Tam Trinh Street after half a year of expansion

HỮU CHÁNH |

Hanoi - The site is still "oo dau" which makes it impossible for the contractor to synchronously construct the Tam Trinh road expansion project, with a capital of nearly VND3,400 billion.

The Tam Trinh road expansion project (Hoang Mai district, Hanoi) is 3.5km long, starting at Minh Khai intersection and ending at Ring Road 3 intersection, with a total investment of nearly VND3,400 billion.

The project started in 2016 and is expected to be completed after 3 years. However, due to many difficulties in site clearance, the project has stalled.

In August 2024, Hoang Mai district handed over about 800m of clean land to the contractor to implement the expansion of Tam Trinh road after many years of delay.

According to the representative of the contractor of Truong Son 97 branch (Truong Son Construction Corporation), the Tam Trinh road expansion project is divided into 2 construction phases.

Phase 1 will be constructed on the left side of the route in sections with available land. Phase 2 will construct the existing part of Tam Trinh Street.

The contractor's representative said that after the investor handed over part of the site, from the beginning of August 2024, the contractor began construction in the form of rolling.

After half a year of construction, the entire retaining wall on the Kim Nguu River has been basically completed.

Contractors are mobilizing many machines and personnel to focus on constructing items such as burying drainage systems, digging and filling roadbeds, spreading crushed stone, and treating weak soil at locations with clean land.

According to the contractor's representative, the construction period of this project is 650 days, from July 31, 2024, the unit is determined to closely follow the progress. However, the assigned site is still "steady and not seamless, so the efficiency of machinery and equipment has not been maximized.

According to the People's Committee of Hoang Mai District, the total land acquisition area (after adjusting the boundary) is about 54,009m2, involving about 1,590 households and 20 organizations, located in the 3 wards of Mai Dong, Hoang Van Thu and Yen So.

Hoang Mai District has set a goal of basically completing site clearance and handing over the maximum amount of clean land by the end of 2024 so that the contractor is qualified to construct continuously, without interruption.

However, up to now, the locality has not yet handed over enough land to the contractor. This delay risks affecting the project's progress, which is to be completed in 2026.

Doan dang duoc nha thau trien khai thi cong tu cau qua song Kim Nguu den ngo 587 Tam Trinh.
The section from the bridge over the Kim Nguu River to alley 587 Tam Trinh, about 350m long, is being expanded by the contractor. Photo: Huu Chanh
Doan nay hien da co mat bang sach, dang duoc mo rong mat cat ngang len 40m. Anh: Huu Chanh
This section is being widened to 40m. Photo: Huu Chanh
May moc duoc huy dong thi cong he thong cong thoat nuoc. Anh: Huu Chanh
Machines and workers are mobilized to construct the underground drainage system. Photo: Huu Chanh
Hang muc bo ke song Kim Nguu
The Kim Nguu river embankment project has been basically completed. Photo: Huu Chanh
Mot so doan via he doc song Kim Nguu
In the photo is the sidewalk along the Kim Nguu River. Photo: Huu Chanh
Nhieu doan mat bang ban giao xoi do.
The handover of the site at many times only reaches 40m/section while for effective construction, cost optimization, the continuous length of the site needs to be over 100m. Photo: Huu Chanh
a
The section in front of the HC supermarket has a clean site but there are no construction activities. Photo: Huu Chanh
a
Many houses on the route have not yet been cleared and handed over the site to the contractor. Photo: Huu Chanh
Tam Trinh la tuyen duong trong yeu tren dia ban quan Hoang Mai, luu luong nguoi va phuong tien tham gia giao thong lon, dieu nay khien nha thau vua thi cong vua phai bao dam giao thong. Anh: Huu Chanh
Tam Trinh is an important route in Hoang Mai district, with a large volume of people and vehicles participating in traffic, which makes it necessary for the contractor to both construct and ensure traffic. Photo: Huu Chanh
Theo ke hoach, du an mo rong duong Tam Trinh se hoan thanh trong nam 2026. Anh: Huu Chanh
According to the plan, the Tam Trinh road expansion project will be completed in 2026. Photo: Huu Chanh
a
After being expanded, the road will have a cross-section of about 40m, meeting 6 lanes, helping to reduce traffic congestion on the southern gateway routes, contributing to the socio-economic development of Hoang Mai district in particular and Hanoi capital in general. Photo: Huu Chanh

HỮU CHÁNH
TIN LIÊN QUAN

The appearance of an important route in Hanoi after 2 years of construction

|

Hanoi - After 2 years of construction, Le Quang Dao Street has reached 90% of the progress and is on the "sprint" to complete the entire route in May.

23h still seriously congested in Khuat Duy Tien intersection

|

Hanoi - The situation of congestion at Nguyen Trai - Khuat Duy Tien node has no signs of cooling down. At 23:00, people still suffer when moving through this area.

Hour 9: I am the third person - Part 2

|

Hour 9 - The husband in the story has developed feelings for his wife's best friend. Where will this marriage go?

Mobilizing resources to treat accident victims on National Highway 6

|

The accident on National Highway 6, Sup Vat commune, Yen Chau district, Son La province caused many casualties and heavy casualties were transferred to the upper level.

Ho Chi Minh City University of Education has many violations in the 17.42 billion VND project

|

The Inspectorate of the Ministry of Education and Training concluded that Ho Chi Minh City University of Education has limitations, shortcomings, and violations related to the project with an investment of 17.42 billion VND.

Man United escaped defeat against Everton

|

Everton drew 2-2 with Man United in the match of round 26 of the Premier League on the evening of February 22 (Vietnam time).

making a living on landfills

|

Soc Trang - The landfill is a home, the only source of life for dozens of households.

Intersection in Hanoi before proposal to build underpass worth over VND1,400 billion

|

Hanoi - The Hoang Quoc Viet extended underpass - Ring Road 3 is proposed to be built 600m long, with an investment capital of more than VND1,400 billion to help reduce congestion and increase connectivity.

Ì ạch thi công mở rộng đường Nguyễn Tuân, Hà Nội

HỮU CHÁNH |

Hà Nội - Hoạt động thi công diễn ra ì ạch trên công trường mở rộng đường Nguyễn Tuân dù mặt bằng đã được bàn giao cách đây gần 3 tháng.

The appearance of an important route in Hanoi after 2 years of construction

HỮU CHÁNH |

Hanoi - After 2 years of construction, Le Quang Dao Street has reached 90% of the progress and is on the "sprint" to complete the entire route in May.

23h still seriously congested in Khuat Duy Tien intersection

HỮU CHÁNH |

Hanoi - The situation of congestion at Nguyen Trai - Khuat Duy Tien node has no signs of cooling down. At 23:00, people still suffer when moving through this area.