Hanoi builds a major intersection connecting 2 important routes

HỮU CHÁNH |

Hanoi - In the period of 2022-2026, the city will deploy the construction of an intersection worth nearly VND 2,400 billion to connect 2 important routes in the area.

The project to build a different-level intersection between Ring Road 3.5 and Thang Long Avenue, Hoai Duc District was approved by the Hanoi People's Council in a resolution on investment policy from 2022.

The project aims to complete the planned traffic infrastructure system, connect and exploit it appropriately with the built infrastructure; reduce congestion, contribute to accelerating the formation of urban areas in the area.

The project has a total investment of VND 2,384 billion, implemented in the period of 2022-2026, with the Hanoi Civil Works Construction Investment Project Management Board as the investor.

Vi tri xay dung nut giao duong Vanh dai 3,5 voi Dai lo Thang Long. Anh: Huu Chanh
Location of the Ring Road 3.5 intersection with Thang Long Avenue. Photo: Huu Chanh

Regarding the scale of construction investment, the intersection includes turbine branches combined with direct underpasses. In particular, the underpass is in the direction of Ring Road 3.5 (Hoang Tung Street) to National Highway 32, the route heart is overlapping with Hoang Tung Street, including 4 lanes with a total length of 975m.

The section under Thang Long Avenue will be designed with a closed tunnel of 150m long; Hoang Tung Street will be designed with an open tunnel of 157.5m long, a retaining wall of 220m long; National Highway 32 will be designed with an open tunnel of 157.5m long and a retaining wall of 200m long.

The remaining part of the project is the wheel abutment, the turbine branch bridge bearing the prestressed reinforced concrete beam with a length of more than 2,350m on 4 branches. The width of the bridge is 8.8m, with 2 lanes for motor vehicles and a reinforced concrete retaining wall with a length of 619m/8 behind the abutment.

Nhieu nha xuong trong khu vuc xay dung nut giao duong Vanh dai 3,5 - Dai lo Thang Long. Anh: Huu Chanh
Many factories in the construction area of the Ring Road 3.5 - Thang Long Avenue intersection. Photo: Huu Chanh

Up to now, Ring Road 3.5 (Hoang Tung Street) has been completed and put into use. As for Ring Road 3.5, the section from Thang Long Avenue to National Highway 32, it is still under construction.

This is one of the important projects in Hoai Duc district, started in 2017. The project has a total length of 5.5km, a total investment of about VND1,800 billion, with the People's Committee of Hoai Duc district as the investor.

s
Some sections of Ring Road 3.5 through Hoai Duc (Hanoi) have been basically completed. Photo: Huu Chanh

The report of the Hoai Duc District Construction Investment Project Management Board said that the Ring Road 3.5 project (phase 1), which started construction on October 28, 2017, is now estimated to have reached 90% of the contract volume.

Phase 2 started construction on January 28, 2019, and the estimated implementation volume is about 80%.

With phase 3, the implementation period is from 2022-2025 (started on June 30, 2023), the construction has now reached about 40% of the volume.

s
Intersection of Ring Road 3.5 with National Highway 32. Photo: Huu Chanh

According to the investor's representative, the project's progress is delayed due to problems in site clearance.

At the Ring Road 3.5 project (phase 2), although construction started in 2019, up to now, the section from Km5+020 - Km5+300 has not been handed over the site due to the Vuon Chuoi Archaeological Site.

Trong anh la Khu di chi khao co Vuon Chuoi dang duoc khai quat. Anh: Huu Chanh
In the photo is the excavated Bananas Garden Archaeological Site. Photo: Huu Chanh

In March 2024, with the permission of the Ministry of Culture, Sports and Tourism, the People's Committee of Hoai Duc district organized the groundbreaking ceremony for the excavation and relocation of the Vuon Chuoi archaeological site. The package implementation period is 330 days, expected to be completed in the first quarter of 2025.

In addition, the Ring Road 3.5 project (phase 3) needs to reclaim land from 6 enterprises in the An Khanh Industrial Cluster, but so far only 4/6 enterprises have been counted.

Currently, Hoai Duc district is coordinating with relevant parties to speed up the site clearance progress to hand over to the project contractor.

For sections without land clearance, the investor is directing project implementation units and contractors to urgently construct in the form of "shelving". It is expected that Ring Road 3.5 will be completed in 2025.

HỮU CHÁNH
TIN LIÊN QUAN

About to build a 1.5km road with a capital of nearly VND2,500 billion in the center of Hanoi

|

Hanoi - Thanh Xuan District is focusing on site clearance to implement the construction of the 1.5km Ring Road 2.5 section, with an investment capital of nearly VND2,500 billion.

Tunnels and roads worth over VND2,000 billion are about to be completed in Hanoi

|

Hanoi - The Ring Road 2.5 project and Giai Phong underpass are expected to be completed in 2025, helping to reduce congestion and increase traffic connectivity in the area.

Hanoi leaders talk about the phenomenon of " spraying medicine the day before, selling the next day"

|

Hanoi - In response to concerns about the phenomenon of " spraying medicine the previous day and selling the next day", the Vice Chairman of the City People's Committee spoke about this issue.

The only waste treatment plant closed, by the end of July, Ca Mau had no more place to bury waste

|

Ca Mau - After the waste treatment plant closed, Ca Mau took the waste to bury. This is a temporary solution, but by the end of July there is no more burial place.

Victims of a series of accidents in Hanoi tell the time they were hit by a car

|

Hanoi - Many people were injured in the series of accidents that occurred this morning (July 9).

40% of meat in Hanoi is not strictly controlled

|

The leaders of the Hanoi Department of Agriculture and Environment acknowledged that the amount of meat imported from localities for consumption in the city has not been strictly controlled.

Da Nang stops all paragliding activities in Son Tra mountain area

|

The Management Board of Son Tra Peninsula and Da Nang tourist beaches said that it has stopped all paragliding activities on Son Tra peninsula since July 9.

Dismantling a series of "tiger cages" after the fire that killed 8 people at Doc Lap residence

|

HCMC - After the tragic fire, many households in Doc Lap residence have proactively hired workers to dismantle the expansion items, encroaching on the corridor and balcony.

About to build a 1.5km road with a capital of nearly VND2,500 billion in the center of Hanoi

HỮU CHÁNH |

Hanoi - Thanh Xuan District is focusing on site clearance to implement the construction of the 1.5km Ring Road 2.5 section, with an investment capital of nearly VND2,500 billion.

Tunnels and roads worth over VND2,000 billion are about to be completed in Hanoi

HỮU CHÁNH |

Hanoi - The Ring Road 2.5 project and Giai Phong underpass are expected to be completed in 2025, helping to reduce congestion and increase traffic connectivity in the area.

Hiện trạng khu đất xây bến xe rộng gấp 1,5 lần bến Nước Ngầm

Hữu Chánh |

Hà Nội - Bến xe khách Yên Sở sắp được xây dựng có diện tích hơn 27.000m2, rộng gấp khoảng 1,5 lần Bến xe Nước Ngầm.