1,300 billion VND road in Hanoi reaches 95% of volume and then "shelved"

HỮU CHÁNH |

Hanoi - 95% of the work has been completed and the construction site has been received, but the 2.1km beltway section, with a capital of 1,300 billion VND, still has no completion date.

Beltway 2.5 (Dam Hong - National Highway 1 section) is a project approved by Hanoi People's Committee in 2002, with site clearance decided in 2010. The project is invested in the form of BT contract.

The project is about 2.1km long, designed to be 40m wide, with a 7.5m wide sidewalk. The total investment is about 1,300 billion VND.

After 14 years of implementation, by the end of 2023, Hoang Mai district authorities will have completed site clearance for the last 14 households within the project scope.

However, after that, the construction site remained motionless as it had been for many years and there was no sign of construction even though 95% of the volume had been completed.

Every time the project to build the road in front of his house is mentioned, Mr. Nguyen Hoang Minh (Dinh Cong ward, Hoang Mai) shakes his head in disappointment, "I don't understand how people do business that it takes so long to build."

"We cannot be satisfied when the construction of a key project is delayed for more than 10 years. I hope the government will soon have a definitive solution," said Mr. Minh.

The representative of the investor, Hoang Ha Construction Company Limited, said that, up to now, the site clearance work has been basically completed. The project has favorable conditions to implement construction and complete the remaining part.

However, investors are still waiting for the Hanoi People's Committee to extend the BT contract implementation period.

"If the problem is resolved soon, the investor commits to arranging sufficient capital to carry out the project's work according to regulations. It is expected that the project will be completed in a few months and handed over to the city," said the investor's representative.

Previously, in March 2023, the Hanoi Traffic Construction Investment Project Management Board sent Document No. 494 to the Hanoi People's Committee regarding the temporary extension of the contract.

By May 2023, the Department of Transport also issued Document No. 472 proposing the Hanoi People's Committee to approve the policy of temporarily allowing the signing of an appendix to the BT contract to ensure continuity and legality, creating a basis for the investor to complete the project. However, to date, Hanoi has not completed this procedure.

a
The starting point of the project is at Dam Hong. According to the plan, the route will continue to be invested in connecting to Nguyen Trai Street. Photo: Huu Chanh
a
At the end of the route, the Kim Dong - Giai Phong underpass is under construction. However, this underpass can only be used when the Ring Road 2.5 connects to it. Photo: Huu Chanh
Du an ngung tre nhieu nam do vuong giai phong mat bang tai 14 can nha giap song Lu.
The entire route is currently in a state of unfinished development. Photo: Huu Chanh
Cuoi nam 2023, nguoi dan da chap nhan ban giao mat bang va thao do cong trinh. Anh: Huu Chanh
The project has been stalled for many years due to problems with site clearance at 14 houses adjacent to the Lu River. At the end of 2023, residents agreed to hand over the site and dismantle the project. Photo: Huu Chanh
a
The unfinished bridge over the Lu River still has its iron frame exposed, covered with thick moss. Photo: Huu Chanh
a
People in this area have to travel through potholes that often collect water when it rains. Photo: Huu Chanh
a
Garbage and machinery are piled up at the project site. Photo: Huu Chanh
Hang ngay cac phuong tien qua lai trong tinh trang bat nhao vi khong co phuong an to chuc giao thong. Anh: Huu Chanh
Every day, vehicles passing by are in a chaotic state because there is no traffic organization plan. Photo: Huu Chanh
Doan duong tro thanh bai do xe, nhech nhac va mat my quan. Anh: Huu Chanh
The road has become a parking lot, dirty and unsightly. Photo: Huu Chanh
a
Machines are "shelved", no date set for start-up. Photo: Huu Chanh
a
Box culverts are scattered in the Dam Hong area - the starting point of the project. Photo: Huu Chanh
a
Many electric wires and poles are tangled and hanging down the road. Photo: Huu Chanh
Hien nha dau tu dang cho UBND TP Ha Noi gia han hop dong BT de trien khai thi cong hoan thien du an. Anh: Huu Chanh
The investor is waiting for the Hanoi People's Committee to extend the BT contract to complete the project. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Đường 1.200 tỉ nổi tiếng làm lâu ở Long Biên sắp hoàn thành

HỮU CHÁNH |

Hà Nội - Dự án đường nối Nguyễn Văn Cừ - Ngọc Thụy đang gấp rút hoàn thiện các hạng mục cuối, dự kiến khánh thành dịp 70 năm Giải phóng Thủ đô (10.10).

Đường rộng 40m nối hai quận Hà Nội trước tháng thông xe

HỮU CHÁNH |

Hà Nội - Dự án đường Lê Quang Đạo kéo dài nối quận Nam Từ Liêm với Hà Đông sắp hoàn thành, dự kiến thông xe kỹ thuật ngày 10.10 sau gần 2 năm thi công.

Mong chờ dự án mở đường rộng 80m, vốn gần 19.000 tỉ đồng ở Hà Nội

HỮU CHÁNH |

Người Hà Nội mong dự án mở rộng Quốc lộ 21 sớm được phê duyệt chủ trương đầu tư và triển khai thi công để giải quyết tình trạng ùn tắc, tai nạn giao thông.

Xe tải bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết

Duy Tuấn |

Bình Thuận - Xe tải đang lưu thông thì bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết.

Tin 20h: Yên Bái kiểm tra nhà hàng "chặt chém" đoàn từ thiện

Nhóm PV |

Tin 20h ngày 19.9: Bà Nguyễn Phương Hằng được ra tù vào hôm nay; Yên Bái kiểm tra nhà hàng bị tố chặt chém đoàn từ thiện...

Phía Miss Universe nói về thông tin Kỳ Duyên chưa tốt nghiệp

Huyền Chi |

Thông tin Hoa hậu Kỳ Duyên chưa tốt nghiệp Trường Đại học Ngoại Thương gây xôn xao mạng xã hội.

Thể Công Tân Cảng bảo vệ thành công chức vô địch giải bóng chuyền U23 Quốc gia 2024

Nhóm PV |

U23 Thể Công Tân Cảng thắng U23 Ninh Bình 3-1 tại chung kết giải bóng chuyền U23 quốc gia vào tối 19.9.

Chậu hoa giấy trên phố đi bộ ở Đà Nẵng đồng loạt "nằm" tránh bão

Nguyễn Linh |

UBND quận Hải Châu, TP Đà Nẵng cho biết đã chủ động đặt nằm các chậu hoa giấy tại phố đi bộ Bạch Đằng để tránh thiệt hại bởi ảnh hưởng của cơn bão số 4.

The famous 1,200 billion VND road in Long Bien is about to be completed

HỮU CHÁNH |

Hanoi - The Nguyen Van Cu - Ngoc Thuy connecting road project is urgently completing the final items, expected to be inaugurated on the occasion of the 70th anniversary of the Liberation of the Capital (October 10).

40m wide road connecting two districts of Hanoi before opening month

HỮU CHÁNH |

Hanoi - The Le Quang Dao extended road project connecting Nam Tu Liem district with Ha Dong is nearing completion, expected to open to technical traffic on October 10 after nearly 2 years of construction.

Looking forward to the project of opening an 80m wide road with a capital of nearly 19,000 billion VND in Hanoi

HỮU CHÁNH |

Hanoians hope that the National Highway 21 expansion project will soon be approved for investment and construction to resolve traffic congestion and accidents .