Progress of nearly 113km route through 3 northern provinces and cities

HỮU CHÁNH |

62 construction sites were simultaneously deployed by contractors, speeding up the progress of the nearly 113km long route, passing through 3 northern provinces and cities.

Regarding the implementation of the Ring Road 4 project in the Capital Region, the Hanoi Traffic Construction Investment Project Management Board said that by the end of October 2024, Hanoi had approved and recovered 98.15% of the land area, completed all 13 resettlement areas and arranged resettlement for 337/818 households.

Hanoi strives to complete site clearance in 2024 and complete the relocation of underground and above-ground technical infrastructure items in the fourth quarter of 2024.

Regarding the progress of component project 2.1, 4 construction packages have been simultaneously deployed by contractors on the handed over land area with 32 construction points (23 road points, 9 bridge points).

The contractor is handling the weak ground, constructing the bridge and the semi-hollow asphalt concrete pavement. The output to date has reached about 36.86%. The parallel road section through Hanoi is expected to be completed in the fourth quarter of 2025.

Duong song hanh Vanh dai 4 doan qua xa Kim Hoa, Me Linh da duoc tham nhua. Anh: Huu Chanh
A section of the parallel road of Ring Road 4 through Kim Hoa commune (Me Linh, Hanoi) has been paved with asphalt. Photo: Huu Chanh

Regarding the progress of the Beltway 4 project through Hung Yen, the locality has reclaimed land and handed over 95.1% of the site, and moved 99.3% of the graves.

Hung Yen has also completed 7/11 resettlement areas, striving to complete the remaining 4 resettlement areas, and hand over resettlement land to households before November 20, 2024.

Component project 2.2 has organized 8 construction teams. Construction output reached about 21.57% of contract value and 95% of approved progress.

In Bac Ninh, the site clearance work has reached 97.28%. However, the locality has only completed 2/11 resettlement areas, striving to basically complete and organize resettlement for affected households in the first quarter of 2025.

Component project 2.3 has 22 construction sites. The construction output of 3 packages is about 9% of the planned value.

Vanh dai 4 qua Ha Noi, Hung Yen va Bac Ninh dai gan 113km. Anh: UBND TP Ha Noi
Ring Road 4 of the Capital Region is nearly 113km long, passing through Hanoi (58km), Hung Yen (19.3km), Bac Ninh (36.2km). Photo: Hanoi People's Committee

The 4th Ring Road of the Capital Region is implemented through 7 component projects, operating independently. Of which, Hanoi implements 3 component projects: Compensation, support, and resettlement; Construction of parallel roads (urban roads) in Hanoi and investment in the construction of the expressway system under the PPP method.

Hung Yen and Bac Ninh provinces are each responsible for two component projects: Compensation, support, resettlement and construction of parallel roads (urban roads) in each province's territory.

The project has a total investment of over VND85,813 billion, of which the Ring Road 4 expressway is invested in the form of PPP with an investment of VND56,500 billion.

Construction started in June 2023, with the parallel road scheduled to be completed in 2026 and the expressway scheduled to be completed in 2027.

When completed, the project will contribute to relieving traffic congestion, connecting provinces and creating new development space for the entire capital region, including Hanoi, Hung Yen and Bac Ninh.

HỮU CHÁNH
TIN LIÊN QUAN

Complete 58km, 6-lane road through Hanoi by 2025

|

Hanoi aims to complete the 58km, 6-lane parallel road to Ring Road 4 in the fourth quarter of 2025.

Road worth over 6,000 billion VND, 6 lanes under construction in Hanoi

|

Hanoi - The Southern Axis Road Project (Phase 2) is over 20km long through Phu Xuyen and Ung Hoa districts and is being deployed for site clearance and construction.

6-lane road connecting 2 districts in Hanoi scheduled to be completed by the end of 2024

|

The 2.6 km long road connecting two districts in Hanoi with an investment capital of more than 700 billion VND missed the scheduled opening date of October 10 and is expected to be completed by the end of 2024.

20h News: Areas in Hanoi are about to ban gasoline vehicles from 2026

|

20h News: Where is Hanoi's Ring Road 1 about to ban gasoline vehicles, including which streets; The problem of printing shops in Lao Cai is worth billions of dong, some units have paid off debts...

1 year of the failed assassination of Mr. Trump, exposing the errors of the US Secret Service

|

A year after the failed assassination attempt on Mr Trump in Pennsylvania, the federal investigation report has just revealed a series of serious errors by the US Secret Service.

Current status of Hanoi Ring Road 1 will ban gasoline vehicles from July 2026

|

Hanoi is about to ban gasoline motorbikes from traveling on Ring Road 1, including the Hoang Cau - Voi Phuc section, the road considered "the most expensive on the planet".

A series of houses in the center of Ho Chi Minh City are still blocked by signs and billboards

|

HCMC - Many houses in the center, where there are many people, have signs and roofs covering all floors, posing a potential risk of obstructing rescue if there is a fire or explosion.

Complete 58km, 6-lane road through Hanoi by 2025

HỮU CHÁNH |

Hanoi aims to complete the 58km, 6-lane parallel road to Ring Road 4 in the fourth quarter of 2025.

Road worth over 6,000 billion VND, 6 lanes under construction in Hanoi

HỮU CHÁNH |

Hanoi - The Southern Axis Road Project (Phase 2) is over 20km long through Phu Xuyen and Ung Hoa districts and is being deployed for site clearance and construction.

6-lane road connecting 2 districts in Hanoi scheduled to be completed by the end of 2024

Hữu Chánh |

The 2.6 km long road connecting two districts in Hanoi with an investment capital of more than 700 billion VND missed the scheduled opening date of October 10 and is expected to be completed by the end of 2024.