Tunnels and roads worth over VND2,000 billion are about to be completed in Hanoi

HỮU CHÁNH |

Hanoi - The Ring Road 2.5 project and Giai Phong underpass are expected to be completed in 2025, helping to reduce congestion and increase traffic connectivity in the area.

The Kim Dong - Giai Phong underpass construction project (Hoang Mai district, Hanoi) started construction in October 2022. The project has a total investment of 778 billion VND, invested by the Hanoi Traffic Construction Investment Project Management Board.

This is the 5th underpass in the capital built from 2009 to present, after the Kim Lien, Trung Hoa, Thanh Xuan, and Le Van Luong tunnels.

The Kim Dong - Giai Phong underpass has a total tunnel and approach road length of 890m in the direction of Ring Road 2.5, of which the closed tunnel is 140m long and the open tunnel is 320m long. The section through the tunnel has 2 lanes each way, 3.5m wide/lane, the section outside the tunnel has 3 lanes each way, 3.5m wide/lane.

z
The Ring Road 2.5 - Giai Phong underpass (Hoang Mai district, Hanoi) has basically completed the open tunnel on the Dam Hong side. Photo: Huu Chanh

According to the representative of the Hanoi Traffic Construction Investment Project Management Board, after more than 2 years of construction, the project has reached more than 60% of the volume.

The project has completed the approach road in Dinh Cong area, the contractor is currently focusing on constructing a tunnel between the intersection and the approach road in Kim Dong street.

"The project is being implemented on schedule, expected to be completed in 2025" - said a representative of the Project Management Board.

a
The tunnel and approach road length is 890m, expected to be completed in 2025. Photo: Huu Chanh

Previously, there were many concerns that when the underpass was completed, it would have to "shelter" the connecting road, because the Ring Road 2.5 project (Dam Hong - National Highway 1A section) had been unfinished for many years, and there was no sign of construction returning.

The project is invested in the form of a BT (build - transfer) contract with a length of 2.06km, with a total investment of more than 1,300 billion VND. Started in 2014, expected to be completed in 2017, but the project is behind schedule.

By 2020, the project was temporarily suspended when it had only reached about 40% of the workload. The reason is that the contract implementation period has not been extended, and the adjusted feasibility study report has not been approved.

Vanh dai 2,5
The Ring Road 2.5 section of Dam Hong - National Highway 1A is still unfinished after more than 10 years of construction. Photo: Huu Chanh

After more than 10 years since the start of construction, the road is still unfinished. Many sections of the road have become garbage dumps, construction material storage areas; the dusty sun and mud make people extremely upset.

Voters in Hoang Mai district have repeatedly reported this situation to the National Assembly delegations, the City People's Council, and the Hoang Mai District People's Council.

a
Many places on the route have become garbage collection points. Photo: Huu Chanh

At the end of 2024, Chairman of the Hanoi People's Committee Tran Sy Thanh chaired a meeting with relevant departments, branches and sectors, "hotly instructing" to urgently re-sign the BT contract appendix for the Ring Road 2.5 investment project (Dam Hong - National Highway 1A section) under the form of a construction - transfer (BT) contract.

On February 24, 2025, the Chairman of the Hanoi People's Committee issued Decision No. 902/QD-UBND on authorizing the signing of the BT contract appendix of the project under the form of a BT contract.

a
The L3 bridge over the Lu river has been constructed with 20 bored piles, all the bridge piers and all the girders and has been abandoned for many years. Photo: Huu Chanh

Accordingly, the Chairman of the Hanoi People's Committee authorized (from the signing date to the end of the first quarter of 2026) the City Traffic Construction Investment Project Management Board to sign a BT contract for the Ring Road 2.5 investment project (Dam Hong - National Highway 1A section) under the form of a BT contract according to the content approved by the City People's Committee.

It is expected that the Ring Road 2.5 project will resume construction from March and be completed in 2025, ensuring the route is opened in sync with the progress of the Kim Dong - Giai Phong underpass project.

HỮU CHÁNH
TIN LIÊN QUAN

Complete the expansion of Hanoi's central road in September 2025

|

Hanoi - According to the plan, the project to expand Nguyen Tuan Street to 720m long, with an investment capital of nearly 400 billion VND, will be completed in September 2025.

After more than 10 years, the billion-dollar road in Hanoi has only reached 40% progress

|

Hanoi - After more than 10 years of construction, the Dam Hong - National Highway 1 Ring Road 2.5 project is still unfinished, affecting people's travel and daily life.

Relocating many trees to open the central road of Hanoi to 21m

|

Hanoi - The authorities have relocated many trees to implement the construction of the 720m-long Nguyen Tuan Street expansion, with an investment capital of nearly 400 billion VND.

Ho Chi Minh City and Hanoi have the highest divorce rates in the country

|

According to statistics, the whole country has about 2,225,000 divorces/devorces, of which Ho Chi Minh City and Hanoi account for the highest rate.

Live volleyball VTV Binh Dien Long An 0-1 Thanh Hoa: Set 2

|

Live volleyball match between VTV Binh Dien Long An and Long Son Thanh Hoa Cement at Hoa Lu Cup 2025, taking place at 1:30 p.m. today (March 4).

Traffic in Thai Nguyen is invested in to help connect better

|

Thai Nguyen - The road connecting Phu Binh district and Pho Yen city with a total investment of 736 billion VND is about to be completed, helping traffic connect better.

In 2025, serving at least 1/3 of the sentence will be considered for amnesty

|

According to the Deputy Minister of Public Security, to be considered for amnesty in 2025, a prison sentence must be served at least 1/3 of the time in cases of limited prison sentences.

Visiting and sharing with the families of the police officer who died

|

Delegations from the Provincial Party Committee, Provincial People's Committee, Ba Ria - Vung Tau Provincial Police and localities visited and shared with the families of police officers who died while on duty.

Complete the expansion of Hanoi's central road in September 2025

HỮU CHÁNH |

Hanoi - According to the plan, the project to expand Nguyen Tuan Street to 720m long, with an investment capital of nearly 400 billion VND, will be completed in September 2025.

After more than 10 years, the billion-dollar road in Hanoi has only reached 40% progress

HỮU CHÁNH |

Hanoi - After more than 10 years of construction, the Dam Hong - National Highway 1 Ring Road 2.5 project is still unfinished, affecting people's travel and daily life.

Relocating many trees to open the central road of Hanoi to 21m

HỮU CHÁNH |

Hanoi - The authorities have relocated many trees to implement the construction of the 720m-long Nguyen Tuan Street expansion, with an investment capital of nearly 400 billion VND.