Hanoi diverts traffic to install a pedestrian bridge on Xuan Thuy Street

Minh Hạnh |

The Hanoi Department of Construction has just announced a traffic diversion plan for construction, relocation and installation of a pedestrian bridge on Xuan Thuy Street.

According to the agreed plan between the sectors, the construction will be divided into 3 sections, applying measures to block roads, narrow lanes and organize traffic guidance to ensure safety for people and vehicles.

Section 1: From December 12 to 14 (23am - 5am), vehicles are prohibited from traveling on Xuan Thuy Street in both directions at the sections from Xuan Thuy - Pham Hung intersection to Lane 181 Xuan Thuy; and from Phan Van Truong - Xuan Thuy intersection to Xuan Thuy - Pham Hung. The limitation is to serve the dismantling and relocation of the existing pedestrian bridge structure. The Department of Construction requires the installation of a full system of signs, warning lights and the arrangement of traffic flow forces at both ends of the construction site.

Phase 2: From December 11 to 21, the contractor will construct the bridge foundation at gate No. 2 of Hanoi National University of Education. Part of Xuan Thuy Street in both directions will be narrowed by 3.5m, with a barrier range of about 15m long, keeping 7m of the road surface for vehicles to circulate. Road narrowing signs, night warning lights and regulators are maintained continuously.

Section 3: From December 24 to 27 (23h - 5am), the installation of pedestrian bridge girders will require prohibiting vehicles from passing through many sections on Xuan Thuy Street, especially from Xuan Thuy intersection - Lane 181 to Xuan Thuy - Tran Quoc Vuong; and from Phan Van Truong to Pham Hung. The authorities also arranged remote signs at locations such as Xuan Thuy - Pham Hung, Xuan Thuy - Cau Giay, Tran Quoc Vuong - Xuan Thuy... for vehicles to proactively choose the direction of travel.

The Department of Construction assigned specialized units to closely monitor the traffic situation and promptly adjust the plan in case of congestion. The Traffic Police Department - Hanoi City Police will organize remote traffic guidance and handle violations at the construction area.

The People's Committee and the Cau Giay Ward Police are requested to widely notify the people and coordinate to guide the vehicles throughout the construction period. The contractor is responsible for arranging forces to be on duty, installing a complete traffic safety system, and being responsible for any unsafe incidents, congestion or damage to infrastructure during the project implementation.

Minh Hạnh
RELATED NEWS

Banning Ring Road 1 motorbikes: Deputy Director of Hanoi Department of Construction talks about support levels for people

|

To make people and businesses feel secure in converting to green vehicles, Hanoi is studying and implementing a comprehensive support policy system.

Director of Hanoi Department of Construction: Drainage sector shows many shortcomings

|

The Director of the Hanoi Department of Construction said that the new administrative boundary has caused a lack of synchronization in management with a series of shortcomings in drainage areas.

Da Nang Department of Construction responds to the proposal to install a pedestrian bridge across Nguyen Huu Tho Street

|

Da Nang - The Department of Construction of Da Nang City has just responded to voters' proposal to install a pedestrian bridge across Nguyen Huu Tho Street.

The pedestrian bridge project across the Saigon River has reached 20% progress after 4 months of construction

|

HCMC - After about 4 months of construction, the pedestrian bridge across the Saigon River has reached 20% of the progress but is slow due to land clearance and technical documents.

sad news

|

Mr. Ngo Duy Son, born in 2013, passed away at 1:45 p.m. on December 10, 2025 (ie October 21, At Ty year), at the age of 93.

The role of the Vietnam Fatherland Front in the market economy and international integration in the current period

|

On December 10, in Hanoi, the Standing Committee of the Central Committee of the Vietnam Fatherland Front organized a scientific workshop on "New factors of market economy and international integration affecting the gathering work, promoting the strength of national solidarity and the role of the Vietnam Fatherland Front in implementing a market economy in our country".

SEA Games 33 Medal Schedule on December 10: Vietnam temporarily ranked 4th

|

Updated the total score for the 33rd SEA Games medal table after the end of the competition on December 10.

Image processing process of AI cameras is about to spread in Hanoi

|

Hanoi - The City Police are about to put into operation more than 1,800 AI cameras, installed at nearly 200 intersections in the area.

Banning Ring Road 1 motorbikes: Deputy Director of Hanoi Department of Construction talks about support levels for people

Anh Tuấn - Sóng Hữu |

To make people and businesses feel secure in converting to green vehicles, Hanoi is studying and implementing a comprehensive support policy system.

Director of Hanoi Department of Construction: Drainage sector shows many shortcomings

Anh Tuấn |

The Director of the Hanoi Department of Construction said that the new administrative boundary has caused a lack of synchronization in management with a series of shortcomings in drainage areas.

Da Nang Department of Construction responds to the proposal to install a pedestrian bridge across Nguyen Huu Tho Street

Thu Giang |

Da Nang - The Department of Construction of Da Nang City has just responded to voters' proposal to install a pedestrian bridge across Nguyen Huu Tho Street.

The pedestrian bridge project across the Saigon River has reached 20% progress after 4 months of construction

Anh Tú |

HCMC - After about 4 months of construction, the pedestrian bridge across the Saigon River has reached 20% of the progress but is slow due to land clearance and technical documents.