From March 15, Hanoi Department of Construction adjusted traffic organization on Nguyen Phan Chanh street to serve the construction of the project "Renovation of downstream Kim Nguu route connecting To Lich River with Yen So Pumping Station".
According to the traffic organization plan, the construction is divided into 3 phases.
In phase 1, the contractor is constructing along Nguyen Phan Chanh street (section between Bang Liet street - Nguyen Huu Tho street). The project is fenced off into 5 sections, the average length of each section is about 65m; the width of the fence is 6.2m, and the remaining road surface is about 5m.
The contractor organizes rolling construction of each segment, returning the asphalt concrete layer before moving to constructing the next segment. At intersections and entrances to agencies, construction units within 1/2 of the road cross-section.
During this period, cars are organized to circulate in one direction on Nguyen Phan Chanh street in the direction from Bac Linh Dam bridge to Nguyen Huu Tho street.
Phase 2, construction at the Nguyen Phan Chanh - Bang Liet intersection. The contractor divides into 2 sections, each section is constructed within 1/2 of the road cross-section and continues to be constructed in a rolling manner, restoring the road surface before moving to the next section.
On Bang Liet street, cars are prohibited from going straight through the Cau Dau intersection.
Phase 3 continues construction at the Nguyen Phan Chanh - Bang Liet intersection with 3 sections, each section occupying 1/3 of the road cross-section.
For section 2 (corrugated iron fence in the middle of the intersection), cars are allowed to circulate in both directions on Nguyen Phan Chanh street, and it is also forbidden for cars from Nguyen Huu Tho street to go straight through the intersection in the direction of Ring Road 3.
For section 3 (corrugated iron fence on the park side), it is forbidden for cars from Nguyen Phan Chanh street to turn right onto Nguyen Huu Tho street.
The contractor continues to construct step by step, restoring the asphalt concrete layer before deploying the next items.
Time to adjust traffic organization from March 15 to April 30, 2026. In which, phase 1 from March 15 to April 12; phase 2 from April 5 to April 13; phase 3 from April 13 to April 29.