Businesses call hard
Mr. Nguyen Van Vuong - General Director of Thanh Phu One Member Limited Company (Vinh Lac hamlet, Vinh Thinh commune, Hoa Binh district, Bac Lieu) - repeatedly reflected the transportation difficult because the road has not been clear.
Besides, the inter -district roads banned the load, making it difficult for aquatic transport vehicles. To transport to the seaport location, businesses must use low -load vehicles then switch to other cars quite expensive.

Most of the seafood processing enterprises in Ganh Hao town (Dong Hai district) are difficult to transport through the road leading to Tran Van early Bridge (Gia Rai town). The reason, this road has not been completed for many years, the upgrade and extended expansion makes the circulation not favorable. Driver Nguyen Van Quan shared: “This road is less than 5 km but we travel 30 minutes, due to too many potholes and elephants. We hope the road to work as soon as possible. ”
Ninh Quoi - Ngan Dua Street has been started for a long time, expected to be completed since 2023, but until now there are still many disordered. This greatly affects the circulation of goods. Meanwhile, many inter -commune roads in Hong Dan district, after the landslide has not been overcome, makes people's travel difficult.
Many traffic projects have not yet been cleared
Typically, the project of building and upgrading Ninh Quoi - Ngan Dua route. The project is invested by the Construction Project Management Board of Bac Lieu Transport works. The total line length is about 10.9km, through Ninh Quoi A, Ninh Hoa and Loc Ninh communes of Hong Dan district.
The scale of level IV of Delta, design speed of 60km/h; The width of the road surface is 7m, the width of the road is 9m, the high -class road surface A1, the construction of the drainage system and the synchronous auxiliary works.
The project includes 8 reinforced concrete bridges and permanent reinforced concrete; Building bridges on the route with HL93 load.

The construction time began in 2019 and the end of 2023. The total project investment is over VND 271 billion. However, up to now, the project has not been completed because in the construction process, it has affected the property of the people. Therefore, households also require support, overcome property, and have not yet delivered the ground.
For the road leading to Tran Van Dong Bridge, according to the Management Board of the Construction Investment Project of Gia Rai Town, the project was approved by the People's Committee of Bac Lieu Province in Decision No. 2415/QD-UBND dated December 26, 2023 with The total investment is nearly 56 billion dong. The project is invested by the People's Committee of Gia Rai Town, the construction contractor is the Nguyen Nam joint venture. Project construction location is located in Ward 1, Gia Rai Town.
The project has a length of 1,870m (the starting point at the garges of Tran Van early bridge; the end of the building at km 1+870 snake canal rotation, adjacent to the territory of Dong Hai district). The design of the design is a level III of the delta, the load of 10 tons, the design speed of 80km/h, the width of the road surface of the motor vehicle is 7m, the width of the road is 14m, the width of the reinforcement is 2m on each side.
In addition, there are also auxiliary works such as: piles, households, signs, and road surface paints that are designed to ensure traffic safety according to national technical regulations.
Project on construction and upgrading of the East Sea dike urgently against climate change in Bac Lieu province - section from canal 1 to canal of shelf phase 2 by the Management Board of Investment Project Construction of agricultural works and distribution Rural development as an investor.
The project is implemented in Hoa Binh district and Dong Hai district, Bac Lieu province, with the total investment of phase 2 is more than VND 288 billion. The project implementation period is 3 years (from 2021 - 2023), put into operation at the end of December 2023. However, in 2025, the project has not been completed.
Facing this situation, Bac Lieu President Pham Van Thieu asked the investor to urgently review the transport projects; coordinate with the locality to remove difficulties, hand over the ground to the contractor. President Bac Lieu emphasized: Traffic is for people to go, create conditions for transporting goods and traveling, slowing down, causing trouble for the people is difficult to accept.