮU CHÁNH |

Hanoi - The project to upgrade and expand Linh Nam road had an investment policy more than 10 years ago but has not been implemented yet due to land clearance problems.

Hanoi builds a major intersection connecting 2 important routes

HỮU CHÁNH |

Hanoi - In the period of 2022-2026, the city will deploy the construction of an intersection worth nearly VND 2,400 billion to connect 2 important routes in the area.